Energy insights
Energy Procurement Glossary
Plain definitions of the terms in your contracts, bills and tenders. Written from the rules and the regulators. Where a term has no regulated definition, we say so.
A
The Australian accounting standard setting out climate-related disclosure requirements, including disclosure of greenhouse gas emissions. Issued by the Australian Accounting Standards Board in September 2024, it applies to annual reporting periods beginning on or after 1 January 2025, with entry phased by entity size and emissions under the Corporations Act.
Why it matters
Where an entity is in scope, its reported scope 2 emissions depend on which electricity it buys and what certificates it holds, which makes contracting and certificate decisions a reporting input rather than a side matter.
Source: AASB, AASB S2 Climate-related Disclosures
ACCCThe common abbreviation for the Australian Competition and Consumer Commission. See Australian Competition and Consumer Commission →
The AER-approved instrument setting the terms on which a gas pipeline service provider sells pipeline services on a scheme pipeline. It must describe all the pipeline services the provider can reasonably provide on the pipeline, specify which of them are reference services, and specify for each reference service the reference tariff and the other terms and conditions on which it will be provided, together with capacity trading, extension and expansion requirements and the dates for its review and revision.
Note: Gas networks are regulated through access arrangements, while electricity distribution networks are regulated through distribution determinations and tariff structure statements. A pipeline that is not a scheme pipeline has no access arrangement.
Why it matters
The gas network charges reaching a site are set in the access arrangement for the pipeline serving it, approved for a period of years and published on the AER's register, so the network component of a gas bill traces to a public instrument rather than to the retailer that invoices it.
Source: National Gas Rules, rule 48, current rules; AER, register of access arrangements
In general procurement, a supplier assessed against published criteria by a scheme owner or buyer and admitted to the group permitted to supply. In Australian energy the term has a statutory counterpart in the energy efficiency certificate schemes: an accredited person under the Victorian Energy Upgrades program, accredited by the Essential Services Commission under the Victorian Energy Efficiency Target Act 2007, and an accredited certificate provider under the New South Wales Energy Savings Scheme, accredited by IPART under Schedule 4A of the Electricity Supply Act 1995.
Note: No accreditation regime of this kind applies to energy brokers, consultants or strategists. Accreditation in the certificate schemes permits the creation of certificates, not the arranging of supply contracts.
Why it matters
Accreditation is specific to the scheme that granted it, so a provider accredited under one certificate scheme is not accredited under another, and admission to a buyer's own panel is a separate decision against that buyer's criteria.
See also
Source: Essential Services Commission, VEU application guide for accredited persons; IPART, application for accreditation guide for ACPs
ACCUThe common abbreviation for Australian carbon credit unit. See Australian carbon credit unit →
A meter that measures only total electricity use between meter readings and does not record the dates and times when the consumption occurred. AEMO's retail market glossary also calls it a basic meter. The matching classification in the Rules is a type 6 metering installation.
Why it matters
An accumulation meter yields one total per read, so demand, time-of-use and interval analysis cannot be done on its data at all, whatever the billing arrangement.
Source: AEMO, Retail Electricity Market Procedures - Glossary and Framework
ACQThe common abbreviation for annual contract quantity. See Annual contract quantity →
The working electrical energy a site consumes, defined as the time integral of the product of voltage and the in-phase component of current flow across a connection point, expressed in watt hours. Active power is the rate at which it is transferred, measured in watts. This is the quantity billed as kilowatt hours.
Why it matters
It is one of three quantities a large site's meter records, alongside the reactive and apparent channels, and the only one a consumption charge is calculated from. A demand charge billed in kilovolt-amperes is not derived from it, so consumption and billed demand can move in opposite directions.
Source: National Electricity Rules, Chapter 10 (glossary), definitions of active energy and active power, current rules
A quantity of energy for a billing period taken from a reading of the meter, rather than estimated or substituted.
Why it matters
The read dates set the boundaries of the period billed, so consecutive bills based on actual reads can cover periods of different lengths and are not directly comparable one to the next.
Source: National Energy Retail Rules, rules 20 and 21, current rules
ADGSMThe common abbreviation for the Australian Domestic Gas Security Mechanism. See Australian Domestic Gas Security Mechanism →
The ceiling AEMO applies to a region's spot prices and market ancillary service prices during an administered price period. The National Electricity Rules set it at $600 per MWh for each region, and set the administered floor price, which applies to spot prices only, at the negative of that figure.
Current status: The $600 per MWh level replaced $300 per MWh from 1 December 2022, and under an AEMC final rule determination of 7 December 2023 is maintained for the period 1 July 2025 to 30 June 2028.
Why it matters
For the intervals it covers, a buyer on a pass-through or spot-linked contract pays no more than the capped price for wholesale energy, while a buyer on a fixed rate sees no change, because the retailer carried that exposure when it priced the contract.
Source: AEMO, Guide to Administered Pricing
A period AEMO declares for a region once the sum of that region's spot prices, or of its prices for a market ancillary service, over the previous 2,016 trading intervals exceeds the cumulative price threshold. During it the administered price cap and administered floor price limit published prices, while dispatch, price determination and PASA otherwise continue under the Rules. It runs to at least 0400 hours and ends only when the seven-day cumulative price, recalculated as if no capping had applied, no longer exceeds the threshold.
Note: It is assessed separately for each region and for each market, energy and ancillary services. Where a regulated interconnector carries power towards a capped region, prices in the exporting region are capped at the importing region's administered price divided by the average inter-regional loss factor, so a region can be collared without having breached the threshold itself.
Why it matters
A business with sites in two states can have one region capped and the other not, so a single national wholesale figure does not describe what either site was exposed to during the event.
Source: AEMO, Guide to Administered Pricing
AEMCThe common abbreviation for the Australian Energy Market Commission. See Australian Energy Market Commission →
The Australian Energy Market Operator. It operates the National Electricity Market and the gas markets, administers metering and settlement systems, and publishes planning and reliability forecasts.
Why it matters
Because AEMO administers the metering and settlement systems, the standing data behind a connection point sits in its registry rather than with the retailer, which is why a NMI and its metering details survive a change of retailer. AEMO does not set retail prices or approve network tariffs.
Source: aemo.com.au
The Australian Energy Regulator. It regulates retail energy markets in New South Wales, Queensland, South Australia, Tasmania and the Australian Capital Territory, approves network revenue and tariff structures, and sets the Default Market Offer. It does not regulate retail markets in Victoria, Western Australia or the Northern Territory.
Why it matters
A portfolio spread across states is not answerable to one retail regulator, because Victoria, Western Australia and the Northern Territory sit outside the AER's retail role. The price caps and retail protections the AER sets stop at those borders, where separate bodies apply their own.
Source: AER, other retail roles
Industry usage
The combined consumption of several sites, used to state a buyer's total volume when it goes to market, or to compare one period with another across a portfolio.
Note: This is not aggregation in the regulatory sense. Aggregation under the National Energy Retail Rules is the act of treating two or more of a business customer's premises as one for the consumption threshold that separates small from large customers, and it requires a written agreement and the customer's explicit informed consent. Adding sites together in a tender document or a report has no effect on that threshold.
Why it matters
A portfolio total states volume and nothing about where it was used, so sites in different network areas and on different tariffs collapse into one figure that cannot be turned back into a cost without the site-level detail.
Treating two or more of a business customer's premises as one for the purposes of the consumption threshold. It requires a written agreement and the customer's explicit informed consent, and a retailer cannot do it on its own initiative.
Why it matters
Aggregating sites moves them out of the small customer protections, which is a trade a business should make deliberately rather than discover later.
Source: National Energy Retail Rules, rule 5
A distribution service that is a direct control service but not a standard control service. The AER classifies distribution services in a distribution determination, and the classification decides the form of control applying to the charge.
Note: The AER's position is that the classification is likely to apply where the cost of a service is directly attributable to an individual customer's connection to the network, and chapter 6 gives the example of a service provided to a small number of identifiable customers on a discretionary or infrequent basis. Connection and metering services are commonly classified this way.
Why it matters
The charge is recovered from the customer whose connection caused the cost rather than spread across a tariff class, so it arrives as a separate fee and does not move when the site's consumption or demand changes.
Source: National Electricity Rules, chapter 10 (glossary) and clause 6.2.2, current rules; AER, connection charge guidelines for electricity customers, April 2023
Industry usage
The total volume of gas a buyer is entitled to take, and commonly commits to take, over a contract year under a gas supply agreement. It is usually stated in terajoules or petajoules, and minimum and maximum annual takes are expressed against it.
Why it matters
The annual figure and the daily entitlement are set separately, so a year's contracted volume can be unused while a particular day's take is already at its limit.
The document a distribution network service provider submits to the AER each year setting its network tariffs for the coming regulatory year. Chapter 6 of the National Electricity Rules requires it to state the proposed tariffs for each tariff class, the charging parameters for each tariff and what elements of service they relate to, the expected weighted average revenue for each tariff class providing standard control services, the nature of any variation that could occur during the year, and how designated pricing proposal charges are passed on.
Note: The proposal has to be consistent with the network's approved tariff structure statement, which fixes the structures for the whole regulatory control period. A pricing proposal sets price levels inside those structures rather than creating new ones.
Why it matters
Network prices for the coming year are proposed, approved and published before the year starts, so the network component a retailer passes through is knowable in advance rather than only in arrears.
Source: National Electricity Rules, clause 6.18.2, current rules
Industry usage
A recurring payment made by an embedded network operator to a site owner or owners corporation under the commercial arrangement.
Why it matters
The payment goes to the owner or the owners corporation, so the party receiving it and the occupants paying for energy at the site are not the same. Its size and duration are set by the deed rather than by any regulated figure.
The combined power flowing at a point, defined as the square root of the sum of the squares of the active power and the reactive power. It is measured in volt-amperes, and at commercial scale in kilovolt-amperes. Power factor is the ratio of active power to apparent power at a metering point.
Why it matters
Network demand charges for larger sites are commonly set on apparent power, so the billed figure takes in the reactive component that does no work at the site. Two sites drawing identical active power are billed different demand if their reactive power differs.
Source: National Electricity Rules, Chapter 10 (glossary), definitions of apparent power and power factor, current rules
Industry usage
A minimum credit rating the issuer of a guarantee must hold before a retailer will accept that guarantee as security. Agreements state the grade required and usually accept an equivalent rating from another agency of similar standing.
Why it matters
It narrows which institutions and which group entities can provide the security, so a buyer whose bank or parent sits below the stated grade has to find another provider or lodge cash instead.
The Australian Standard specifying general purpose natural gas, setting limits on the composition and energy properties gas must meet. The National Gas Rules adopt it, making the specifications it contains the standard gas quality specifications for the Victorian declared wholesale market and for short term trading market hubs, together with anything added by Commonwealth or State legislation or, at a hub, by the applicable access arrangement.
Current status: The Rules cite the 2005 edition and pick up later versions through the words "as amended or replaced from time to time". Standards Australia has published later editions since, and an individual pipeline's gas specification states which edition it reproduces.
Why it matters
The limits reach a gas buyer through the gas specification the pipeline or network publishes rather than directly, and supply and connection contracts commonly name the standard rather than restate it. Gas outside the applicable specification is off-specification gas, which a facility operator is under no obligation to accept.
Source: National Gas Rules, Part 19, rule 200, and Part 20, rule 364 (standard gas quality specifications), current rules
The Australian and New Zealand standard for energy audits of commercial buildings. It sets minimum requirements for commissioning and conducting three prescribed types of audit, numbered Type 1 to Type 3, and covers all forms of energy used in the building. Parts 2 and 3 of the standard cover industrial and related activities and transport-related activities.
Why it matters
The standard fixes the minimum content of each type, so the type named in a scope of works is what decides how far an audit has to go, and an audit of one type does not meet the requirements set for another.
Source: Standards Australia, AS/NZS 3598.1:2014 Energy audits, Part 1: Commercial buildings
The joint Australian and New Zealand standard titled Grid connection of energy systems via inverters, Part 2: Inverter requirements. It sets the device specifications, functionality, testing and compliance requirements for electrical safety and performance of inverters connecting energy sources or energy storage systems to the grid at low voltage, and covers electric vehicles operating in a vehicle-to-grid mode.
Note: The National Electricity Rules define the DER Technical Standards as the requirements for distribution connected units under AS 4777.2:2020 as in force from time to time, so an amendment to the standard takes effect without a change to the Rules. The 2020 edition was published in December 2020 and carries amendments from 2021 and 2024.
Why it matters
Compliance is a condition of connecting an inverter, so a model that does not meet the edition in force cannot be connected whatever its output rating or price.
See also
Source: Standards Australia, AS/NZS 4777.2:2020; National Electricity Rules, chapter 10 (glossary), definition of DER Technical Standards, current rules
Industry usage
The passing of ownership of embedded network equipment between parties, usually at the end of an agreement and often on payment of a residual value.
Why it matters
Until it happens, the equipment inside the building belongs to the operator rather than to the site, which is what makes the end of an agreement a transaction rather than a stop date.
See also
A Queensland arrangement under which a designated retailer must make a standing offer to large customers at notified prices, under a large customer standard retail contract. No equivalent exists in the other national framework jurisdictions.
Why it matters
It gives a Queensland large customer a notified price available by entitlement rather than by negotiation, which is a position large customers in the other national framework jurisdictions do not have.
See also
Source: National Energy Retail Law (Queensland), sections 64B to 64K
The exchange market on which Australian electricity, gas and environmental derivatives are listed and traded. Electricity futures are listed for the New South Wales, Victoria, Queensland and South Australia regions, are cash settled against those regions' reference prices rather than by physical delivery, and are cleared through the exchange's clearing house.
Why it matters
Settlement prices for the listed contracts are published, so a forward price for a region and a quarter can be read independently of any offer a buyer has been given.
Source: ASX Energy, Australian electricity derivatives
Work to enlarge a transmission or distribution system, or to increase its capacity to transmit or distribute electricity. An extension, being an augmentation that requires connecting a line or facility outside the present boundaries of the network, is treated as a separate case in the connection charge principles.
Why it matters
Whether a connection needs augmentation beyond an extension decides whether the network can seek a contribution towards shared network costs at all, because a retail customer below the threshold in the network's connection policy cannot be required to make one.
See also
Source: National Electricity Law, section 2, as applied in Queensland, current Act; National Electricity Rules, chapter 10 (glossary) and clause 5A.E.1, current rules
A tradeable financial product issued to individuals or businesses running eligible projects that reduce or avoid emissions. Each unit represents one tonne of carbon dioxide equivalent that would otherwise have been released into the atmosphere, and units are issued under the Carbon Credits (Carbon Farming Initiative) Act 2011 by an entry in the Australian National Registry of Emissions Units.
Why it matters
Cancelling units offsets an emissions figure, it does not alter the figure. Measured scope 1 and scope 2 emissions stay as reported, and the offset is a separate step on top.
Source: Clean Energy Regulator, glossary
The national competition and consumer regulator, established under the Competition and Consumer Act 2010 and operating across all industries rather than energy alone. In energy it enforces competition and consumer law, reports on the east coast gas market under a ministerial direction extended to 2030, holds a standing inquiry into prices, profits and margins in the supply of electricity in the National Electricity Market, and monitors and enforces the Gas Market Code.
Why it matters
Its remit runs nationally, including Western Australia and the Northern Territory where the national retail framework does not reach, but it acts on market conduct, pricing and reporting across the industry rather than on an individual customer's contract or bill.
Source: ACCC, gas inquiry 2017-30 reports
A Commonwealth power to restrict liquefied natural gas exports when a domestic gas supply shortfall is forecast, described by the administering department as a measure of last resort. It took effect on 1 July 2017 and operates through Division 6 of the Customs (Prohibited Exports) Regulations 1958 together with the Customs (Prohibited Exports) (Operation of the Australian Domestic Gas Security Mechanism) Guidelines 2023. The Minister for Resources determines whether a shortfall market exists, informed by AEMO, the ACCC, and industry and other government sources.
Current status: The Commonwealth released exposure drafts for a Domestic Gas Reservation Bill 2026 for consultation, which opened on 10 September 2026 and closed on 24 September 2026.
Why it matters
It acts on export permissions rather than on domestic contracts, so an activation changes how much gas is available to the domestic market without altering the price or terms in any supply agreement a buyer holds.
See also
Source: Department of Industry, Science and Resources, domestic gas supply
The rule maker and reviewer for the national energy market, established under the Australian Energy Market Commission Establishment Act 2004 of South Australia and operating since July 2005. It makes and amends the National Electricity Rules, the National Gas Rules and the National Energy Retail Rules, conducts market reviews, and advises energy ministers. Its Reliability Panel reviews the reliability standard and the market price settings and recommends them.
Note: The AEMC makes the rules, the AER enforces them and regulates networks, and AEMO runs the market. The three are separate bodies with separate functions.
Why it matters
A change it makes to the national rules does not reach Western Australia's own market rules or Victoria's retail code, so a portfolio spread across those jurisdictions does not move all at once. It also has no complaints or enforcement role, so nothing about a particular bill is decided here.
Source: AEMC, annual report 2024-25
The two standards the Australian Accounting Standards Board issued in September 2024 to govern sustainability and climate reporting: AASB S1, covering sustainability-related financial information, which entities may elect to apply; and AASB S2, covering climate-related disclosures, which certain entities are required to apply under the Corporations Act 2001.
Current status: AASB S2 is phased in by entity group. Group 1 entities apply it for annual reporting periods beginning on or after 1 January 2025, Group 2 entities for periods beginning on or after 1 July 2026, and Group 3 entities for periods beginning on or after 1 July 2027.
Why it matters
Only AASB S2 carries a legal obligation, so an entity brought into scope must disclose climate-related information while the wider sustainability disclosures in AASB S1 stay a choice it can decline.
See also
Source: AASB, An Overview of Australian Sustainability Reporting Standards
B
BAFOThe common abbreviation for best and final offer. See Best and final offer →
Industry usage
The electricity a retailer supplies in the periods when the contracted generator is not producing enough to cover a site's consumption. It is priced separately from the contracted renewable quantity.
Why it matters
It is the share of the load the renewable quantity does not price, so one arrangement carries two prices and the second applies to however much consumption falls outside the generator's output.
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements
Industry usage
An undertaking by a financial institution to pay a stated amount to the retailer on demand, given in place of cash security. The institution pays first and recovers from the buyer under its own facility terms.
Note: The demand runs against the issuing institution rather than against the buyer, so a call on the guarantee does not require the retailer to establish a breach by the buyer first.
Why it matters
It is issued against the buyer's banking facilities, so the guaranteed amount usually reduces available borrowing for the life of the contract even though no cash leaves the business.
Industry usage
Whether a project's expected revenue is certain enough, and runs for long enough, for lenders to finance it on terms the developer can accept. In energy procurement it usually describes whether a contracted offtake is firm enough and long enough to support debt on new generation or storage.
Why it matters
The buyer's own commitment is part of what lenders assess, so the term and firmness a buyer will accept, and not the price alone, bear on whether a project reaches financial close.
A NABERS rating assessing the energy consumed in supplying a building's central services to office net lettable area and common spaces. Lifts, common area lighting and central heating and cooling sit inside its scope, and energy consumed within a tenancy sits outside it.
Why it matters
Energy a tenant uses in its own space is excluded, so the rating describes how the landlord's services performed and cannot be read as the building's total consumption.
See also
Source: NABERS, The Rules: Energy and Water for Offices, Table 1.1.3
Two ideas combined. A base contract covers every trading interval in the period, which the exchange defines as midnight Monday to midnight Sunday. A strip is four consecutive quarters traded as one line, over a calendar or financial year.
Why it matters
A base contract covers every interval equally, so a site whose consumption concentrates in peak hours is only partly matched by one and the remainder is priced separately. Buying a strip fixes a year in a single line, which fixes the quarters inside it at the blend rather than individually.
See also
Source: AER, State of the energy market, on futures products; ASX, Australian electricity derivatives fact sheet
A connection service for a retail customer's premises where the customer is typical of a significant class of customers who have sought or are likely to seek the service, or is a micro resource operator, where the service involves minimal or no augmentation of the distribution network, and where the AER has approved a model standing offer for providing it on that basis.
Note: A connection service does not include providing, installing or maintaining a metering installation for the premises, so metering at a new connection is arranged separately from the connection itself.
Why it matters
A customer applying for one cannot be required to contribute towards the cost of augmentation beyond an extension, and the network has 10 business days from a properly completed application to make a connection offer in accordance with the approved model standing offer.
See also
Source: National Electricity Rules, clauses 5A.A.1, 5A.E.1 and 5A.F.1, current rules
A meter that records cumulative totals only, so consumption is known for the period between reads and not within it. In electricity it is AEMO's alternate name for an accumulation meter. In gas it is a metering installation with no data logger, whose index is read at the start and at the end of each measurement period.
Note: The gas sense turns on the absence of a data logger rather than on the register type. In the Victorian retail gas market it is also the class of site for which the distribution business, rather than AEMO, converts measured volume into energy.
Why it matters
A basic meter yields one total per read, so no demand or time-of-use figure can be derived from its data. On the gas side the energy billed against it rests on an average heating value across the whole read period rather than on daily values.
Source: AEMO, Retail Electricity Market Procedures - Glossary and Framework; AEMO, Wholesale Market Metering Procedures (Victoria), chapter 3
Industry usage
A system of battery cells, inverters and control equipment that charges from a supply and discharges electricity later. Systems range from a cabinet behind a single customer's meter to grid-scale installations connected at transmission voltage.
Note: In the national electricity market the registration category is different from the commercial label. Following the Australian Energy Market Commission's 2021 rule on integrating energy storage, grid-connected storage is registered as a bidirectional unit operated by an Integrated Resource Provider.
Why it matters
A battery shifts when a site draws energy rather than reducing what it uses, so its value sits in the demand and time-varying parts of a bill, and round-trip losses mean it returns less energy than it took in.
See also
Source: AEMC, Integrating energy storage systems into the National Electricity Market, final determination, 2 December 2021
BEECThe common abbreviation for Building Energy Efficiency Certificate. See Building Energy Efficiency Certificate →
Industry usage
Generation, storage or consumption on the customer's side of the connection point, so the energy does not pass through the revenue meter as a grid import. Solar output consumed on site, and battery charging and discharging within the premises, are behind the meter.
Why it matters
Behind-the-meter energy avoids retail, network and environmental charges on the volumes it displaces, which is why its value to a site differs from the feed-in tariff paid for the same kilowatt hour exported.
Industry usage
Comparing a site's or a portfolio's energy performance against a reference point: the same site in an earlier period, comparable sites, or a published rating or index. In procurement the word is also used for comparing a contract price against the market at a point in time, which is a different exercise using the same name.
Note: In the Australian energy audit standard, benchmarking is a step within data analysis rather than a standalone piece of work.
Why it matters
The result is a function of the reference point chosen, so the same site can compare well against one benchmark and poorly against another, and a price benchmark holds only for the moment it was taken.
Source: Standards Australia, AS/NZS 3598.1:2014 Energy audits, Part 1: Commercial buildings
The point at which a discount, credit or other benefit under a market retail contract ends or changes. For small customers the retailer must give written notice between 40 and 20 business days beforehand, and after that date cannot charge more than its standing offer prices.
Why it matters
What ends is the discount rather than the underlying rate, so the amount payable can rise with no change to the prices stated in the contract. The notice period and the standing offer limit are small customer protections, so a large customer's benefit end date is governed by its agreement alone.
Source: National Energy Retail Rules, rules 48A and 48C
BESSThe common abbreviation for battery energy storage system. See Battery energy storage system →
A stage in a multi-stage procurement in which shortlisted suppliers are invited to submit a final offer after clarification or negotiation. Victorian government guidance describes it as a process to obtain the best result from shortlisted suppliers against the procurement requirements, with the final offer not subject to further negotiation.
Why it matters
Anything the buyer wants changed has to be raised before this round, because the offer that comes back closes the negotiation.
Source: Victorian Government, glossary of goods and services procurement terms
Industry usage
Checking an energy invoice against the contract, the metering data and the applicable network tariff to confirm the charges are correct.
This is settled industry usage rather than a defined term.
Why it matters
Commercial bills combine contracted energy rates with network charges, market fees and environmental costs, each of which can be applied incorrectly. Errors persist until someone checks.
Industry usage
A consolidated record of a buyer's energy invoices across sites and billing periods, holding the account and supply point identifiers, the period, consumption, charges by component and the amount payable. It is the basis for bill validation and for comparing invoiced rates against contracted rates.
Why it matters
A register built from invoices carries whatever the invoices contained, so it can show an invoiced rate differing from a contracted rate without showing whether the consumption behind it came from an actual read, an estimate or a substitution.
A high-methane content gas produced by biogas upgrading and suitable for use as a natural gas substitute. Biogas upgrading is the refining of biogas and the stripping of its impurities, which may include pre-treatment, drying or scrubbing, and post-treatment processing or compression.
Why it matters
The definition turns on suitability as a natural gas substitute rather than on the source of the gas, so a quantity of it is metered and converted to energy the same way natural gas is, and the renewable attribute travels on a separate certificate.
Source: National Greenhouse and Energy Reporting Regulations 2008, section 1.03, current regulations
Industry usage
Renegotiating an existing contract by blending its remaining rate with a new rate and extending the term.
Why it matters
The remaining rate is carried into the new term rather than ended, so the blended figure reflects the old position as well as the new one, and the commitment runs beyond the original end date.
See also
Break feeAnother name for an early termination charge. See Early termination charge →
Industry usage
A commission paid to an intermediary for arranging a supply contract. It is commonly expressed as an amount per unit of energy, such as dollars per megawatt hour or cents per kilowatt hour, and recovered through a margin on the energy rate, so the retailer pays it out of the contract and recovers it in the rate the buyer pays. Fixed amounts per site or per contract are also used.
Note: A fee recovered through the rate forms part of the rate rather than appearing as a separate invoice line.
Why it matters
The amount and structure sit in the intermediary's engagement terms rather than in the supply contract, so both documents describe the cost of the arrangement. The Energy Charter's voluntary code publishes a procurement checklist listing costs, commissions, fee structures and contract terms as matters for a customer to establish.
Source: The Energy Charter, National Customer Code for Energy Brokers, Consultants and Retailers
Industry usage
An existing building where the embedded network is already operating, usually with an incumbent operator and an existing agreement to review.
Why it matters
The terms are inherited rather than set at the outset, so what the site can do next is bounded by the remaining term of the existing agreement and by what that agreement says about ending it.
See also
Industry usage
A development built to be held and leased by a single owner rather than sold lot by lot. The ownership structure changes who contracts for energy at the site.
Why it matters
One owner contracts for the whole site, so the energy arrangement is decided by that owner and reaches occupants through their leases rather than through an owners corporation decision.
See also
Industry usage
A development built for sale of individual lots, after which common property passes to an owners corporation.
Why it matters
The party that signs the original site agreement is the developer, and by the time the arrangement is being lived with, the counterparty to it is an owners corporation that did not negotiate it.
See also
The certificate that discloses energy efficiency information about office space under the Commercial Building Disclosure programme. It combines a NABERS Energy for Offices rating for the building with a Tenancy Lighting Assessment, is valid for up to 12 months, and is published on the Building Energy Efficiency Register.
Note: The two components have different lives. The NABERS rating is valid for up to 12 months and the Tenancy Lighting Assessment for five years, and the certificate lapses when the earlier of the two expires.
Why it matters
A current registered certificate must be in place before disclosure affected office space is advertised or offered for sale, lease or sublease, and the NABERS rating from it must appear in the advertising.
Source: DCCEEW, Building Energy Efficiency Certificate
Bulk hot waterAnother name for centralised hot water. See Centralised hot water →
Industry usage
A contract structure in which network charges and other costs are combined with the energy rate into a single price.
There is no regulated definition, and the choice to bundle sits with the retailer.
Why it matters
A bundled price carries the retailer's estimate of future network and regulated costs, and the risk of that estimate being wrong. That risk is priced.
Industry usage
Two or more buyers who combine their requirements and approach the market together, so that one negotiation covers all of them. Where the members compete with each other, negotiating collectively engages the competition provisions of the Competition and Consumer Act, and the ACCC's class exemption, notification and authorisation processes are the routes to legal protection for it.
Why it matters
Whether competition law protection is needed turns on whether the members compete with one another, not on the size of the combined load, so a group of buyers in unrelated markets and a group of direct rivals sit differently even when they buy identically.
BuyoutAnother name for residual value in an embedded network agreement. See Residual value →
C
Industry usage
The process of reversing an invoice that has already been issued and issuing a replacement covering the same period. It is normally triggered when the metering data behind the original invoice changes, for example when an estimated or substituted read is replaced by an actual read, or when a rate, loss factor or network tariff applied to the account is corrected.
Note: The term names the billing process, not its outcome. A cancel and rebill can produce a credit or a further amount owing.
Why it matters
The National Energy Retail Rules set out what a retailer must do on undercharging and overcharging, including notification and repayment duties and a recovery period limit, but those rules apply to small customers. A large customer's position on a corrected invoice is governed by its contract and by general law.
Source: National Energy Retail Rules, rules 30 and 31, current rules
Industry usage
A contract that limits the price paid for electricity above a set level, so the buyer is protected from prices beyond it. Exchange-traded caps in the national market have a strike price of $300 per megawatt hour.
Note: This strike price is a feature of the traded contract and is unrelated to the administered price cap, which is a regulatory ceiling AEMO applies during an administered price period. The two are different mechanisms that have at times carried the same figure.
Why it matters
The protection operates only above the strike level, so outcomes below it still pass through to the buyer, and the cost of holding the cap is incurred whether or not prices ever reach that level.
Source: AER, State of the energy market, on contract products
AEMO's daily auction of transportation capacity on the pipelines and compression facilities subject to it, held for use on the following gas day. Only capacity that has been contracted but not nominated by the nomination cut-off time is offered. The auction runs as a single sealed-bid round with a reserve price of zero, clears on a pay as cleared basis, and sells forward haul, backhaul and compression services.
Note: Part 25 does not apply in Western Australia until an order under section 7A of the National Gas Access (WA) Act 2009 is published in the Western Australian Government Gazette.
Why it matters
Capacity won in the auction is not firm within the meaning of the Rules, so it is scheduled after firm services and curtailed before them. Because the reserve price is zero, a product left partly unsold clears at nothing per gigajoule.
Source: National Gas Rules, Part 25, rules 645 to 652, current rules
Capacity chargeAnother name for a demand charge, used in some tariff schedules. See Demand charge →
The unit in which Western Australia's Reserve Capacity Mechanism measures and pays for capacity. Under the Electricity System and Market Rules a Capacity Credit is a Peak Capacity Credit or a Flexible Capacity Credit, each equivalent to one megawatt of the relevant capacity provided by a facility during a Capacity Year, and each held by the Market Participant registered for that facility.
Why it matters
The number of Capacity Credits AEMO assigns, and the Reserve Capacity Price paid for them, set the pool of capacity cost that Western Australian loads then fund in proportion to their Individual Reserve Capacity Requirement. There is no equivalent unit in the National Electricity Market, so an eastern states site funds no comparable payment.
See also
Source: Electricity System and Market Rules (WA), chapter 11 glossary, current rules
Industry usage
A generating plant's actual output over a period as a share of what it would have produced running at its registered capacity for the whole of that period.
Note: The AER publishes an available capacity factor, which compares a generator's availability to its registered capacity. That measures what the plant was able to offer rather than what it produced, so the two figures are not interchangeable.
Why it matters
It converts a stated plant capacity into expected energy over a year, so the megawatts named in a generation or power purchase offer do not by themselves establish how much of a site's consumption the project can cover.
Source: AER, Wholesale electricity market performance report 2026
A Commonwealth revenue underwriting scheme that runs competitive tenders for agreements supporting new renewable generation and clean dispatchable capacity such as battery storage. It targets an additional 40 GW of capacity by 2030, made up of 26 GW of generation and 14 GW of dispatchable capacity, following an uplift from 32 GW announced on 29 July 2025. AEMO and the scheme's tender delivery partner administer the tender process.
Current status: The expanded scheme is being rolled out from 2024 to 2027, with tender rounds published on an indicative timetable by market and technology. Tenders are held in the National Electricity Market and in Western Australia's Wholesale Electricity Market until 2027.
Why it matters
It reaches both the national market and Western Australia, which few energy schemes do. The money goes to generators as underwriting, so its effect on a buyer shows up in forward wholesale prices and not as a line on a bill.
Source: Department of Climate Change, Energy, the Environment and Water, Capacity Investment Scheme
A payment a connecting customer makes towards the cost of work a network must do to provide a connection service, including a prepayment or a financial guarantee. The connection charge principles allow a reasonable contribution towards an extension of the network, towards augmentation of premises connection assets at the connection point, and towards wider augmentation of the distribution system for a standard connection service or under a negotiated connection contract, and only where provision for the cost has not already been made through distribution use of system charges or the tariff applying to the connection.
Note: Each network's connection policy must set a shared network augmentation charge threshold below which a retail customer cannot be required to contribute towards augmentation beyond an extension. The AER requires that threshold to be based on a measure of demand and fixed for the regulatory control period, and allows a network to set a different threshold in each identifiably different area of its network. Where a connection asset stops being dedicated to the customer's exclusive use within 7 years of its construction and the customer is entitled to a refund under the connection charge guidelines, the network must make the refund and may recover it from the new users of the asset.
Why it matters
The amount is settled at the connection offer and paid once, while the asset it funds is owned and operated by the network, so it is a capital cost of establishing the site rather than a charge that later moves with consumption or demand.
See also
Source: National Electricity Rules, clause 5A.E.1, current rules; AER, connection charge guidelines for electricity customers, April 2023
A small customer who continues consuming energy at premises after their contract expires without new terms being agreed and without applying to a retailer.
Why it matters
A business becomes one without acting, because the status follows from an expiry date passing while supply continues. Until new terms are agreed, what governs supply is the statutory arrangement rather than the contract that ended.
Source: National Energy Retail Law, section 2
Industry usage
A shared hot water service in a building, where water is heated centrally and supplied to individual lots. It is commonly metered and billed to occupants alongside electricity in an embedded network.
Why it matters
A lot can be charged for hot water without holding any gas or electricity account for it, so that charge reaches the occupant through the embedded network arrangement rather than from a retailer they chose.
Industry usage
A defined event allowing a supplier to adjust charges, or introduce a new charge, to recover costs arising from a legal change after the contract starts. Definitions commonly reach the introduction, amendment or repeal of any law, regulation, rule or code, and any new or increased tax, fee or charge affecting the supplier's cost of buying or selling the energy.
Why it matters
It is the route by which a charge the buyer never agreed to appears inside a term that was priced as fixed, and what is recovered is the supplier's cost rather than any compliance cost of the buyer's own.
Check meterAnother name for a child meter. See Child meter →
A connection point within an embedded network, serving an individual lot or tenancy, which can be registered in the market so the occupant can take supply from a retailer of their choice.
Why it matters
Retailer choice is exercised point by point, so one tenancy can move to a retailer of its own while the rest of the site keeps buying from the exempt seller.
Source: AEMO MSATS procedures; AER embedded network material
Industry usage
A meter within an embedded network that records consumption for an individual lot, tenancy, common area or service.
Note: The rules define the parent and child connection point rather than the meter, so the meter terms are market usage built on the defined connection points.
Why it matters
An occupant's charge is calculated from this reading, and common area and service meters sit in the same set, which is what separates shared costs from a single tenancy's. The site's bill from its retailer is not the sum of these readings, because that bill is calculated at the parent meter.
CHWThe common abbreviation for centralised hot water. See Centralised hot water →
CISThe common abbreviation for the Capacity Investment Scheme. See Capacity Investment Scheme →
The Commonwealth statutory authority that administers Australia's carbon and renewable energy schemes, established under the Clean Energy Regulator Act 2011 and operating since 2 April 2012. Its schemes include the Renewable Energy Target, made up of the large-scale target and the small-scale scheme, the Australian Carbon Credit Unit scheme, the Safeguard Mechanism, National Greenhouse and Energy Reporting, the Guarantee of Origin scheme and the Nature Repair Market.
Note: It has no role in energy prices, retailer conduct or network regulation. Its schemes sit behind the environmental component of an energy price rather than the price itself.
Why it matters
Its schemes are Commonwealth and apply in every state and territory, so the certificate obligations sitting behind the environmental component of a bill are the same wherever a site is, unlike retail rules, which change with the jurisdiction.
Source: Clean Energy Regulator, about us
An Australian Government programme that certified businesses and organisations against the Climate Active Carbon Neutral Standards and licensed them to use the Climate Active trade mark.
Note: The programme is being wound down. The government announced in July 2026 that it will end certification of voluntary climate claims, with certification proposed to cease on 30 June 2027 and the trade marks and the official carbon neutral term for voluntary claims discontinued.
Why it matters
A carbon neutral claim resting on this certification has an end point, and any claim continuing past it rests on a different basis.
Source: Climate Active, Climate Active certification ending, have your say
Carbon dioxide equivalence. Under the National Greenhouse and Energy Reporting Act it is the amount of a greenhouse gas multiplied by a value specified in the regulations for that kind of gas, which places gases of differing warming effect on a single scale.
Why it matters
The reporting thresholds and the Safeguard Mechanism are both expressed in it, so whether an obligation applies is settled by the converted figure rather than by the physical quantity of any one gas emitted.
See also
Source: National Greenhouse and Energy Reporting Act 2007, section 7, current Act
An ACCC class exemption that allows eligible businesses to negotiate collectively with a common supplier or customer without breaching the cartel and anti-competitive conduct provisions of the Competition and Consumer Act. A corporation is eligible for a financial year if it reasonably believes its aggregated turnover in the previous financial year was less than $10 million. Franchisees negotiating with their franchisor, and fuel retailers negotiating with their fuel wholesaler, are eligible regardless of turnover.
The mechanism is a notice. The group gives a notice in the approved form to the ACCC, and a copy to the target business before negotiating, making or giving effect to the contract. Conduct is covered from the notice date, or from no more than 14 days before it. The exemption does not cover a provision whose purpose is to restrict supply to or acquisition from the target, that is, a collective boycott.
Why it matters
Cover runs from the notice rather than from when the group formed, and reaches back only a short way before it, so earlier negotiation sits outside the exemption. Eligibility is tested on the previous financial year's turnover, so a group can qualify in one year and not the next.
See also
Source: ACCC, Competition and Consumer (Class Exemption-Collective Bargaining) Determination 2020, sections 5, 7, 8, 9 and 10
A national regulatory programme requiring energy efficiency information to be provided in most cases when commercial office space of 1,000 square metres or more is offered for sale, lease or sublease. It is administered by DCCEEW under the Building Energy Efficiency Disclosure Act 2010.
Why it matters
The obligation attaches to offering space to the market rather than to occupying it, and it reaches sublease, so a tenant looking to sublet qualifying office space is caught as much as the building's owner.
Source: DCCEEW, legal framework
Industry usage
A description of an arrangement in which the intermediary is paid a fee by the buyer and takes no commission from the retailer, so the fee is invoiced to the buyer rather than recovered through the energy rate.
Note: This is a market claim, not a regulated or defined term. What it covers in a particular engagement depends on that engagement's terms.
Why it matters
The intermediary's fee reaches it directly from the buyer, so it is recorded as a cost of the procurement in the buyer's own accounts rather than forming part of the rate paid per unit of energy.
A written disclosure of any actual, potential or perceived conflict of interest, made by a person taking part in a procurement. A conflict of interest arises where an official, an adviser or a supplier has an affiliation or interest that might prejudice, or be seen to prejudice, their impartiality. Commonwealth guidance says the declaration should be made before the person takes part in the process, and that the obligation to disclose conflicts arising later runs until the process is complete.
Why it matters
Perceived conflicts are within what is disclosed, so an interest that would not in fact change a decision still falls to be declared. The disclosure attaches to a person's participation rather than to the buyer's own staff, so it reaches external advisers sitting on an evaluation panel.
Source: Department of Finance, ethics and probity in procurement; Victorian Government, glossary of goods and services procurement terms, under conflict of interest form
Industry usage
A distribution network's agreement to a new or altered connection at a site, on conditions it sets. Under chapter 5A of the Rules the sequence for a retail customer is a connection application, then a connection offer from the network, then a connection contract formed by acceptance of that offer.
Note: "approval" is not a defined term in the Rules. Networks use it both for that decision and for the separate approval of inverter or generation capacity at an existing connection. Which process applies, what information is required and what conditions attach are set in the relevant network's AER-approved connection policy.
Why it matters
Adding or altering generation capacity at an existing connection can require the network's approval even though the connection itself is unchanged, and the conditions attached come from that network's own connection policy, so the same installation can be approved on different terms in different network areas.
See also
Source: National Electricity Rules, clauses 5A.A.1 and 5A.D.3, current rules
The contract formed by the making and acceptance of a connection offer, between the distribution network service provider and the retail customer or real estate developer.
Why it matters
It is held with the distributor and governs the connection itself, so its terms, including any export limit attached to the connection point, survive a change of retailer and cannot be altered by renegotiating the supply contract.
See also
Source: National Electricity Rules, clause 5A.A.1, current rules
An offer by a distribution network service provider to enter into a connection contract with a retail customer or a real estate developer. It must be accompanied by a schedule itemising connection costs, including the applicable connection charges, the cost of any network extension, details and cost of upstream augmentation required to provide the service, and any other incidental costs with the basis of their calculation.
Note: The timing differs by category. For a basic or standard connection service the network must make the offer within 10 business days of a properly completed application, in accordance with the approved model standing offer. For a negotiated connection contract it must use best endeavours to make the offer within 65 business days of the application, and that offer lapses 20 business days after its date unless the parties agree to extend the period for acceptance.
Why it matters
The itemised schedule separates what is charged for an extension from what is charged for upstream augmentation, which is the split that decides whether the threshold in the network's connection policy applies to the quote.
See also
Source: National Electricity Rules, clauses 5A.A.1, 5A.E.2, 5A.F.1 and 5A.F.4, current rules
The point at which a customer's electrical installation connects to the distribution or transmission network. Financial responsibility for energy taken at a connection point sits with one market participant, usually the retailer, and each connection point carries its own identifier.
Why it matters
The connection point is the unit the market actually works in. Contracts, metering obligations and network tariffs all attach to it, which is why a portfolio is a set of connection points rather than a set of addresses.
Source: AEMO, MSATS technical guide
Industry usage
Loss that does not arise naturally, or in the usual course of things, from a breach of contract. Australian supply agreements exclude it mutually, and commonly do so under drafted labels such as indirect loss and economic loss rather than under the phrase itself.
Note: The phrase has no fixed content in Australian law, so what is excluded is read from the contract's own definition. Where that definition names business interruption losses, loss of profits and data corruption, the exclusion removes the buyer's own lost production and profit as well as the supplier's.
Why it matters
The exclusion runs both ways, so a buyer whose site stops because of a supply failure carries its own lost output and lost margin, and recovers only loss falling inside what the contract leaves available.
The mathematical representation AEMO uses to manage power system limitations and frequency control ancillary service requirements in the dispatch engine. A physical restriction, such as how much a transmission element can carry under given conditions, is translated into a linear equation the dispatch solver must satisfy, which turns it into a restriction on what can be dispatched. AEMO formulates them under the Constraint Formulation Guidelines, made under clause 3.8.10(c) of the National Electricity Rules.
Why it matters
A binding constraint can hold cheaper generation out of a region and lift that region's price while prices elsewhere stay low. That is the mechanism behind a retailer attributing a price move to the network rather than to generation or demand, and the constraint that bound is on the public record.
Source: AEMO, Constraint Formulation Guidelines
The consumer data portability regime established under the Competition and Consumer Act 2010 and applied to energy by the Consumer Data Right (Energy Sector) Designation 2020. In energy it lets a consumer require a retailer to share nominated data with an accredited data recipient. Product data sharing commenced on 1 October 2022 and consumer data sharing on 15 November 2022 for the retailers named as initial retailers in the CDR Rules, with later dates for larger retailers.
Note: Retailers are primary data holders, holding customer, account, billing and tailored tariff data. AEMO is a secondary data holder with no direct customer relationship, holding metering data, National Metering Identifier standing data and distributed energy resources register data. The regime covers the National Electricity Market, and data holder obligations apply only to authorised or licensed retailers operating in it.
Why it matters
A consumer data request made on behalf of a large customer, including commercial and industrial customers, is a complex request under the CDR Rules and carries later commencement dates than a non-complex request.
Source: Australian Government, CDR in the energy sector
Small-scale energy resources owned by customers that can produce, store or vary how energy is used. The AEMC's examples are rooftop solar, batteries and electric vehicles, alongside older assets such as hot water heaters and pool pumps.
Note: Consumer energy resources has taken over most of the work that distributed energy resources used to do, and it is the term in AEMO's CER Data Exchange programme and in the Energy Ministers' national consumer energy resources roadmap. The two are not exact synonyms. The AEMC uses consumer energy resources for the customer-owned subset and distributed energy resources for the broader category, which also takes in assets such as neighbourhood batteries.
Why it matters
The dividing line is ownership by the customer, so whether equipment at a site falls under the term turns on who owns it rather than on where it sits or what it does.
See also
Source: AEMC, Unlocking the full potential of consumer energy resources
Industry usage
Whether a customer is allowed to choose their electricity or gas retailer. It is a function of jurisdiction and consumption rather than a single national rule.
Note: In the National Electricity Market jurisdictions every customer is contestable, which is why those markets are described as having full retail contestability. In the South West Interconnected System in Western Australia, a customer consuming not more than 50 MWh a year at a supply point is a prescribed customer and is non-contestable, so it can be supplied only by the state-owned retailer. In the Northern Territory, retail choice is confined to larger customers under the Territory's own arrangements.
Why it matters
A site below the threshold in a non-contestable jurisdiction cannot be tendered at all, whatever its spend.
Source: Energy Policy WA, information paper on the SWIS prescribed customers order 2023
Industry usage
The recurring yearly date on which a supply contract took effect. Contracts use it to time rate steps, review points and notice periods.
Note: It is not the contract end date, and it need not align with the billing cycle or the financial year.
Why it matters
A rate step or review geared to the anniversary can fall part-way through a billing period, so a single invoice carries the rate from either side of the date.
See also
A cash-settled contract on a fixed price for a stated quantity over a stated period. Where the spot price is above the fixed price, the seller pays the buyer the difference; where it is below, the buyer pays the seller. In over-the-counter markets, electricity futures go by the names swaps and contracts for difference.
Why it matters
The obligation runs both ways, so a buyer makes payments to the seller in periods when the spot price sits below the fixed price. That two-way exposure is what separates it from a cap, which only pays above a set level.
Source: AER, State of the energy market 2021, chapter 2
The calendar quarter an exchange-traded electricity contract covers. Contract months are March, June, September and December, and because a quarter runs to 90, 91 or 92 days, a base load contract unit of one megawatt covers 2,160, 2,184 or 2,208 megawatt hours depending on which quarter it is.
Why it matters
The number of hours behind a quarter differs from one quarter to the next, so the same rate per megawatt hour settles against a different volume each time.
Source: ASX, Australian electricity derivatives fact sheet
Industry usage
A record of a buyer's supply agreements, holding for each one the counterparty, start and end dates, the contracted rates and charges, the sites covered, and the dates on which notice must be given or a review falls due.
Note: In government procurement the same phrase names a published register of awarded contracts kept to meet a disclosure obligation, which is a different document from a buyer's internal record.
Why it matters
A site can pass from one agreement to another during a portfolio's life, so the register is what establishes which contract covered a given site on a given date, which neither a list of sites nor a run of invoices shows.
Industry usage
The volume of energy a buyer commits to take under a supply agreement.
Why it matters
It is a commitment rather than a forecast, so under a take-or-pay arrangement it sets the volume payable even where less is consumed.
Under the National Greenhouse and Energy Reporting Act, a constitutional corporation that does not have a holding company incorporated in Australia. A controlling corporation's group consists of the corporation and its subsidiaries, and may consist of the corporation alone.
Why it matters
The duty to apply for registration and to report falls on this entity rather than on whichever subsidiary operates a site, so the obligation sits at the top of the Australian structure even where no energy account is held there.
See also
Source: National Greenhouse and Energy Reporting Act 2007, sections 7 and 8, current Act
The National Greenhouse and Energy Reporting threshold measured across the whole of a controlling corporation's group: 50 kilotonnes of CO2-e emitted, 200 terajoules of energy produced, or 200 terajoules of energy consumed, in a financial year.
Why it matters
It is a sum across the group, so a portfolio of sites that each sit under the facility threshold can still bring the group into the scheme, and adding or divesting entities moves the total that is tested.
See also
Source: National Greenhouse and Energy Reporting Act 2007, section 13(1)(a) to (c), current Act
Industry usage
Dividing an energy cost across sites, departments, tenants or cost centres, normally from metering data and normally where one supply or one account serves more than one user.
Why it matters
Apportioning a cost does not alter who holds the supply account, so the account holder remains liable to the retailer for the whole amount however the cost is divided internally. A user without its own meter receives an apportioned share rather than a measured one.
A contingency event whose occurrence AEMO considers reasonably possible in the surrounding circumstances, including the technical envelope. The Rules give as likely examples the unexpected disconnection or unplanned capacity reduction of one operating generating or bidirectional unit, and the unexpected disconnection of one major item of transmission plant other than through a three phase fault. Events outside that set, such as three phase faults or simultaneous multiple failures, are non-credible contingency events.
Why it matters
The size of the largest relevant credible contingency event in a region is the reserve margin AEMO measures against when declaring LOR2, so it sets the point at which supply-risk notices start appearing for a buyer's region.
Source: National Electricity Rules, clause 4.2.3, current rules
Industry usage
A retailer's review of a buyer's financial standing and payment record. In large customer supply agreements it is commonly a continuing right rather than a single step at signing, with the buyer undertaking to provide the information needed for it throughout the term.
Note: For small customers the Retail Rules deal with the related question of credit history, requiring a retailer to ask the customer for permission to run a credit check and to consider the result before requiring a security deposit. Those requirements do not reach large customer agreements, where the scope and timing of assessment are set by the contract.
Why it matters
A buyer that passed at signing can be assessed again at any point in the term, and a changed result is the event that opens the retailer's right to call for security.
Source: National Energy Retail Rules, rule 39, current rules
Industry usage
The umbrella term for any instrument standing behind a buyer's payment obligations, covering cash security, bank guarantees and parent company guarantees. Agreements use it to describe the obligation at a level above whichever instrument is chosen.
Why it matters
Because the obligation is drafted at that level, the retailer usually decides which instrument satisfies it, so the choice between tying up cash and committing bank facilities may not sit with the buyer.
CT meteringThe common abbreviation for current transformer metering. See Current transformer metering →
The dollar figure that, once exceeded by the sum of a region's prices over the previous 2,016 trading intervals, equivalent to seven days, triggers an administered price period in that region. The AEMC calculates it by 28 February each year from a base value set in the Rules, indexed to the Australian consumer price index, and publishes it in a schedule of reliability settings to apply from 1 July. For the 2026-27 financial year it is $2,225,900 per MWh, equivalent to an average spot price of $1,104.12 per MWh across the seven days.
Current status: From 1 November 2028 the calculation changes under an AEMC final rule made on 23 April 2026. AEMO will use prices received rather than dispatch prices to work out when the threshold is reached, and trading intervals priced from the market suspension pricing schedule will be excluded from the cumulative price.
Why it matters
The trigger is a seven-day total rather than a single interval, so a sustained run of moderately high prices can bring the cap on while one extreme spike does not. That is what decides whether a pass-through buyer's exposure across a bad week is collared or not.
Source: National Electricity Rules, clause 3.14.1, current rules
Metering in which instrument transformers present the meter with a scaled-down version of the current flowing to the load, so the meter measures a fixed proportion of what the site draws rather than the whole of it. At high voltage, voltage transformers scale the voltage in the same way. The National Electricity Rules count current and voltage transformers as part of the metering installation, and AEMO's metrology procedure sets the standards they must meet and treats instrument transformer connected metering as a category distinct from whole current metering.
Why it matters
The reading on the meter is a fraction of the energy consumed until the meter multiplier is applied, so a register reading taken on site cannot be compared with a bill without it.
See also
Source: National Electricity Rules, chapter 7 and schedule 7.4, current rules; AEMO, Metrology Procedure Part A, section 3.1
Industry usage
Output or export being limited below what a plant or site could otherwise have produced or sent to the network. The limit may come from a network constraint, a dispatch instruction, a market price outcome, or a cap written into a connection agreement.
Note: The Rules do not define the word, and it is used for both generation being constrained and a site's exports being reduced. The solar-specific sense is a separate entry in this glossary.
Why it matters
The word covers limits imposed by a connection agreement, a network constraint, a dispatch instruction and a price outcome alike, so it says output was reduced without saying what reduced it, and the cause decides whether the limit is permanent, occasional or a commercial choice.
The reduction of a solar system's output or export below what it could otherwise produce. For a customer system this happens through a fixed export limit set at connection, a flexible export limit signalled by the distributor to the inverter, or an inverter reducing output in response to local voltage.
Note: The word also describes a wholesale generator reducing output, which is a different mechanism with different causes. See Curtailment.
Why it matters
Curtailed energy produces neither a bill saving nor a feed-in credit, so a site's modelled solar yield and its realised yield can diverge without any fault in the equipment.
Source: AER, Export limits guidance note
The defining term in the Retail Law for a contract between a small customer and a retailer. Because the definition is limited to small customers, the protections attaching to it do not reach large customers.
Why it matters
The definition is the hinge the Retail Law's protections hang from, so a business that crosses the consumption threshold loses them by operation of that definition rather than through anything in its agreement changing.
Source: National Energy Retail Law, section 2
Network assets paid for by the connecting customer rather than recovered from all customers through network tariffs. Under the connection charge principles a retail customer may be asked for a reasonable capital contribution towards an extension of the network, or towards augmentation of premises connection assets at their connection point. A customer cannot be required to contribute towards wider augmentation where the application is for a basic connection service or where the threshold in the network's connection policy is not exceeded.
Note: What a customer funds, the threshold above which a contribution applies, and whether any later refund is available if the asset comes to serve other premises, are set in each network's AER-approved connection policy. Energex, for example, runs a pioneer scheme giving a partial refund where an extension funded by one customer is used to connect other premises within seven years.
Why it matters
The asset is commonly owned, operated and maintained by the network once built, so the contribution buys a connection rather than an asset the customer holds.
See also
Source: National Electricity Rules, clause 5A.E.1; Energex, connection policy 2025-30
D
Industry usage
The baseline volume of gas a buyer may nominate on any one day under a gas supply agreement, usually stated in gigajoules or terajoules. Permitted variation above and below it is set separately, as swing.
Why it matters
The daily baseline rather than the annual total governs what can be taken on a given day, so a cold week can reach the daily limit while the contract year still has volume left in it.
Industry usage
A fixed amount payable for each day premises are connected and supplied, charged independently of how much energy is consumed. On electricity invoices it is normally expressed in cents per day.
Note: The same line appears as "supply charge", "service to property charge", "fixed charge" and "standing charge" depending on the retailer and the jurisdiction. The labels are not standardised.
Why it matters
The amount does not fall when consumption falls, so it is not captured by a comparison of unit rates alone.
A two-character identifier used with a National Metering Identifier to name one datastream at a connection point. Appended to the ten-character NMI it forms a twelve-character identifier in which the first ten characters are the connection point and the last two the datastream. The first character identifies the measured quantity and the direction of flow, and the second distinguishes meters or measuring elements where more than one records the same quantity.
Note: Whether a datastream carries interval or accumulated data is readable from the first character. An alphabetic first character identifies interval metering data, and a numeric one accumulated data from a type 6 metering installation.
Why it matters
A connection point can carry several datastreams, so what a row of data represents is established by its suffix rather than by the NMI, and one NMI can return consumption, reactive and generation channels that must not be added together.
Source: AEMO, MSATS Procedures: National Metering Identifier, section 6
DCQThe common abbreviation for daily contract quantity. See Daily contract quantity →
The Victorian high-pressure gas transmission network that AEMO operates as a single market carriage system. The Victorian Transmission System is declared to be the declared transmission system under section 39(1)(b) of the National Gas (Victoria) Act 2008, and AEMO notes that the two names are often used interchangeably.
Why it matters
Transmission across it is bundled into bids in the Declared Wholesale Gas Market rather than sold as reservable pipeline capacity, so a Victorian site does not hold a haulage contract across the transmission system in the way a site on a contract carriage pipeline does.
Source: National Gas (Victoria) Act 2008, section 39(1)(b); AEMO, guide to understanding the scope of the DWGM and Victorian retail market
The wholesale gas market AEMO operates across Victoria's declared transmission system and certain declared distribution systems. Gas is scheduled and priced five times each gas day, at 6 am, 10 am, 2 pm, 6 pm and 10 pm, and each pricing schedule sets an ex ante market price by stacking participants' injection and withdrawal bids against AEMO's demand forecast.
Note: It is a market carriage system operating as a single virtual hub, so participants do not reserve pipeline capacity across the transmission system. The cumulative price is the marginal clearing price accumulated over the preceding 35 scheduling intervals, which is one week; if it reaches the cumulative price threshold, an administered price period begins and the price cannot exceed $40 a gigajoule. Trades in this market, like those in the short term trading markets, sit outside the Gas Market Code's reasonable price provisions.
Why it matters
The wholesale component of a Victorian gas price is set in this market rather than by bilateral negotiation with a producer, so a Victorian site's exposure moves with five schedules a day, and the volume weighted price across a gas day tends towards the 6 am schedule because most gas is traded there.
Source: AER, Victorian gas market cumulative price; National Gas Rules, Part 19, current rules
The arrangement that applies when a small customer keeps taking supply at premises without a contract, for example after moving in or after a contract ends. It is a statutory safety net, and it applies to small customers only.
Why it matters
A large customer in the same position has no equivalent. What applies is whatever the expired contract provides, or terms the retailer sets.
Source: National Energy Retail Law, section 54
An exemption that applies automatically to a seller meeting the stated criteria, with no registration required.
Why it matters
The conditions attached still bind the seller even though nothing was lodged or approved, and because there is no registration step there is no point at which the regulator has looked at the arrangement.
Source: AER, retail exempt selling guideline
The forward period over which small-scale technology certificates are created for a system, described by the Clean Energy Regulator as an estimate of how many years a system will generate renewable energy. It decreases by one year for each later installation year until the scheme ends in 2030, so a system installed in 2026 has five years and one installed in 2030 has one.
Note: The regulator's glossary frames the deeming period as the estimated amount of electricity a system generates or displaces, while the entitlement calculation applies it as a number of years. The number of years is the operative figure.
Why it matters
Because certificates for the whole deeming period are created at installation, the subsidy value of an identical system falls each year as the period shortens.
Source: Clean Energy Regulator, calculate small-scale technology certificate entitlements
A price cap set annually by the Australian Energy Regulator for standing offers to residential and small business customers in New South Wales, south-east Queensland and South Australia. It is also the reference price against which market offers are compared. Small business for this purpose means consumption below 100 MWh a year.
Why it matters
It does not apply to large customers, and it does not follow a small customer onto an expired market contract. It is frequently assumed to be a general protection, and it is neither.
Source: AER, Default market offer prices 2026-27, final determination, May 2026
Default rateAnother name for an out-of-contract rate, and not to be confused with the Default Market Offer, which is a regulated price cap for small customers. See Out-of-contract rate →
The point on a pipeline at which gas is withdrawn and handed to the party taking it. The Rules define a receipt or delivery point as a point on a pipeline at which a service provider takes delivery of covered gas or delivers it, and a delivery point as that point when used for withdrawal.
Why it matters
Services, tariffs and metering are all written per delivery point, so a business with gas arriving at two points holds two sets of each, and the quantities agreed at one do not carry across to the other.
Source: National Gas Rules, rule 3 (receipt or delivery point) and rule 141 (delivery point), current rules
A network charge based on the rate at which electricity is drawn at a site, rather than total consumption. There is no national definition: each distributor sets the measurement interval, the unit, the time window, the look-back period and any minimum chargeable level in its own tariff structure statement.
Why it matters
Because the definition varies by distributor, an identical load is billed differently in different states, and a demand charge can continue reflecting a single peak for twelve months after it occurred.
Source: Distributor tariff structure statements approved by the AER. Examples: Ausgrid charges on the highest half-hourly kVA in a defined weekday evening window over the previous twelve months; CitiPower charges on a fifteen-minute kVA maximum across a daytime window with a minimum chargeable demand.
A gas delivery point priced on hourly demand rather than on the volume of gas delivered, because the quantity delivered there has passed the threshold set in the relevant network's access arrangement.
Note: Each access arrangement sets its own threshold. On the Australian Gas Networks Victoria and Albury networks a delivery point is a Demand DP if the quantity of gas delivered has exceeded 10 TJ in the preceding 12 months, or 10 GJ in any hour during the preceding 12 months. That network classifies and reclassifies delivery points, taking into account expected demand and connection characteristics and the reference tariffs assigned to delivery points with the same or materially similar characteristics.
Why it matters
Reaching the threshold moves a site from a volume tariff to one charged on maximum hourly quantity, changing what the network charge responds to, and the classification is one the network makes on the gas actually delivered.
Source: Australian Gas Networks, Victoria and Albury access arrangement 2023-28.pdf)
The network setting a site's chargeable demand to a figure lower than its recorded maximum would otherwise produce, so an earlier peak stops driving the charge. On tariffs that charge on a rolling maximum, a reset is generally granted only on application and on evidence of a permanent change at the site.
Note: Both the grounds and the effect vary by network. On the CitiPower and Powercor networks a 12-month rolling demand reset may be granted where power factor correction equipment has been installed and a certificate of electrical safety supplied, with demand then measured from commissioning, or where the customer evidences another permanent change to the load. The applicable rule is the one in the relevant network's tariff schedule or pricing documents.
Why it matters
Without a reset, a recorded peak keeps setting the demand charge until it falls out of the look-back period, so a load change made after the peak may not show up in the bill for months.
Source: CitiPower and Powercor, large business tariffs fact sheet
A change in a consumer's electricity consumption, relative to what would otherwise have been consumed, made in response to a price signal or an instruction. Under the wholesale demand response mechanism in the Rules, a demand response service provider may offer a consumer's reduction into the spot market and be settled at the spot price for it.
Note: The term also covers arrangements made directly between a retailer and a customer, outside the market mechanism, where the reduction is settled under the supply contract instead.
Why it matters
Which route a reduction runs through decides how it is paid, at the spot price where a demand response service provider offers it into the market, or on the terms of the supply contract where it is arranged directly with the retailer.
Source: National Electricity Rules, current rules
A person who has classified a connection point as a wholesale demand response unit, or connected plant as an ancillary service unit, or both, and who is registered by AEMO as a Demand Response Service Provider. The person does not need to be the Market Customer for the connection point.
Note: Registration requires satisfying the requirements for registration as a Market Participant and obtaining AEMO's approval for the classification. The provider's activities extend only to the units it has classified, and only while its registration holds.
Why it matters
Because the provider need not be the retailer at the site, a business can sell demand reduction into the wholesale market through a party other than its retailer, and the provider needs the retail customer's consent before classifying the connection point.
Source: National Electricity Rules, chapter 10 (glossary) and clauses 2.1A.4, 2.1B.5 and 2.3.6, current rules
Industry usage
A network or retail tariff that includes a charge based on the rate at which electricity is drawn at a site, in addition to or instead of a charge on total consumption.
Why it matters
On a demand tariff the bill no longer follows consumption alone, so a site can cut kilowatt hours without moving the demand component if the rate at which it draws power at its peak is unchanged.
DERThe common abbreviation for distributed energy resources. See Distributed energy resources →
Industry usage
A contract under which an end-use customer appoints its own metering coordinator rather than accepting the one appointed by its retailer. One provider commonly holds the metering coordinator, metering provider and metering data provider roles under the same agreement.
Note: The phrase is market shorthand and appears nowhere in the Rules. The right it rests on does: at a connection point other than one connecting a generating system to a distribution network, a metering coordinator may be appointed either by the financially responsible Market Participant or by the large customer whose premises are supplied at that connection point.
Why it matters
The appointment is the customer's, so the metering installation and the data arrangements survive a change of retailer, and the right to make it rests with a large customer rather than with any customer at the connection point.
See also
Source: National Electricity Rules, clause 7.6.2(a)(3), current rules
An instruction from AEMO requiring a registered participant to act outside normal market dispatch, available where AEMO is satisfied it is necessary to maintain or re-establish the power system to a secure, satisfactory or reliable operating state. Where the instruction relates to a scheduled resource, an ancillary service unit or a market generating or bidirectional unit it is a direction; other instructions under the same power are clause 4.8.9 instructions. Issuing one triggers intervention pricing, under which AEMO settles the market at the prices that would have applied had the direction not occurred.
Why it matters
The directed participant and any participants whose dispatch was displaced are compensated, and that compensation is recovered from market customers in the regions that benefited, in proportion to the energy consumed at their connection points. It reaches a buyer either as a pass-through line or inside a fixed rate, in a billing period after the event rather than during it.
See also
Source: AEMO, Guide to Intervention Pricing
The five-minute period for which AEMO runs central dispatch in the National Electricity Market, issuing dispatch instructions to scheduled plant and determining a dispatch price for each region. Dispatch has run on a five-minute cycle since the market began in 1998.
Note: Since five-minute settlement took effect, the dispatch interval and the trading interval are the same five minutes. Before that, six dispatch intervals sat inside one 30-minute trading interval.
Why it matters
Dispatch prices are set region by region, so two sites in different states carry different wholesale exposure at the same moment, and at five-minute granularity it is the timing of load within an hour that decides which price it meets.
Source: National Electricity Rules, chapter 10 glossary, current rules
Industry usage
The clause setting the steps parties must take before either can litigate, typically written notice with full particulars, a negotiation period, escalation to senior management and a meeting within a stated number of business days. Urgent injunctive or declaratory relief is usually carved out of the requirement.
Why it matters
Where the clause preserves each party's obligations while a dispute runs, the invoice under dispute stays payable throughout the process. Access to an energy ombudsman scheme is set by that scheme's own jurisdiction rather than by the clause.
Consumer-owned devices that, as individual units, can generate or store electricity or actively manage energy demand. Rooftop solar, batteries, hot water systems, smart appliances and electric vehicles are the common examples.
Why it matters
This is the category networks and AEMO use when setting connection conditions, export limits and visibility requirements, so a device that counts as a distributed energy resource brings approvals with it that an ordinary load does not.
See also
Source: AEMO, about the DER Program
A factor representing the average energy losses incurred in transporting electricity across a distribution network between a distribution connection point and the transmission connection point or virtual transmission node to which that point is assigned, for a given financial year. AEMO applies it to metered energy at a connection point, alongside the transmission loss factor, to derive the adjusted energy amount used in settlement.
Note: A distribution network service provider determines the factors for its own network under a methodology the AER has approved, then provides them to AEMO for publication before the financial year starts. The Rules allow either a site-specific factor or one derived from a volume-weighted average of losses across a class of connection points assigned to the same node.
Why it matters
The factor scales the volume on which wholesale energy is settled, so a site's billed wholesale quantity differs from its metered quantity, and the factor is reset each financial year outside any contract negotiation.
Source: National Electricity Rules, clause 3.6.3, current rules; AEMO, loss factors and regional boundaries
A person who engages in the activity of owning, controlling or operating a distribution system, being the network and connection assets between the transmission system and customer connection points.
Why it matters
The distributor for a site is fixed by where the site is and cannot be changed by switching, so a portfolio spread across several network areas deals with several distributors on connections, metering access and tariffs.
See also
Source: National Electricity Rules, chapter 10 (glossary), current rules
DistributorAnother name for a distribution network service provider. See Distribution network service provider →
DLFThe common abbreviation for distribution loss factor. See Distribution loss factor →
DMAThe common abbreviation for direct metering agreement. See Direct metering agreement →
DMOThe common abbreviation for the Default Market Offer. See Default Market Offer →
DNSPThe common abbreviation for distribution network service provider. See Distribution network service provider →
DRSPThe common abbreviation for a Demand Response Service Provider. See Demand Response Service Provider →
DTSThe common abbreviation for the declared transmission system. See Declared transmission system →
Distribution use of system charges, the component of network charges covering the cost of standard control distribution services, together with revenue adjustments and any pass-through amounts the regulator has approved.
Some distributors publish the same acronym as "distribution use of service".
Why it matters
Because the charge carries revenue adjustments and approved pass-through amounts as well as the cost of the service itself, the amount can change between years while a site's tariff and consumption stay the same. It is set per distribution area, so identical sites in different areas pay different DUOS.
Source: AER, tariff structure statement decision
DWGMThe common abbreviation for the Declared Wholesale Gas Market. See Declared Wholesale Gas Market →
E
A charge payable when a customer ends a fixed term contract before its end date. For small customers the Retail Rules require the amount or its calculation method to be stated in the contract and to be a reasonable estimate of the retailer's costs, and those costs cannot include lost profit. No equivalent restriction applies to large customer contracts.
Why it matters
In a large customer contract the termination sum is whatever the contract says, and commonly does price in the retailer's lost margin.
Source: AEMC, National Energy Retail Rules, rule 49A, current rules
ECMThe common abbreviation for energy conservation measure. See Energy conservation measure →
AEMO's annual ten-year outlook for electricity supply and demand in the National Electricity Market, published under clause 3.13.3A of the National Electricity Rules. It forecasts expected unserved energy against the reliability standard and indicates when new generation capacity or network augmentation would be needed.
Note: AEMO publishes a separate statement of opportunities for the Wholesale Electricity Market in the South West Interconnected System, under the Western Australian rules rather than the National Electricity Rules.
Why it matters
The forecast is restated each year and reported region by region, so the published view of a supply gap in a site's region can change from one year to the next without anything changing at the site.
Source: AEMO, ESOO and reliability forecast methodology
An over-the-counter contract exchanging the floating spot price for a fixed price over a defined period and quantity. Each contract relates to a nominated time of day in a particular region. The exchange-traded equivalent is a futures contract.
Why it matters
The quantity, region and time of day written into the contract set how much of a bill it fixes, so consumption outside those periods settles at the spot price whatever the swap covers.
Source: AER, State of the energy market 2021, chapter 2
A generating unit connected within a distribution system and without direct access to a transmission system. On-site solar, cogeneration and standby generation connected to a distribution network sit in this category.
Note: The National Electricity Rules do not use the term, dealing with the equipment instead through categories such as distribution connected units and micro resource operators. The definition above is the one in TasNetworks' AER-published network tariff application guide.
Why it matters
Network use of system charges for embedded generation are not always drawn from a published tariff. On the TasNetworks network they are individually calculated, so the network charge outcome for a site with its own generation is settled with the network rather than read off a schedule.
See also
Source: TasNetworks, network tariff application guide 2024-2029
A private electricity network within a single site, such as an apartment building, shopping centre or business park, which takes supply through one connection to the distribution network and distributes it to occupants through internal meters. The operator buys energy in bulk and sells it to occupants, which requires either a retailer authorisation or an exemption.
Why it matters
The site takes network charges once at its single connection and allocates them internally, so an occupant's rate is set by the operator's arrangements rather than by a network tariff of the occupant's own. What protections that occupant has follow whether the operator holds a retailer authorisation or an exemption, which are different regimes.
Source: AER, retail exempt selling guideline
The accredited party responsible for the market-facing functions of an embedded network, including registering child connection points so occupants can choose their own retailer.
Why it matters
Retailer choice inside an embedded network depends on this role being filled, because a child connection point cannot be registered in the market without an accredited party to do it.
Source: AEMO accreditation framework; AER embedded network material
Industry usage
The party that operates the private network and buys energy in bulk for sale to occupants. The role is commercial rather than defined in the rules, and is often combined with the exempt seller role.
Why it matters
Because the role sits in the contract rather than in the rules, what the operator owes a site comes from the deed while what it owes as a seller comes from the exemption conditions. Where one party holds both roles, the two sets of obligations still have different sources.
See also
A jurisdictional arrangement allowing a distribution network service provider to remotely turn down or switch off a customer's solar system during an energy supply emergency, used as a last resort and only when AEMO requires it. The National Consumer Energy Resources Roadmap requires each state and territory to have one. In Victoria it applies to new, upgrading and replacement solar systems above 200 kW from 25 October 2023, and from 1 October 2024 to new systems of 200 kW and under and to legacy systems whose inverter is replaced other than like for like or under warranty.
Current status: Each jurisdiction is implementing it on its own timetable and through its own instrument, so the systems covered, the capacity thresholds and the start dates differ by state and territory.
Why it matters
Where it reaches a site's own solar, generation that normally offsets consumption can be reduced for the duration, so the site draws more from the grid and pays for that energy at its contracted rate while the mechanism is active.
Source: AEMO, Minimum system load fact sheet; Victorian Department of Energy, Environment and Climate Action, Victoria's emergency backstop mechanism for solar
An exemption from part of a liable entity's Renewable Energy Target obligation, claimed through an exemption certificate issued to an entity conducting eligible emissions-intensive trade-exposed activities. The entity passes the certificate to its liable entity in return for lower electricity charges.
Note: Eligibility attaches to defined activities that produce high emissions while facing international trade competition, not to high consumption on its own.
Why it matters
Applications open on 1 August and close on 30 March, do not roll over from previous years, and cannot be lodged late, so an eligible site that misses the window carries the full certificate cost for that year.
See also
Source: Clean Energy Regulator, Renewable Energy Target liability and exemptions
A free, independent dispute resolution scheme that handles a customer's complaint about an energy business once the business's own complaints process has been exhausted. Each jurisdiction has its own: the Energy and Water Ombudsman NSW, which also takes Australian Capital Territory energy complaints, the Energy and Water Ombudsman Victoria, the Energy and Water Ombudsman Queensland, the Energy and Water Ombudsman South Australia, the Energy and Water Ombudsman Western Australia, the Energy Ombudsman in Tasmania, and in the Northern Territory the Territory's general Ombudsman rather than an industry scheme.
Note: Scheme membership and eligibility are set by each jurisdiction, and the schemes are generally open to residential and small business customers. A large customer's dispute may fall outside the scheme, leaving negotiation or the courts.
Why it matters
A complaint goes to the scheme for the jurisdiction the site sits in rather than the one where the business is based, so a portfolio spread across states deals with several schemes, each on its own eligibility terms.
Source: AER, contacts for consumers; Utilities Commission, electricity supply complaints
A category of contractual instrument under the Greenhouse Gas Protocol's Scope 2 Guidance representing information about how energy was generated, but not the energy itself. The guidance uses the term as the general label for instruments that go by other names in individual markets, among them certificates, tags, credits and generator declarations.
Why it matters
It separates the attribute from the delivered electricity, so the instruments behind a reported claim need not come from generation that physically supplied the site, and a claim is evidenced by the instruments held and retired rather than by the supply arrangement.
See also
Source: Greenhouse Gas Protocol, Scope 2 Guidance
Industry usage
An intermediary that approaches retailers on a buyer's behalf, obtains offers and arranges a supply contract. The role has no regulated definition in Australia and no licence or authorisation attaches to it. The sector's main conduct standard, the Energy Charter's National Customer Code for Energy Brokers, Consultants and Retailers, is voluntary and applies to signatories. Remuneration is commonly a commission from the retailer that wins the contract, recovered through the energy rate.
Why it matters
Where the commission is recovered through the energy rate, the cost of the arrangement is spread across the units supplied and continues for the life of the contract.
See also
Source: The Energy Charter, National Customer Code for Energy Brokers, Consultants and Retailers
The method by which a measured gas volume becomes the energy quantity billed. Volume measured at the pressure and temperature prevailing at the meter is converted to the volume the gas would occupy at standard conditions, and that corrected volume is multiplied by the heating value of the gas to give energy. AEMO's energy calculation procedures, made under rule 303(6) of the National Gas Rules, set a method for each of the three meter types used at distribution delivery points: a flow corrector meter, a data logger meter and a basic meter.
Note: In the Victorian market the standard conditions are 101.325 kPa absolute and 15 degrees Celsius. Responsibility for performing the conversion is split, with the distribution business calculating consumed energy for Tariff V sites and AEMO doing so for Tariff D sites.
Why it matters
Two figures that come from outside the meter, the pressure correction factor and the heating value, sit between the volume on the dial and the gigajoules invoiced, so a meter read that is correct can still produce a wrong energy figure.
See also
Source: AEMO, Wholesale Market Metering Procedures (Victoria), chapter 3, made under rule 303(6) of the National Gas Rules
An action or set of actions designed to improve efficiency, conserve energy or water, or manage demand. The term is defined this way in the measurement and verification protocol used in energy performance contracting, where the savings attributed to a measure are established by comparing consumption or demand before and after it is implemented, with adjustments for changes in conditions.
Why it matters
The saving attributed to a measure is calculated against an agreed baseline with adjustments for changed conditions, so it is a derived figure rather than the difference between two bills, and the baseline and the adjustments decide how large it is.
Source: Efficiency Valuation Organization, IPMVP Core Concepts
Industry usage
An intermediary engaged to advise on energy purchasing and run the procurement process, commonly also covering bill validation, metering and network tariff review, consumption reporting and contract administration. The role has no regulated definition in Australia. Remuneration varies by engagement: a fee for service or retainer paid by the buyer, a commission from the retailer, or a combination of the two. The Energy Charter's voluntary code covers consultants as well as brokers and retailers.
Why it matters
The work described continues after a supply contract is signed, so the scope and duration of the engagement are set by its own terms rather than by the term of any one supply contract.
Source: The Energy Charter, National Customer Code for Energy Brokers, Consultants and Retailers
Under the National Greenhouse and Energy Reporting (Measurement) Determination, the gigajoules of energy per unit of a fuel, measured as gross calorific value. Default factors for each fuel type are listed in Schedule 1 of the Determination.
Why it matters
It is what converts a quantity of fuel into the energy figure a report carries, so the volume on a gas invoice and the gigajoule total tested against the reporting thresholds are connected by the factor applied rather than being the same measurement.
Source: National Greenhouse and Energy Reporting (Measurement) Determination 2008, section 1.8 and Schedule 1, current determination
The convention by which the National Electricity Market names the direction of an energy flow. Direction is stated by reference to the market rather than to the customer, so energy a customer consumes is export and energy generated into the market is import. Net energy in MSATS is export less import, which makes an end user's net quantity positive and a generator's negative. The same convention applies to reactive energy.
Why it matters
The channel labelled export in a data file holds the site's consumption, so a file read on the ordinary meaning of the two words inverts a solar site's load and its generation.
Source: AEMO, MSATS Procedures: National Metering Identifier, section 6.2
In the standards sense, the policies, objectives, processes and procedures an organisation uses to manage and improve its energy performance. AS/NZS ISO 50001:2021, which adopts ISO 50001:2018 without change, sets the requirements for establishing, implementing, maintaining and improving one, covering energy policy, the energy review, energy baselines and performance indicators, operation, and performance evaluation. It does not prescribe how much energy performance must improve.
Note: The same three words are used loosely in the market for monitoring and reporting software. A platform that collects and displays consumption data may sit inside an energy management system, but it is not the management system the standard describes.
Why it matters
The standard sets requirements for the process and not for the outcome, so conformance evidences that the system is in place and operating, not that a site's consumption or cost has fallen.
Source: Standards Australia, AS/NZS ISO 50001:2021 Energy management systems
The Victorian instrument setting the rules electricity and gas retailers must follow when selling energy to Victorian customers, covering customer contracts, billing, the contents of bills, payment difficulty and disconnection. It was deemed a code of practice made under Part 6 of the Essential Services Commission Act 2001 on 1 December 2021, remade in that form on 1 March 2022, and the current version is version 7.
Note: This is Victoria's substitute for the National Energy Retail Rules, which do not apply there. A retailer selling in Victoria and in a national framework jurisdiction is complying with two different retail rule sets.
Why it matters
It is made and remade by the Victorian regulator rather than through the national rule change process, so retail obligations at a Victorian site move on a Victorian timetable and not with changes to the national rules.
See also
Source: Essential Services Commission, Energy Retail Code of Practice
A New South Wales scheme, part of the NSW Energy Security Safeguard, that creates a market for energy savings certificates. Scheme participants must surrender certificates to meet an energy savings target, and accredited certificate providers create certificates by carrying out eligible energy saving activities in homes and businesses. It is established under the Electricity Supply Act 1995, administered and regulated by IPART, with NSW DCCEEW setting the policy and legal framework.
Why it matters
Scheme costs are recovered through electricity charges in New South Wales, while certificate value only reaches a site that carries out an eligible activity there, so a business with sites in the state can carry the cost in its bills without a project bringing any of it back.
Source: IPART, about the ESS
Industry usage
A market term for a role that places energy purchasing inside a wider plan for a site or portfolio, covering matters such as demand and load shape, metering and tariff structure, on-site generation and storage, emissions reporting, and the timing and sequencing of contracting. The role has no regulated definition in Australia and no settled scope. Remuneration is commonly a fee for service or a retainer paid by the buyer.
Why it matters
Metering configuration, network tariff assignment and supply are each settled with a different party and on their own timetable, so the decisions grouped under this role do not all fall due at the same point in a site's life.
Industry usage
A wholesale electricity market design in which generators earn revenue from the energy and market services they are dispatched to provide, with no separate payment for holding capacity available. The National Electricity Market is described this way. Western Australia's Wholesale Electricity Market runs an energy market alongside a capacity market, the Reserve Capacity Mechanism.
Why it matters
In an energy-only market the cost of keeping enough capacity available arrives through wholesale and contract prices rather than as an identified capacity charge, which is why a National Electricity Market bill carries no counterpart to the Western Australian capacity line.
ENMThe common abbreviation for embedded network manager. See Embedded network manager →
ENOThe common abbreviation for embedded network operator. See Embedded network operator →
The component of an energy price covering compliance with renewable and energy efficiency schemes.
Why it matters
The amount follows the obligations those schemes impose and the price of the certificates that discharge them, both of which are set outside the supply agreement.
Source: AER, annual retail markets report 2024-25
ERAThe common abbreviation for the Economic Regulation Authority. See Economic Regulation Authority →
ESCThe common abbreviation for the Essential Services Commission. See Essential Services Commission →
ESOOThe common abbreviation for the Electricity Statement of Opportunities. See Electricity Statement of Opportunities →
Victoria's independent economic regulator, established under the Essential Services Commission Act 2001. In energy it licenses retailers and distributors, grants exemptions, makes the Energy Retail Code of Practice and other codes, sets the Victorian Default Offer, and reports on the Victorian retail market. It also regulates water, council rate caps, the Port of Melbourne and the Victorian Energy Upgrades scheme.
Note: Victoria sits outside the National Energy Customer Framework, so the ESC rather than the AER holds the retail consumer protection role in the state. The AER still regulates Victoria's electricity and gas networks.
Why it matters
Because it grants exemptions as well as licences, an embedded network at a Victorian site deals with the ESC rather than the AER on whether it may sell energy at all.
Source: Essential Services Commission, about us
A quantity of energy assigned to a billing period by estimate rather than from a reading of the meter. For small customers the Retail Rules limit when a retailer may do this, to cases where the customer consents, where metering data is not provided, or where the retailer cannot reasonably or reliably base the bill on actual data, and a small customer must receive a bill based on meter data at least once every twelve months.
Why it matters
Those limits are written for small customers. A large customer's position on estimated billing is governed by its contract.
Source: National Energy Retail Rules, rules 20 and 21, current rules
The stated standards against which offers are assessed and compared. Victorian guidance describes them as the standards of judgment, and ranking or priority, used to assess offers and compare the alternatives respondents put forward. Commonwealth guidance requires that the criteria advertised in the request documentation be the criteria used to evaluate offers, be related to the response requirements, and not be altered during evaluation without a formal amendment to that documentation.
Why it matters
Changing what is assessed once offers are in requires the request documentation to be amended, so anything a buyer wants weighed has to be in the criteria before the market is approached.
See also
Source: Victorian Government, glossary of goods and services procurement terms; Department of Finance, ethics and probity in procurement
Industry usage
A defined list of circumstances giving the other party stated rights, commonly including suspension of supply, a demand for security and termination. The list typically reaches insolvency, breach of a material provision left unremedied after notice, a failed credit assessment and a failure to provide requested security.
Why it matters
Several listed events are not failures to pay, so a buyer current on every invoice can still sit in default through a changed credit position or an unprovided guarantee.
Industry usage
A contract with no fixed end date, which continues until one party ends it. Where benefits such as discounts attach to it, they also have no end date.
Why it matters
With no end date, nothing in the contract marks a point at which its rates come up for review, and they continue until one party gives notice.
A person buying energy from an exempt seller rather than from an authorised retailer.
Why it matters
A tenant or lot owner becomes an exempt customer through the site's supply arrangement rather than by signing up to it, and stays one until the connection point serving them is registered in the market.
See also
Source: AER, retail exempt selling guideline
A person or business selling energy to occupants of a site without holding a retailer authorisation, under an exemption from the Australian Energy Regulator. Exemptions carry conditions covering pricing, billing, metering and dispute resolution.
Why it matters
An occupant of an embedded network is buying from a party that holds no retailer authorisation, so the terms governing the sale come from the exemption's conditions rather than from the authorisation regime that applies to retailers.
Source: AER, retail exempt selling guideline
Exit feeAnother name for an early termination charge. See Early termination charge →
The measure of supply reliability used in the National Electricity Market, being the energy demanded that is forecast not to be supplied because generation, demand response or interregional network capability is insufficient, expressed as a percentage of the total energy demanded in a region in a financial year. Clause 3.9.3C(a) of the National Electricity Rules sets the reliability standard at a maximum of 0.002%.
Note: Clause 3.9.3C(a1) sets a separate Interim Reliability Measure of 0.0006%, expressed the same way, which the AEMC extended to the reliability forecast for Retailer Reliability Obligation purposes until 30 June 2028. A region can be reported as exceeding one threshold and not the other.
Why it matters
It is assessed region by region and probability-weighted across a year, so a forecast breach describes the chance of a shortfall somewhere in a region rather than the risk of an interruption at any one site.
See also
Source: AEMO, ESOO and reliability forecast methodology
Consent given by a customer who has been given the relevant information and has agreed to a specific thing. The Retail Rules require it for defined changes, including an agreement to treat several premises as aggregated.
Why it matters
Where the Rules require it, a change cannot take effect through silence, inaction or a retailer's own decision, so a step such as aggregating sites needs an identifiable act of agreement from the customer.
See also
Source: National Energy Retail Rules, rule 5
A cap on how much electricity a site may send into the distribution network. A static export limit is a fixed cap. A flexible export limit varies with network conditions, with signals sent to the site's inverter to adjust exports as those conditions change.
Note: The AER's guidance note on export limits is not binding on networks. The limit that applies to a site is the one in its connection agreement, set under the relevant network's connection policy, and in some locations a static zero export limit applies.
Why it matters
The limit caps how much of an on-site generation or storage investment can be exported, which affects the return on that investment independently of the tariff paid for exports.
Source: AER, export limit guidance note, October 2024
F
Under the National Greenhouse and Energy Reporting Act, the reporting unit is an activity, or a series of activities including ancillary activities, that involves greenhouse gas emissions or the production or consumption of energy, and that either forms a single undertaking or enterprise meeting the requirements of the regulations, or is declared to be a facility by the Clean Energy Regulator.
Note: The test is the activity and the undertaking it forms rather than the premises, so a facility need not line up with a site, a lease boundary or a National Metering Identifier.
Why it matters
How activities are grouped into facilities decides which totals are tested against the facility threshold, so the same operations can fall above or below it depending on how the boundaries are drawn.
See also
Source: National Greenhouse and Energy Reporting Act 2007, section 9, current Act
The National Greenhouse and Energy Reporting threshold measured at a single facility: 25 kilotonnes of CO2-e emitted, 100 terajoules of energy produced, or 100 terajoules of energy consumed, in a financial year. Where a group entity holds operational control for only part of a year, the Act applies the threshold on a pro rata basis for the days of control.
Why it matters
One facility crossing it brings the controlling corporation's group into the scheme on its own, with no need for the group totals to be reached.
See also
Source: National Greenhouse and Energy Reporting Act 2007, sections 13(1)(d) and 13(2), current Act
The current available at a point in the network during a fault, expressed as the power it represents. The Rules define three phase fault level, measured in MVA, as the product of the pre-fault nominal voltage in kilovolts between a pair of phases, the fault current in each phase in kiloamperes for a three phase fault at that location, and the square root of three.
Why it matters
It sets the ratings the switchgear and protection equipment at a connection have to be built to, and it is fixed by the network at the point of connection rather than chosen by the site. The Rules require minimum three phase fault levels sufficient for protection systems to operate correctly, for voltage control systems to remain stable, and for the power system to stay stable after a credible contingency event.
Source: National Electricity Rules, Chapter 10 (glossary), definition of three phase fault level, and clause S5.1a.9, current rules
FCASThe common abbreviation for frequency control ancillary services. See Frequency control ancillary services →
A payment made by an electricity retailer in exchange for electricity fed into the grid from a customer's renewable generation.
Note: Arrangements differ by jurisdiction. Retailers set the rates they offer, except where a jurisdiction sets a minimum. In Victoria the Essential Services Commission determines minimum flat and time-varying rates that operate as floors, and retailers may offer more.
Why it matters
The payment applies only to energy actually exported, and the rate is a term of the retail offer rather than a scheme entitlement, so two retailers can credit the same exported kilowatt hour differently at the same site.
Source: AER, how to get value for your renewable energy and feed-in tariffs explained
A power purchase agreement made directly with a generator and settled entirely in cash against the spot price, with no electricity delivered under it and no retailer in the arrangement. The site's physical supply continues under its retail contract.
Why it matters
The retail supply contract is untouched, so a buyer runs two agreements with separate terms, counterparties and end dates, and the retail contract still governs what is delivered and billed.
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements, section 4.2
Industry usage
A working document that gathers the figures needed to calculate the value of an offer or an engagement in one place: consumption by site and period, current and offered rates by charge component, network and metering charges, fees, and the term over which each applies. It is a calculation input, not a deliverable.
Why it matters
The figure it produces is the product of the rates and the consumption and term assumed alongside them, so the same offer values differently when the assumed volume or period changes.
The Market Participant identified in MSATS as financially responsible at a connection point. It is usually a retailer, and may also be a Generator, Market Customer or Market Small Generation Aggregator. At most connection points it is the party entitled to appoint the metering coordinator.
Why it matters
The role is recorded in MSATS against the connection point, so it passes to a new retailer when that transfer takes effect in the system rather than on the date a supply contract was signed.
See also
Source: AEMO, Retail Electricity Market Procedures - Glossary and Framework; National Electricity Rules, clause 7.6.2
Transportation capacity reserved for one user, where a nomination made before the nomination cut-off time up to the reserved quantity will be scheduled, and nominations by other users on the same facility do not reduce it. The Rules define firm in those terms and treat capacity sold in the capacity auction as not firm.
Why it matters
It sets a scheduling priority attached to a quantity rather than guaranteeing gas, so capacity still has to be nominated before the cut-off time to be scheduled at all. Services ranked below it, described in the market as interruptible, as available or authorised overrun, are curtailed first when a pipeline is short.
Source: National Gas Rules, Part 25, rule 647 (definitions of firm, reserved and lower tier service), current rules
South Australia's scheme for securing long-duration dispatchable electricity capacity, established by the National Electricity (South Australia) (Firm Energy Reliability and Orderly Exit Management) Regulations 2025. A Minister declares a Firm Energy Target, a Scheme Administrator runs competitive tenders for long-term agreements, and an independent Financial Vehicle meets the underwriting and administration costs. The South Australian transmission network service provider passes those costs through to transmission customers, and they are in turn passed on to South Australian electricity consumers.
Current status: The regulations were finalised on 18 September 2025. The South Australian Government appointed the AER as a Scheme Regulator on 19 February 2026, the AER approved the Scheme Administrator's risk management framework in March 2026, and the AER published its Scheme Regulator guideline in July 2026 after a draft in April 2026. The first tender, opened in October 2025, sought 700 MW of long-duration capacity.
Why it matters
The AER sets the amount to be recovered through an annual contribution determination, so the figure is reset each year and is not fixed for the life of any agreement. It arrives inside a South Australian site's transmission charges, under no scheme name of its own, and it reaches no other state.
See also
Source: AER, Firm Energy Reliability Mechanism; AER, appointed as SA FERM Scheme Regulator and approval of the risk management framework
Industry usage
Dispatchable capacity, typically storage, hydro, gas-fired generation or demand response, used to cover periods when wind and solar output is unavailable.
There is no formal definition in the rules. The regulator uses the word in quotation marks, and ties it to contracting: firming variable generation "can support contract market participation", because a firmed position can be sold forward where an unfirmed one cannot.
Why it matters
A renewable-backed offer carries the cost of covering the hours the generation is not there, because an unfirmed position cannot be sold forward the way a firmed one can. That cost tracks the hours when wind and solar output is low, rather than the site's annual volume.
Source: AER, State of the energy market 2021, chapter 2
The change that shortened the trading interval in the National Electricity Market from 30 minutes to five, so that settlement is based on the same five-minute periods as dispatch. It took effect on 1 October 2021. Before it, the spot price for a 30-minute trading interval was the time-weighted average of six five-minute dispatch prices.
Why it matters
A buyer with spot exposure, or a contract priced off spot, is now settled against five-minute prices, so short price spikes land in full rather than being averaged down across half an hour.
Source: AEMO, five minute settlement fact sheet
A market retail contract that states when it ends, or sets a method for working out when it ends.
Why it matters
The stated end date is what an early termination charge attaches to, and it fixes the point from which the agreed rates no longer apply.
Source: National Energy Retail Rules, rule 45A, current rules
Industry usage
A consumption pattern with little variation across the day, and often across the week and year as well, so average demand sits close to maximum demand. Data centres, cold stores and continuous process plants typically have one. Expressed as a ratio, a flat load is a high load factor.
Why it matters
With average demand sitting close to maximum, there is little consumption available to move between periods, so a tariff that prices periods differently has less to work on at a flat-load site than at a peaky one.
Industry usage
A defined event beyond a party's reasonable control, and not reasonably capable of being prevented by it, which suspends that party's obligations for as long as it is prevented from performing them. No Australian statute defines the term, and the relief comes from the clause rather than from any implied rule.
Note: Suspension usually stops short of payment. Drafting commonly states that a force majeure event does not suspend any obligation to pay amounts owed to the other party.
Why it matters
Where the payment obligation survives the suspension, a buyer can owe charges for a period in which the counterparty's own performance was excused.
Industry usage
The volume a buyer declares it will consume in each contract year, stated in the schedule and used to price the agreement. The minimum and maximum volumes that trigger adjustment charges are usually calculated as percentages of it.
Why it matters
Because the tolerance bands are derived from this figure rather than from actual consumption, a forecast set high raises the minimum the buyer must reach to avoid a shortfall charge. Adding or removing connection points during the term commonly leaves the forecast unchanged unless the parties expressly agree otherwise.
Industry usage
The set of prices at which electricity for future periods can currently be contracted, read across successive quarters and years. It is specific to a region and to a contract profile, so a base curve and a peak curve differ.
No regulator or exchange definition could be located. Worth stating plainly in the entry: a forward curve is a market observable at a point in time, not a forecast.
Why it matters
An offer is priced off the curve on the day it is struck, so two quotes obtained weeks apart are not comparable even from the same retailer. The curve that applies depends on the region and the contract profile, so a base price does not describe a site whose load sits in peak hours.
See also
Services AEMO procures to hold power system frequency within its operating limits. They divide into regulation services, which correct the small continuous imbalances between supply and demand, and contingency services, which restore frequency after an event such as a generator, load or network element tripping. Contingency services are procured in separate markets by response speed.
Why it matters
AEMO recovers the cost of these services from market participants, and it reaches a buyer either as a separate market charge where costs are passed through, or inside the energy rate where they are bundled. Either way the amount moves with system conditions rather than with the site's consumption.
Source: AEMO, guide to ancillary services in the National Electricity Market
FRMPThe common abbreviation for financially responsible market participant. See Financially responsible market participant →
Industry usage
A retail power purchase agreement under which a fixed price applies to all of a buyer's consumption, covering both the part matched by the generator's output and the part supplied when output falls short. It is one of three firming models, alongside partially firmed and spot-exposed.
Why it matters
The retailer holds the difference between what the generator produces and what the site uses, so periods of low renewable output reach the buyer at the contracted price rather than at the price prevailing then.
Source: Business Renewables Centre Australia, Renewable Energy Power Purchase Agreements in Queensland
G
AEMO's public register of natural gas infrastructure information, operated under the National Gas Law and Part 18 of the National Gas Rules. Operators of designated pipelines, storage facilities and production facilities must submit data including nameplate ratings, short and medium term capacity outlooks, daily production and flow, storage levels and nominations, which AEMO publishes.
Note: There are two boards. The national board covers New South Wales, the Australian Capital Territory, Queensland, South Australia, Victoria and Tasmania. Western Australia has a separate bulletin board, launched in 2013, with its own zones that AEMO must review at least once every five years.
Why it matters
The published capacity, flow and outlook data is free and is drawn from the same submissions sellers make, so it can be read before a gas tender without asking a supplier for it. Which board carries a site's region depends on the state the site sits in.
Source: National Gas Rules, Part 18, Division 5, current rules; AEMO, Western Australian GBB zones review
The mandatory code of conduct for the east coast gas market, made as the Competition and Consumer (Gas Market Code) Regulations 2023 under the Competition and Consumer Act 2010 and in effect from 11 July 2023. It applies to covered gas producers and their affiliates selling to wholesale customers, requires good faith conduct and set information in offers, and prohibits supply of regulated gas above a reasonable price determined under the Code, set at $12 a gigajoule at commencement and reviewable by the ACCC. The ACCC monitors and enforces it.
Note: Several instruments are loosely called a gas code. This entry is the Commonwealth code governing wholesale gas supply. Separate retail market procedures and gas distribution codes operate under the National Gas Rules and under state instruments, and the Code does not apply to trades on the Victorian declared wholesale gas market or the short term trading markets. Exemptions from the price cap exist for producers making domestic supply commitments.
Why it matters
It governs supply from covered producers to wholesale customers, so a business buying gas on a retail contract is not a party to it and the reasonable price in the Code is not a cap on what that contract charges.
Source: ACCC, compliance guidelines for gas industry as new Gas Market Code takes effect
The composition and energy limits gas must meet at the point it is injected into a transmission or distribution system. Under the Rules the applicable specification is the standard gas quality specifications drawn from AS 4564, unless another standard has been approved for that injection point by AEMO or the distributor, or authorised under the law of the relevant jurisdiction.
Why it matters
A specification attaches to an injection point rather than to a customer, and the Rules provide that a market participant is taken to accept that the gas delivered to it may not match the specification of the gas injected on its behalf. Heating value, which converts metered volume into the gigajoules billed, varies within the limits the specification allows.
Source: National Gas Rules, Part 19, rule 200, and Part 20, rule 364, current rules
AEMO's annual forecast of gas consumption and maximum gas demand, together with its assessment of whether the central and eastern gas markets can supply that demand across a twenty-year outlook period. It is published under section 91DA of the National Gas Law and Part 15D of the National Gas Rules. The 2026 edition was published in March 2026, based on information available as at 28 February 2026.
Note: AEMO publishes a separate statement of opportunities for the Western Australian gas market.
Why it matters
The twenty-year horizon rolls forward each year, so the date at which a southern supply shortfall is forecast moves between editions without anything changing at a site. That forecast is the evidence most often cited in the supply-risk section of a gas tender and in arguments about contract length.
See also
Source: AEMO, 2026 Gas Statement of Opportunities
Industry usage
A contract for the supply of the gas commodity itself, as distinct from a contract to transport it. It sets the contract quantities, the price and any price review mechanism, the delivery point at which the gas is handed over, and the take-or-pay and flexibility terms.
Note: The phrase is market usage and is defined in neither the National Gas Rules nor the Gas Market Code Regulations. The Regulations use the term agreement for supply of regulated gas, and impose procedural, price and good faith requirements on those agreements where the supplier is a covered supplier.
Why it matters
It covers the commodity alone, so the price in it is not the delivered cost of gas at a site, and moving that gas to the site is contracted separately.
See also
Source: Competition and Consumer (Gas Market Code) Regulations 2023, Parts 4 and 5
AEMO's voluntary exchange for standardised short-term physical gas products, with trading locations at Wallumbilla, operating since March 2014, and Moomba, from 1 June 2016. The product suite includes balance of day, day ahead, daily, weekly and monthly contracts. AEMO centrally settles transactions, manages prudential requirements and publishes reports.
Why it matters
It offers a route to short-term gas volumes without a bilateral supply agreement, but only at those two locations, so gas bought there reaches a site through whatever haulage runs from them and not at the site itself.
See also
Source: AEMO, Gas Supply Hub industry guide
The contract between a pipeline service provider and a user for transporting gas on that pipeline. It names the services taken, the receipt and delivery points, the maximum daily and hourly quantities, and the nomination, imbalance and overrun terms. The National Gas Rules call the equivalent instruments facility agreements, split between primary facility agreements and operational transportation service agreements.
Why it matters
It is a separate contract from the gas supply agreement, so a business buying gas at the field holds two: one for the commodity and one for moving it. Delivered gas bought from a retailer bundles both, and the transportation terms then sit behind the retailer rather than with the business.
Source: AER, access arrangement access principles (definition of Gas Transportation Agreement); National Gas Rules, Part 24, rule 593
Gate meterAnother name for the parent meter. See Parent meter →
The Victorian instrument setting the exemption framework for selling energy without a licence. Victoria regulates separately from the national framework, and its price cap for exempt sellers references the Victorian Default Offer rather than a local area retailer's standing offer.
Why it matters
A Victorian site's exempt selling price is measured against the Victorian Default Offer, so an owner with sites in Victoria and in national framework states is working to two different caps for the same kind of arrangement.
Source: Essential Services Commission, electricity licence exemptions
A unit of energy equal to 1,000 megajoules, or 1,000,000,000 joules. It is the usual contracting and invoicing unit for gas supplied to commercial and industrial customers in Australia.
Conversions: 1 GJ = 1,000 MJ = 277.7778 kWh = 0.2777778 MWh. One megawatt hour is 3.6 GJ.
Why it matters
Commercial and industrial gas contracts are written per gigajoule while many invoices meter in megajoules, so the volume on the contract and the volume on the bill are expressed in units a thousand apart.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement), current regulations
GJThe common abbreviation for gigajoule. See Gigajoule →
Industry usage
A development where the embedded network has not yet been established, so the arrangement is set from the start rather than inherited.
Why it matters
The term, the residual value formula and the payment arrangements are all settled at this stage, and they apply to the owners and occupants who arrive later rather than being negotiated with them.
See also
A government-managed accreditation program under which electricity retailers sell renewable electricity products, with the renewable generation independently audited. The New South Wales department is the program manager, on behalf of the National GreenPower Steering Group.
Why it matters
The product is bought on top of ordinary supply, so it adds a cost per unit and leaves the electricity delivered to the site unchanged. Accreditation and independent audit are what separate it from a retailer's own renewable description of a product.
Source: greenpower.gov.au
Industry usage
The physical and contractual link between a site and the electricity network at an agreed connection point. The Rules use "connection" and "connection point"; "grid connection" is the market's shorthand for the same thing.
Note: Which part of the Rules governs a connection depends on what is connecting. Chapter 5A covers connections for retail customers and real estate developers, including micro embedded generators. Chapter 5 covers generator connections and connections to transmission and distribution networks more broadly.
Why it matters
The connection point is both the boundary between the network's assets and the site's own wiring and the point a NMI identifies, so network charges, metering and any export limit attach to it rather than to whoever occupies the site.
See also
Source: National Electricity Rules, chapters 5 and 5A, current rules
GSAThe common abbreviation for gas supply agreement. See Gas supply agreement →
GSHThe common abbreviation for the Gas Supply Hub. See Gas Supply Hub →
GSOOThe common abbreviation for the Gas Statement of Opportunities. See Gas Statement of Opportunities →
Industry usage
A clause stating that all amounts under the contract are GST exclusive, and that the charges payable are increased by the amount of GST once GST becomes payable on a taxable supply under the contract.
Note: GST itself is statutory. The GST Act sets out when a supply is a taxable supply, fixes the amount of GST at 10% of the value of the supply, and governs tax invoices. The gross-up clause allocates that amount to the buyer rather than creating the liability.
Why it matters
A rate quoted under this drafting is invoiced with 10% added, so comparing a GST exclusive rate from one offer against a GST inclusive rate from another understates the first.
Source: A New Tax System (Goods and Services Tax) Act 1999, sections 9-5, 9-70 and 29-70, current Act
GTAThe common abbreviation for gas transportation agreement. See Gas transportation agreement →
H
Components of the voltage or current waveform at integer multiples of the supply frequency, produced by equipment that draws current non-linearly, such as variable speed drives, rectifiers and switch-mode power supplies. The Rules set harmonic voltage distortion as a system standard by reference to the compatibility levels in IEC/TR 61000.3.6, and require network service providers to establish planning levels for their own networks on that basis.
Why it matters
A network allocates harmonic emission limits when a site applies to connect, so the limits a site's equipment has to work within are settled at connection rather than afterwards. The Rules also provide that, as far as practicable, the cost of managing distortion beyond the automatic access standard falls on the users whose facilities cause it.
Source: National Electricity Rules, clauses S5.1a.6 and S5.1.6, current rules
The service of transporting gas through a pipeline or a distribution network, charged separately from the gas itself. Gas distributors publish their regulated tariffs as haulage reference services, with a site's tariff set by its annual consumption and its maximum hourly quantity.
Why it matters
The charge is for moving the gas rather than for the gas, so it tracks the network's approved tariffs and the access arrangement behind them rather than a contracted commodity price. A fixed gas price therefore does not fix the haulage component of the bill unless the contract says so.
Source: AER, Multinet annual tariff report (haulage reference service tariffs V, D and L); National Gas Rules, Part 8 (access arrangements for scheme pipelines)
A voluntary commitment negotiated between the Commonwealth Minister for Resources and east coast liquefied natural gas exporters, under which the exporters commit to supply sufficient, competitively priced gas to Australian users and to offer uncontracted gas to the domestic market.
Current status: The Department of Industry, Science and Resources records the agreement as in place until 1 January 2026. Exposure drafts for a Domestic Gas Reservation Bill 2026 were released for consultation between 10 and 24 September 2026.
Why it matters
A buyer is not a party to it and it sets no price, so it bears on which domestic offers exist and not on the terms of any offer received.
See also
Source: Department of Industry, Science and Resources, domestic gas supply
The energy content of gas per unit of volume at standard conditions, expressed in megajoules per standard cubic metre. It is the factor that turns a corrected gas volume into an energy quantity. AEMO calculates and publishes heating values for the Victorian market, and the Essential Services Commission's gas distribution code of practice governs how they are applied there.
Note: Gas composition varies with the source of supply and with flow conditions, so the heating value applied to a site is a figure published for an area and a period rather than a constant.
Why it matters
The energy billed moves with the heating value even where the volume taken does not, so the same volume delivered in two different periods or areas produces two different gigajoule figures.
See also
Source: AEMO, Wholesale Market Metering Procedures (Victoria), chapter 3
Entering financial contracts that fix a price for future electricity, so that movements in the spot price are offset.
Why it matters
A hedge fixes a price for a quantity, not the quantity itself, so consumption above or below the hedged volume still settles against the spot price. The contract is financial, so it changes the price outcome and not where the electricity physically comes from.
See also
Source: AER, State of the energy market
A wholesale electricity price outcome the AER counts and reports where a region's 30-minute price exceeds $5,000 per megawatt hour. The AER publishes the count by region each quarter alongside the quarter's average prices.
Note: The criteria for the significant price outcomes the AER must monitor and report on are set in its significant price reporting guidelines, made under the National Electricity Rules rather than fixed in the Rules themselves.
Why it matters
The count records how often a region reached that level, not how long it stayed there or how much energy was consumed while it did, so a quarter with few events can still carry a higher average price than one with many.
See also
Source: AER, industry charts; National Electricity Rules, clauses 3.13.7 and 3.13.7A, current rules
A voltage greater than 1 kV. Networks use the term for their sub-transmission and distribution feeders, and for sites that take supply directly at those voltages rather than through a shared distribution substation.
Note: Connecting at high voltage changes which tariff class a site falls into, because classes are constituted partly on the nature of the connection. A high voltage class in a network's schedule usually carries different charging parameters and a different minimum chargeable demand from the low voltage class in the same schedule.
Why it matters
A site taking supply at high voltage usually owns and maintains the transformer and switchgear that step the voltage down on its side of the connection point, so costs the network carries for a low voltage site sit with the customer instead.
Source: National Electricity Rules, chapter 10 (glossary), current rules
The ability of a network to accept energy generated by consumer energy resources without affecting power quality to the point where the network stops operating within its defined operational limits, such as voltage or thermal limits. The AER notes that it varies by location and by time, with consumption and the level of generation connected.
Note: Networks assess hosting capacity by different methods, probabilistic or deterministic, and the AER's position is that assessments and the methodologies behind them should be published so export limits are not set conservatively low.
Why it matters
The export a network will accept is a property of the local network at the time of assessment rather than of the site's equipment, so identical installations on different feeders can be offered different limits.
Source: AER, export limit guidance note, October 2024
Industry usage
Industry shorthand for data centre capacity built at the largest scale, normally a single operator's purpose-built facility or campus serving cloud or AI workloads. There is no regulated definition and no agreed capacity threshold, so the word describes an operating model rather than a size.
Why it matters
The word says nothing about the load a facility presents at its connection point, so two facilities both described this way can sit on different sides of any megawatt threshold a network or market framework sets.
I
The difference between the gas a shipper puts into a pipeline and the gas taken out at the delivery points, accumulated over time. The Operational Transportation Service Code requires a shipper to use reasonable endeavours to bring its accumulated imbalance to zero at the end of each day, sets an imbalance allowance, and provides for an imbalance charge where the accumulated imbalance exceeds that allowance.
Note: The Victorian declared wholesale gas market uses imbalance in a separate, defined settlement sense, where a participant's scheduled and actual imbalances determine its imbalance and deviation payments.
Why it matters
The position is measured against the quantities the pipeline scheduled, so it moves whenever actual use differs from what was nominated, independently of how much gas the business bought. The service provider can require a shipper to adjust its receipts or deliveries to correct an imbalance, which changes what a site may take inside a day already scheduled.
Source: Operational Transportation Service Code, clauses 12 and 12.4, as amended by the AER; National Gas Rules, Part 19, rule 235 (imbalance payments and deviation payments)
Industry usage
A promise to cover a defined category of the other party's loss. It operates on the trigger the clause states rather than on proof of breach, so it can be called on in circumstances where no breach has occurred.
Why it matters
An indemnity sits outside the liability cap unless the drafting expressly brings it inside, so an agreement with a negotiated cap can still carry uncapped exposure through its indemnities.
An exemption granted on application, required where a seller does not fit a deemed or registrable class. Retrofitted embedded networks generally need one where consent cannot be obtained from every affected customer.
Why it matters
Adding an embedded network to an occupied building turns on either consent from every affected customer or a decision the regulator can refuse, so the arrangement is not settled by the site owner alone.
See also
Source: AER, retail exempt selling guideline
The megawatt quantity AEMO determines for each Market Participant in Western Australia's Wholesale Electricity Market, setting that participant's share of the Reserve Capacity Mechanism's cost. It is determined under clause 4.28.7 of the Electricity System and Market Rules, revisable under clause 4.28.11A, recalculated monthly in accordance with Appendix 5, and based for an existing interval meter on the median metered consumption during the twelve Peak SWIS Trading Intervals of the preceding Hot Season.
Current status: Stage two of the Coordinator of Energy's review of the Reserve Capacity Mechanism assessed the consequences for the Individual Reserve Capacity Requirement, with detailed design to be put forward as proposed rule amendments at stage three.
Why it matters
The quantity turns on consumption in twelve identified peak intervals rather than on annual volume, so two Western Australian sites with the same yearly usage can carry different capacity costs according to their load at those moments. The calculation applies to Western Australian loads only.
See also
Source: AEMO, WEM Individual Reserve Capacity Requirement calculations, version 2.2, published 7 March 2025
Defined in the Rules as the contribution to the capability of the power system to resist changes in frequency by means of an inertial response from a generating unit, bidirectional unit, network element or other equipment. An inertial response is the immediate, inherent electrical power exchange from a device on the power system in response to a frequency disturbance, and power system inertia is the aggregate equivalent inertia of all devices capable of providing one.
Note: AEMO divides the national grid into inertia sub-networks and determines the inertia levels each must hold for satisfactory and secure operation, under clause 5.20B of the Rules and its Inertia Requirements Methodology.
Why it matters
An inertial response is the inherent physical behaviour of connected equipment rather than an output dispatched on instruction, and the levels required are set for each inertia sub-network rather than for individual connection points.
Source: National Electricity Rules, Chapter 10 glossary, quoted in AEMO, Inertia Requirements Methodology, section 2.1.1
Industry usage
A payment or capital works contribution made by an embedded network operator towards the site's electrical infrastructure, usually recovered across the term of the agreement.
Why it matters
Recovery across the term is what sets how long the agreement needs to run, and the amount still unrecovered is usually what a residual value at the end is calculated from.
See also
AEMO's roadmap for the National Electricity Market, which the National Electricity Rules require it to produce every two years under clause 5.22, across a planning horizon of at least twenty years. It sets an optimal development path, being the least-cost combination of generation, storage and network investment to meet forecast consumer needs and government policies. The 2026 plan was published on 25 June 2026 and runs to 2050.
Why it matters
Transmission projects become actionable through this plan and are then recovered through transmission charges, so it indicates where network cost is heading for a site's region years before any charge changes. It covers the National Electricity Market, so it describes nothing about a Western Australian site.
See also
Source: AEMO, 2026 Integrated System Plan; National Electricity Rules, clause 5.22, current rules
A transmission line, or group of transmission lines, that connects the transmission networks in adjacent regions. A regulated interconnector is one subject to the transmission service regulation and pricing arrangements in Chapter 6A of the Rules, which distinguishes it from a market network service.
Why it matters
Each National Electricity Market region sets its own spot price, and flows across interconnectors are what hold those prices close to one another. When an interconnector is constrained or out of service, the regions either side can price very differently, so a multi-state portfolio's wholesale outcome is determined region by region rather than nationally.
Source: National Electricity Rules, Chapter 10 definitions, current rules
A load able to be disconnected, manually or automatically, which is provided for the restoration or control of power system frequency by AEMO to cater for contingency events or shortages of supply.
Note: The market also uses the phrase loosely for any load a contract permits to be cut, including interruption arranged directly with a retailer or a network. The defined term is narrower and attaches to load made available to AEMO for frequency and reserve purposes.
Why it matters
A clause letting a retailer or a network interrupt a site's load does not make that load interruptible load in the Rules' sense, because the defined term requires the load to be available to AEMO for power system purposes.
Source: National Electricity Rules, chapter 10 (glossary), current rules
Consumption data recorded by a meter in intervals that correspond to, or divide into, a market trading interval. In the National Electricity Market a trading interval is five minutes, and older meters record in thirty-minute intervals.
Why it matters
Interval data shows when energy is used, not just how much. Retailers price from it, network demand charges are calculated from it, and without it an offer is priced on assumption rather than on the site's actual pattern.
Source: AEMC, National Electricity Rules, chapter 10 definitions, current rules
The field in an interval metering data file stating the recording period of each value, in minutes. The Meter Data File Format Specification permits 1, 5, 10, 15 and 30 minutes.
Why it matters
The number of values in a day follows from it, so a file read on an assumed period returns totals out by the ratio between the two. It also fixes the finest resolution at which the site's demand can be established from its own data.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, NMI data details record, published with the metering procedures
The amounts AEMO determines as payable after an AEMO intervention event, being the issue of a direction or the exercise of the Reliability and Emergency Reserve Trader. Directed participants and holders of exercised reserve contracts are compensated, as are affected participants whose dispatch was changed by the intervention, and submissions can be made for additional amounts covering direct costs such as fuel, incremental maintenance and staffing. Compensation for market suspension pricing schedule periods runs through separate provisions, and the AEMC administers claims arising from the application of the administered price cap or administered floor price.
Why it matters
Recovery falls on market customers in the regions that benefited from the intervention, weighted by the energy consumed at the connection points each is financially responsible for. A buyer's share therefore follows its own consumption during the event rather than the size of its contract or its retailer's market share.
Source: AEMO, Guide to Intervention Pricing
Invoice validationAnother name for bill validation. See Bill validation →
IRCRThe common abbreviation for the Individual Reserve Capacity Requirement. See Individual Reserve Capacity Requirement →
ISPThe common abbreviation for the Integrated System Plan. See Integrated System Plan →
K
The energy delivered by a power of one kilowatt sustained for one hour. It is an Australian legal unit of measurement of work and energy, and it is the standard unit in which electricity consumption is metered and billed. Because a watt is one joule per second and an hour is 3,600 seconds, one kilowatt hour is 1,000 x 3,600 joules, that is 3,600,000 joules, or 3.6 megajoules exactly.
Conversions: 1 kWh = 3.6 MJ. 1,000 kWh = 1 MWh. 1 GJ = 277.7778 kWh. 1 MJ = 0.2777778 kWh.
Why it matters
Electricity is metered and billed in kilowatt hours while contract and wholesale prices are quoted per megawatt hour, so one price appears as cents per kilowatt hour on an invoice and as dollars per megawatt hour in a contract, a thousand units apart.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement), current regulations
Kilovolt-ampere, the unit of apparent power. One kVA is 1,000 volt-amperes. The regulator describes apparent power as a measure of the current and voltage, which "will differ from real power when the current and voltage are not in phase".
Why it matters
Networks commonly bill demand in kVA rather than kW, so a site with a poor power factor is charged for apparent power it never converts into useful work.
See also
Source: AER, tariff structure statement glossary
Kilovolt-ampere reactive hour, the unit of reactive energy. The Rules define reactive energy as a measure, in varhour, of the alternating exchange of stored energy in inductors and capacitors, being the time integral of the product of voltage and the out-of-phase component of current flow across a connection point. One kVArh is 1,000 varhours.
Why it matters
It is recorded as its own channel in a large site's interval data, separate from the active energy channels, and it is what makes a power factor or excess reactive charge checkable against the meter. A data file supplied without the reactive channels cannot be used to verify one.
Source: National Electricity Rules, Chapter 10 (glossary), definition of reactive energy, current rules
Kilowatt, the unit of real power, being the rate at which energy is used. One kilowatt is 1,000 watts. Power is a rate; energy is the quantity that accumulates, which is why a kilowatt hour is one kilowatt of power used for one hour.
Why it matters
The two sides of an electricity bill are measured in different units, so a reduction in kilowatt hours does not necessarily reduce the kilowatt peak that a demand charge is set from. Equipment is rated in kW, which describes what a site could draw rather than what it consumes.
See also
Source: AER, tariff structure statement glossary
kWhThe common abbreviation for kilowatt hour. See Kilowatt hour →
L
A condition AEMO declares for a region when it determines, under its Reserve Level Declaration Guidelines, that the probability of load shedding other than of interruptible load is, or is forecast to be, more than remote. Three levels are declared, in increasing severity. LOR1 applies where the consecutive occurrence of both the largest and the second largest relevant credible contingency events would cause load shedding, or forecast reserves fall below that measure. LOR2 applies where the largest relevant credible contingency event alone would cause it, or forecast reserves fall below that measure. LOR3 applies where load shedding is occurring because of a reserve shortfall, or forecast reserves are at or below zero.
Why it matters
The levels describe reserve margins, so a declaration in a buyer's region is not in itself a loss of supply. Because they are published ahead of time, a site with flexible load or on-site generation has notice to reduce its draw before AEMO reaches for load shedding.
See also
Source: AEMO, Reserve Level Declaration Guidelines
A business customer consuming energy at or above the upper consumption threshold. Under the national regulations the threshold is 100 MWh a year for electricity and 1 TJ a year for gas, and some jurisdictions set a different figure: South Australia 160 MWh, Tasmania 150 MWh, Victoria 40 MWh under its own framework. The Northern Territory sits outside the national retail framework and applies its own bands under the Territory's Electricity Industry Performance Code, with a small customer threshold of 160 MWh a year and a separate large customer band above 750 MWh.
Why it matters
The consumer protections in the Retail Law are written for small customers. The Law states that its customer protection Part does not apply to the relationship between retailers and large customers. Crossing the threshold changes what the contract has to do, because the rules stop doing it.
Source: AER, Retail Exempt Selling Guideline version 7, August 2025; Victorian threshold from the ESC
Industry usage
A descriptive term for a single customer load big enough to matter to network and power system planning. It carries no definition of its own in the Rules, and no single threshold applies across the frameworks that use it.
Note: The adjacent regulated term is the large inverter-based load. In March 2026 the AEMC published a draft rule that would define and classify large inverter-based loads in the Rules and raise the threshold for facilities connecting to a distribution network from 5 MW to 30 MW, so that disturbance ride-through standards apply to the facilities most able to affect power system security. Submissions closed on 7 May 2026, with a final rule to follow.
Why it matters
Obligations attach to the defined terms in each framework rather than to this phrase, so whether a facility counts as large depends on which framework is being applied, and a threshold in a draft rule has no effect until a final rule is made.
A certificate created for each megawatt hour of electricity generated by an accredited renewable power station under the Renewable Energy Target. Certificates are traded separately from the electricity itself and are surrendered to make a renewable claim.
Why it matters
A renewable supply claim is a certificate transaction. The certificate conveys the renewable attribute of generation; the physical electricity delivered to a site comes from the grid mix regardless.
Source: Clean Energy Regulator, voluntary offsetting and surrender
Any type 5 or type 6 metering installation in operation, other than a type 5 installation capable of remote acquisition. The term was added to the Rules by the Accelerating Smart Meter Deployment Rule, which requires each local network service provider to publish a legacy meter replacement plan and sets the objective of replacing all legacy meters with type 4 metering installations between 1 December 2025 and 30 November 2030.
Note: Legacy meter and accumulation meter overlap but are not the same. Every type 6 accumulation installation in service is a legacy meter, and so is a manually read interval installation without remote acquisition, which is not an accumulation meter at all.
Why it matters
The classification turns on the installation type and whether the meter can be read remotely, not on its age, so a recently installed meter can be a legacy meter and fall within a replacement plan.
Source: National Electricity Amendment (Accelerating smart meter deployment) Rule 2024 No. 20, clause 11.177.1, final rule
LGCThe common abbreviation for a large-scale generation certificate. See Large-scale generation certificate →
A purchase of a project's large-scale generation certificates without taking a price position on the electricity, leaving the buyer's existing retail supply contract in place. The certificates are surrendered against consumption to support a renewable claim.
Current status: The Renewable Energy Target ends on 31 December 2030 and no further large-scale generation certificates are created for generation after that date. The Renewable Electricity Guarantee of Origin scheme continues beyond it, so an arrangement running past 2030 spans two certificate schemes.
Why it matters
Physical supply and the retail contract are unchanged, so the arrangement moves no rate on the bill and the renewable claim rests on the certificate surrender alone.
See also
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements, section 4.1; Clean Energy Regulator, Renewable Energy Target
Industry usage
A ceiling on what each party can be required to pay the other, commonly expressed as the total charges paid in the twelve months before a claim and applied to all claims in a year in aggregate. Stated categories usually sit outside it, including death or personal injury, damage to property, fraud or wilful misconduct, and any liability that cannot be limited by law.
Note: The Australian Consumer Law makes a contract term void to the extent it excludes, restricts or modifies the consumer guarantees or liability for failing to comply with them, so a cap does not reach that liability. For services other than those of a kind ordinarily acquired for personal, domestic or household use, section 64A permits a term limiting that liability to supplying the services again or paying the cost of having them supplied again, unless the buyer establishes that reliance on the term is not fair or reasonable.
Why it matters
Where the cap is measured by charges paid, it scales with the buyer's own spend, so the same failure leaves a smaller buyer with a smaller recoverable amount.
Source: Australian Consumer Law, sections 64 and 64A, in Competition and Consumer Act 2010 Schedule 2
LMSPThe common abbreviation for local metering service provider. See Local metering service provider →
An estimate of the export parity price a gas supplier could expect for exporting its gas, worked out by taking the price obtainable for liquefied natural gas and deducting the supplier's costs of converting the gas to LNG and shipping it to the destination port. The ACCC publishes a series of these estimates for the east coast gas market.
Why it matters
It describes what a seller could earn by exporting rather than what gas costs delivered to a site, so transportation and retail charges sit above it, and it is an estimate of an alternative rather than a price at which gas is offered.
See also
Source: ACCC, LNG netback price series
LOAThe common abbreviation for a letter of authority. See Letter of authority →
Industry usage
The ratio of average demand to peak demand over a period, expressed as a percentage. A site consuming 100 kW steadily has a load factor near 100%; a site averaging 100 kW but peaking at 400 kW has a load factor of 25%.
Why it matters
Demand charges are set by the peak, while energy charges follow the total. A low load factor means a larger share of the bill is fixed by a short peak rather than by consumption.
Comparing a site's consumption interval by interval against a generator's output over the same intervals, to establish how much of the load the generation covers, how much must be supplied from elsewhere, and how much generation exceeds consumption and is sold to the market.
Why it matters
It is the analysis that sizes the balancing portion, so two sites with the same annual consumption and the same generator can carry different firming costs depending on the hours they use electricity in.
Source: Business Renewables Centre Australia, Renewable Energy Power Purchase Agreements in Queensland
Reducing or disconnecting load from the power system, other than by means of wholesale demand response. It is the last measure available when generation and reserves cannot meet demand, and it is the outcome AEMO's lack of reserve declarations are calibrated to avoid.
Why it matters
This is the event that stops supply rather than moving a price, and a supply contract does not exempt a site from it. Load a business has made available as interruptible load is reduced ahead of it and sits outside the measure AEMO assesses reserve levels against.
See also
Source: National Electricity Rules, Chapter 10 definitions, current rules
The retailer designated for a distribution area, whose standing offer price sets the cap an exempt seller may charge. An exempt seller must not charge more than the local area retailer would charge for the same supply, applied component by component.
Why it matters
This is the price protection for occupants of an embedded network, and it is written for small customers. A large customer inside an embedded network does not get the same cap.
See also
Source: AER, retail exempt selling guideline, condition 7
Industry usage
Market shorthand for the distributor-supplied metering role that applied before metering was opened to competition, when the local network service provider provided and maintained most meters and held the metering obligations at the connection point.
Note: The phrase has no definition in the Rules or in AEMO's procedures, and the regulated role it describes was the responsible person, which for type 5, 6 and 7 metering installations was typically the local network service provider. The responsible person was replaced by the metering coordinator on 1 December 2017 under the National Electricity Amendment (Expanding competition in metering and related services) Rule 2015 No. 12. AEMO's systems still carry the role code RP for the metering coordinator.
Why it matters
The role code RP that survives in AEMO's systems now identifies the metering coordinator, so a record showing RP at a connection point does not mean the distributor still provides the metering there.
Source: AEMC, Expanding competition in metering and related services; AEMO, Retail Electricity Market Procedures - Glossary and Framework, section 2.8
The scope 2 accounting method that reflects the average emissions intensity of the grids on which energy consumption occurs, using mostly grid-average emission factor data. Grid-average factors are not adjusted for contractual claims made by suppliers or end users.
Note: The Greenhouse Gas Protocol requires companies operating in markets where contractual instruments are available to report scope 2 under both this method and the market-based method, labelled separately. This is dual reporting.
Why it matters
A renewable supply contract or certificate purchase changes the market-based figure and leaves the location-based figure unchanged, so the two numbers move independently and are not alternatives to choose between.
Source: Greenhouse Gas Protocol, Scope 2 Guidance
A New South Wales revenue underwriting contract for generation, long-duration storage or firming capacity, awarded by competitive tender by the Consumer Trustee under the Electricity Infrastructure Investment Act 2020. The costs are paid from the New South Wales Electricity Infrastructure Fund. The AER makes an annual contribution determination under section 56 of that Act, the Scheme Financial Vehicle recovers the determined amount through contribution orders issued to the New South Wales distribution network service providers, and those costs are passed through to retailers, which recover them from New South Wales customers through retail bills.
Why it matters
The cost arrives inside a New South Wales site's distribution and retail charges, with nothing on the bill naming the scheme, and the AER's determination resets it each year. No other jurisdiction recovers costs under this Act.
See also
Source: AER, NSW Electricity Infrastructure Fund contribution determination guideline, September 2026
LORThe common abbreviation for lack of reserve. See Lack of reserve →
LOR1The common name for the least severe of the three lack of reserve levels. See Lack of reserve →
LOR2The common name for the middle of the three lack of reserve levels. See Lack of reserve →
LOR3The common name for the most severe of the three lack of reserve levels. See Lack of reserve →
Industry usage
A voltage at or below 1 kV, the level at which most sites take supply. Nominal low voltage supply in Australia is 230 volts single phase and 400 volts three phase.
Note: The Rules define high voltage as a voltage greater than 1 kV but do not define low voltage, so the boundary is the complement of the defined term. Networks commonly divide their low voltage customers further, with a separate class above a stated demand or annual consumption level, and connection at high voltage instead moves a site to a different tariff class again. Both splits sit in the relevant network's tariff schedule.
Why it matters
Equipment rated for 400 volts needs a three phase supply, so a site connected single phase has to have the connection itself altered by the network before it can run that equipment.
Source: National Electricity Rules, chapter 10 (glossary), by reference to the definition of high voltage, current rules
M
Industry usage
An obligation to return premises or equipment to a defined condition at the end of an agreement.
Why it matters
The cost falls at the end of the term on whichever party the agreement names, and it sits separately from any residual value, so an exit can carry both.
See also
Industry usage
Gas a buyer has paid for under a take-or-pay obligation without taking it, and which the agreement allows it to take in a later period at no further charge. The conditions, including any period within which it must be taken, are set by the agreement.
Why it matters
The value of a shortfall is recoverable as gas rather than as money, and only through later consumption above the contracted volume, so a buyer whose demand has fallen permanently has no route to take it back.
A factor representing the marginal transmission losses between a transmission network connection point and the regional reference node for that region. AEMO calculates one for each connection point for each financial year, under a methodology it determines, publishes and maintains, and applies it in settling energy at that point.
Note: The National Electricity Rules call these intra-regional loss factors. "Marginal loss factor" is the operational and market name, and AEMO uses it in its own loss factor publications. The Rules require AEMO to calculate intra-regional loss factors and inter-regional loss factor equations annually and publish the results by 1 April, before the financial year they apply to, with quarterly updates during the year to pick up new and revised connection points.
Why it matters
The factor is marginal rather than average, so a connection point's figure can move between years as generation and demand around it change. Where a contract settles on a loss-adjusted volume, that movement reaches the invoice without any change to the contract or to consumption.
Source: National Electricity Rules, clauses 3.6.1 and 3.6.2, current rules; AEMO, loss factors and regional boundaries
A customer registered with AEMO under clause 2.3.4 of the National Electricity Rules, whose activities relate to a market load and which purchases all its electricity from the spot market. A Market Customer pays AEMO for electricity supplied at each connection point for each trading interval. First-tier and second-tier Customers must not participate in the spot market for their first-tier or second-tier loads.
Note: The same words carry different meanings elsewhere. Victoria's wholesale gas market uses registrable capacities named Market Participant - Transmission Customer and Market Participant - Distribution Customer, each being an end user that buys natural gas in the declared wholesale gas market and withdraws it from the declared transmission system or a declared distribution system. Western Australia's rules formerly had a Market Customer class, which is deemed registered in the single Market Participant class from the New WEM Commencement Day.
Why it matters
Registration puts settlement, prudential and reporting obligations on the business rather than on a retailer, and the Retailer Reliability Obligation's liable entity test is framed around Market Customers and Integrated Resource Providers, so the status also governs who carries that obligation.
See also
Source: AEMO, application guide, registering as a Customer in the NEM; National Gas Rules, rule 135A, current rules
Fees AEMO charges Registered Participants to recover the costs of operating and administering the markets it runs. The amounts are set each year through AEMO's budget and fees process, and the structure under which they are levied is determined by AEMO after consultation under the Rules. Where a retailer passes them on, they appear on an invoice as a separate market charge, often split between market operation and ancillary services.
Note: The National Electricity Rules use the term participant fees. "Market fees" is the name that appears on invoices and in AEMO's own fees publications, and the two refer to the same charges.
Why it matters
The amounts are set annually by AEMO rather than by the retailer, so under a pass-through arrangement they change during a contract term independently of the agreed energy rate.
Source: National Electricity Rules, clause 2.11, current rules; AEMO, energy market fees and charges
AEMO's formal message to market participants about an event affecting the market, issued through the Market Management System and updated in real time. Notices carry advance notice of low reserve conditions, the status of market systems, over-constrained dispatch, price adjustments, constraints, directions, interventions and market suspensions.
Why it matters
It is the public record of what AEMO declared and when it started and ended, so a retailer's account of a price move or a supply warning can be checked against it without relying on the retailer's own reporting.
Source: AEMO, NEM events and reports
The highest price the spot market can reach in a trading interval in the National Electricity Market. The AEMC sets it in the National Electricity Rules, and it is adjusted for the consumer price index each year by 28 February. It is $23,200 a megawatt hour for the year from 1 July 2026, up from $20,300 a megawatt hour in 2025-26, following a staged increase to the base rate made by rule in December 2023.
Why it matters
It is the ceiling on a buyer's per-interval spot exposure, and it rises every year.
Source: AEMC, AEMC updates market price cap for 2026-27
The lowest price the spot market can reach in a trading interval in the National Electricity Market, set at negative $1,000 a megawatt hour. Unlike the cap, it is not indexed to the consumer price index and has not changed.
Note: The National Electricity Rules call it the market floor price. Both names are in use.
Why it matters
Spot prices can go below zero, so a site with spot exposure can be paid for the energy it consumes in some intervals, while a site exporting at the spot price receives a negative price in those same intervals.
Source: AER, State of the energy market 2025, chapter 2
A retail contract negotiated between a retailer and a customer on terms other than the standard retail contract. Under the Retail Law these are small customer contracts; large customer agreements sit outside that framework entirely.
Why it matters
Because the terms are negotiated rather than set by the Rules, two businesses supplied by the same retailer can hold materially different terms, and the signed contract is the only record of which ones apply.
Source: National Energy Retail Law, current Act
AEMO's suspension of the spot market in a region. It is available where that region's power system has collapsed to a black system, where a participating jurisdiction has directed suspension after formally declaring a state of emergency, or where AEMO determines it has become impossible to operate the spot market in accordance with the Rules. AEMO may not suspend solely because prices have reached the market price cap or floor, or because it has issued a direction or otherwise intervened. Bidding and dispatch continue under rule 3.8 of the Rules where AEMO considers that practical, and the market resumes once none of the three conditions applies and AEMO is satisfied there is minimal possibility of suspending again within 24 hours for the same cause.
Why it matters
The most recent instance covered every National Electricity Market region, declared on 15 June 2022 and lifted on 24 June 2022, and across most of it spot prices came from the market suspension pricing schedule rather than from dispatch. Pass-through contracts settled against those scheduled prices, and the compensation paid over the same period was recovered from market customers afterwards.
See also
Source: AEMO, Guide to Market Suspension in the NEM
The set of pre-published prices AEMO applies in a suspended region where it is not practical to keep determining prices through dispatch. Each schedule holds two sets of half-hourly prices for every region and market, one for weekdays and one for weekends and public holidays, each price being the historical average for that region, market, day type and half hour across the 28 days to the end of the preceding billing week. AEMO publishes a new schedule weekly and at least 14 days before the first day it relates to.
Why it matters
Because the prices are averages of the four weeks before publication, they can sit well below the conditions that caused the suspension. Generators are separately compensated for that gap, and market customers in the affected regions fund the compensation, so a buyer can pay a low scheduled price during the event and a recovery amount after it.
Source: AEMO, Guide to the Market Suspension Pricing Schedule
The scope 2 accounting method that reflects emissions from the electricity a company has purposefully chosen, or its lack of choice. It derives emission factors from contractual instruments, which include energy attribute certificates, direct contracts for generation, supplier-specific emission rates, and residual mix factors where no qualifying contractual information applies.
Note: The Greenhouse Gas Protocol sets quality criteria that a contractual instrument must meet to be used as a data source under this method.
Why it matters
Only a contractual instrument meeting the criteria can move the figure, so electricity bought as renewable without a qualifying instrument behind it is still reported at the residual mix factor.
See also
Source: Greenhouse Gas Protocol, Scope 2 Guidance
Industry usage
A clause allowing a party to reopen, suspend or exit where defined circumstances worsen significantly. No Australian statute defines it, and what counts as material is whatever the clause states.
Note: The phrase carries no settled content. Two agreements using it can allocate very different rights, because the test is built entirely from the clause's own wording on what must change, by how much, and whose assessment decides.
Why it matters
Where the clause leaves the assessment to one party's opinion, the other party's exposure turns on that opinion rather than on an event both parties can observe.
Industry usage
The largest volume of gas a buyer may take in a day under a supply or transportation agreement.
Why it matters
It is a daily ceiling rather than an annual one, so a single high-demand day can exceed it while the year's total volume stays within the contracted quantity.
The highest amount of electrical power delivered, or forecast to be delivered, over a defined period such as a day, week, month, season or year, either at a connection point or simultaneously across a defined set of connection points.
Note: What counts for billing is narrower than the defined term. Networks differ on the measurement interval, on whether demand is measured in kW or kVA, and on the hours, days and months in which a recorded peak counts. The CitiPower and Powercor large business tariffs, for example, use the maximum 15-minute kVA demand measured between 7am and 7pm on workdays.
Why it matters
Demand measures the rate at which power is drawn rather than the amount used, so the same annual consumption packed into shorter periods produces a higher demand figure and a higher demand charge.
Source: National Electricity Rules, chapter 10 (glossary), current rules
The highest quantity of gas, in gigajoules per hour, withdrawn at a delivery point. Gas distribution demand tariffs for larger sites are charged per unit of maximum hourly quantity, and a gas transportation agreement states an agreed maximum hourly quantity for each delivery point.
Note: Maximum hourly quantity and maximum daily quantity measure different things. The hourly figure governs the rate of flow at a point within the gas day; the daily figure governs the total for the whole gas day.
Why it matters
The measure is a peak rather than a total, so one hour of high flow can set the demand charge for a billing year while total consumption is unchanged. It also decides which gas network tariff a site sits on, alongside annual consumption.
Source: AER, Multinet annual tariff report (Tariff D maximum hourly quantity, measured in GJ per hour); AER, Multinet tariff schedule 2026-27
MDQThe common abbreviation for maximum daily quantity. See Maximum daily quantity →
A unit of energy equal to 1,000,000 joules. It is the unit in which gas consumption is metered and billed on most Australian retail and small business invoices, while wholesale and large customer gas contracts are written in gigajoules and terajoules.
Conversions: 1 MJ = 0.2777778 kWh. 1 kWh = 3.6 MJ. 1,000 MJ = 1 GJ. 1,000,000 MJ = 1 TJ.
Why it matters
Gas volumes in megajoules and electricity volumes in kilowatt hours are not directly comparable, because one kilowatt hour is 3.6 megajoules, so a site's total energy use across both fuels only adds up once both are in the same unit.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement), current regulations
One thousand kilowatt hours. It is the unit in which wholesale electricity volumes are settled and in which wholesale and contract prices are quoted, as dollars per megawatt hour.
Conversions: 1 MWh = 1,000 kWh = 3,600 MJ = 3.6 GJ = 3,600,000,000 joules. 1 TJ = 277.7778 MWh.
Why it matters
The annual thresholds that separate small from large electricity customers are expressed in megawatt hours, so the unit a site's volume is settled in is also the unit that decides which retail framework applies to it.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement), current regulations
Industry usage
The order in which offered generation is dispatched, cheapest first. In the National Electricity Market, AEMO selects the lowest priced offers and then progressively more expensive ones until enough has been dispatched to meet demand, and the last generator needed sets the spot price for that dispatch interval.
Why it matters
The price follows the most expensive generation needed rather than the average of what ran, and every dispatched generator is paid that price regardless of what it offered.
Source: AER, Wholesale electricity market performance report 2026
Any alteration or replacement of a metering installation. The Rules require it to be managed under the meter churn procedures AEMO publishes for the metering coordinator, metering provider, metering data provider and financially responsible Market Participant, and those procedures must allow a new or replacement installation to be fitted as soon as practicable after AEMO has effected the transfer of the market load at the connection point.
Note: In market usage the term is often narrowed to the meter replacement that follows a change of retailer or metering coordinator. The defined meaning is wider and covers any alteration or replacement, however it arises.
Why it matters
Because the defined meaning covers any alteration or replacement, the churn procedures apply to work arising from an upgrade or a failed meter and not only to a replacement that follows a change of retailer.
Source: National Electricity Rules, clauses 7.8.9(a) and 7.8.9(f); AEMO, Retail Electricity Market Procedures - Glossary and Framework
The factor applied to a meter register reading to turn it into a quantity of billable energy. It is held in MSATS as a mandatory item of register-level standing data, supplied by the metering provider. Where the meter measures a scaled-down current through instrument transformers, the multiplier restores the reading to the quantity the site drew. Where the whole of the load current passes through the meter it is ordinarily one.
Why it matters
A wrong multiplier scales the account by the ratio between the two values, so the result is a clean factor rather than a small discrepancy, and every period billed from that register is affected until the standing data is corrected and the invoices reissued.
See also
Source: AEMO, Standing Data for MSATS, register-level standing data
Industry usage
A charge for the provision, installation, maintenance and reading of a metering installation at a connection point. On a large customer invoice it is commonly a separate line; on a small customer invoice it may sit inside network or retail charges rather than being shown on its own.
Note: Under the Rules a metering coordinator is responsible for the metering installation at a connection point, including its provision, installation and maintenance and the collection and delivery of metering data. Who holds that role determines whose charge it is. Where the meter is a regulated distributor asset the charge forms part of regulated network charges and the AER approves the price; where metering is contestable the charge is commercial and is not subject to AER price approval.
Why it matters
Whether the amount is an AER-approved price or a commercially set one follows from who holds the metering coordinator role, so the same line can be a regulated charge at one site and a negotiated one at another.
Source: National Electricity Rules, clause 7.3.1, current rules
The registered participant responsible, for the term of its appointment at a connection point, for the provision, installation and maintenance of the metering installation. It appoints the metering provider and the metering data provider, and tells the financially responsible Market Participant who they are.
Why it matters
The metering provider and the metering data provider are the coordinator's appointees, so changing the coordinator changes who installs the meter and who supplies the data at that connection point.
See also
Source: National Electricity Rules, clauses 7.3.1 and 7.3.2
Industry usage
A party that collects, processes and delivers metering data. The Rules give this function to the metering data provider, and the two names are used in the market for the same role.
Why it matters
No separate appointment sits behind the phrase, so a document using it is describing the metering data provider the metering coordinator has already appointed.
A party accredited by AEMO to collect, process and deliver metering data for a connection point. The metering coordinator appoints the metering data provider.
Why it matters
Collection and processing sit with the same party, so validation and any substitution of missing data happen here before the data reaches the retailer or the customer.
Source: National Electricity Rules, chapter 7, current rules
The AEMO procedures setting the minimum requirements for the manner and form in which a retail customer's metering data is provided when the customer, or its authorised representative, requests it from the retailer or the distributor. They specify both a detailed and a summary data format, and a response timeframe of no more than 10 business days, with a longer allowance where one representative requests data for several customers of the same party.
Why it matters
The obligation and the response timeframe fall on the retailer or distributor holding the data, and they run from a request by the customer or an authorised representative rather than arising on their own.
Source: National Electricity Rules, rule 7.14, current rules
The classification that fixes a metering installation's accuracy requirements and determines how its data is obtained. Types 1, 2 and 3 cover connection points by annual energy throughput: above 1,000 GWh, between 100 and 1,000 GWh, and from 0.75 GWh to under 100 GWh. Type 4 is the smart metering installation that meets the minimum services specification, and is required for any new or replacement installation at a small customer's connection point. Type 4A is a manually read interval installation permitted where AEMO has exempted the metering coordinator because no telecommunications network enables remote access. Type 5 is a manually read interval installation, type 6 an accumulation installation, and type 7 an unmetered connection point where the load is small and predictable enough for AEMO to allow it to be calculated rather than measured.
Note: Each jurisdiction sets its own annual consumption ceiling for types 4A, 5 and 6, recorded in AEMO's metrology procedure, and 750 MWh a year is the maximum the Rules permit for any of them.
Why it matters
The type decides whether interval data exists for the site at all, and whether it can be collected remotely or only by a site visit.
Source: National Electricity Rules, clauses 7.8.3, 7.8.4 and 7.8.8 and Schedule 7.4; AEMO, Metrology Procedure Part A
A party accredited by AEMO to provide, install and maintain metering installations. The metering coordinator appoints the metering provider for a connection point.
Why it matters
The provider is the metering coordinator's appointee and must hold AEMO accreditation, so changing who installs and maintains a meter at a connection point runs through the coordinator.
Source: National Electricity Rules, chapter 7, current rules
A two-character numeric flag on a reading in a metering data file naming which substitution or estimation method produced it. It occupies the second and third characters of the data quality field, behind the quality flag, and is mandatory where the quality flag records estimated or substituted data. Its permitted values correspond to the substitution and estimation types in AEMO's metrology procedure and are listed in an appendix to the Meter Data File Format Specification.
Why it matters
It states how a figure that did not come from the meter was derived, which is the only thing in the file separating a value interpolated between two actual reads from one taken off a comparable day.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, method flags appendix
MHQThe common abbreviation for maximum hourly quantity. See Maximum hourly quantity →
The floor a network applies to chargeable demand, so a site is billed on at least that level of demand whether or not its recorded demand reaches it.
Note: The figure belongs to the tariff, not to the market. On the CitiPower and Powercor networks the rolling demand charge carries a minimum chargeable demand of 120 kVA for large low voltage, 500 kVA for high voltage and 5 MVA for sub-transmission. The applicable figure is the one in the relevant network's tariff schedule or pricing proposal.
Why it matters
Below the floor, cutting demand further does not cut the demand charge, so the floor marks the point at which demand reduction stops paying on that component of the bill.
Source: CitiPower and Powercor, large business tariffs fact sheet
The lowest level of demand on a network or in a region over a period. At system level AEMO measures minimum operational demand, being the lowest demand that has to be met by grid-scale generation, which excludes what is supplied by rooftop solar and other generation behind the meter.
Note: This is the system-level sense and is distinct from minimum chargeable demand, which is a billing floor applied to one site. Growth in rooftop solar has lowered minimum operational demand and moved the daily minimum from overnight to the middle of the day.
Why it matters
The system minimum now falls in the middle of the day, which is the same window in which a site's solar is exporting most, so the hours of greatest export are the hours in which the network has least room to accept it.
See also
Source: AEMO, minimum operational demand fact sheet
Periods when large volumes of rooftop solar reduce the demand met from grid-scale generation far enough to limit access to essential system services and create a power system security risk. They occur on mild, sunny days, typically in autumn and spring. AEMO signals them through three tiers of market notice: MSL1 is advance notice of a possible event, MSL2 states that grid-scale actions are being taken, and MSL3 is the activation of solar management programmes run by state governments and distribution networks.
Current status: Two rule change requests on the minimum system load framework, one of them from the AEMC's Reliability Panel, are before the AEMC. It published a consultation paper on 9 July 2026 and a draft determination is due by 3 December 2026.
Why it matters
The grid-scale actions available at MSL2 include increasing demand from large users, so a site with flexible load can be asked to consume more at the time of day when spot prices are most often negative. Tariff arrangements and demand response written only around peak events do not reach it.
See also
Source: AEMO, Minimum system load fact sheet
A ten-character identifier for a gas supply point. It is not a separate scheme from the electricity identifier: AEMO describes a MIRN as a sub-class of National Metering Identifier, using the block of identifiers beginning with 5 that was set aside for the gas industry. The characters encode the market, the state and the distributor.
The acronym is expanded three different ways within AEMO's own procedure, as Meter Installation Registration Number, Metering Installation Registration Number and Metering Identification Registration Number.
Why it matters
A gas tender runs on MIRNs the way an electricity tender runs on NMIs. Western Australia sits outside this structure and uses a different identifier.
See also
Source: AEMO, MIRN Structure, version 2.0
MJThe common abbreviation for megajoule. See Megajoule →
MLFThe common abbreviation for marginal loss factor. See Marginal loss factor →
A customer who begins taking supply at premises without first entering a contract.
Why it matters
Energy taken from the day of occupation is billable even though no rate has been agreed, so a first invoice at new premises can cover a period for which the business negotiated nothing.
Source: National Energy Retail Law, section 2
The Market Settlements and Transfer Solution, the AEMO system that registers metering installations, holds standing data against each National Metering Identifier, transfers end users between retailers, and supports settlement and the administration of NMIs. The MSATS Procedures are made under clause 7.16.2 of the Rules and published as separate documents along functional lines.
Why it matters
Settlement is calculated from what MSATS records, so the participants and data streams registered there, rather than the parties' own records, determine who is billed for the load at a connection point.
Source: AEMO, Retail Electricity Market Procedures - Glossary and Framework
MWhThe common abbreviation for megawatt hour. See Megawatt hour →
N
The National Australian Built Environment Rating System, which rates the measured operational performance of buildings and tenancies from one to six stars across energy, water, waste and the indoor environment. Ratings are valid for twelve months and are managed by the NSW Government on behalf of the federal, state and territory governments.
Note: Ratings measure actual metered performance over a period, not design intent, which is why bills and metering data are the inputs to an assessment.
Why it matters
A rating describes how a building actually ran over the rated period, so a change in occupancy, hours or equipment shows up in the next rating rather than the current one, and the rating lapses after twelve months whether or not anything has changed.
Source: NABERS, what is NABERS
The wholesale electricity market covering Queensland, New South Wales including the Australian Capital Territory, Victoria, South Australia and Tasmania. Western Australia and the Northern Territory are not part of it.
Why it matters
A business with sites in Western Australia or the Northern Territory holds part of its portfolio outside this market, so spot prices and NEM-referenced contract structures do not describe those sites. Inside the market, prices are set by region, so sites in different states carry different wholesale exposure under one contract.
Source: AER, State of the energy market 2025, chapter 2
The rules governing the National Electricity Market, made and amended by the AEMC under the National Electricity Law. They cover registration of participants, central dispatch and spot pricing, settlement, network connection and access, the economic regulation of transmission and distribution networks, metering, and the reliability standard and market price settings.
Note: They apply in the National Electricity Market jurisdictions. Western Australia runs its own Wholesale Electricity Market rules, and the Northern Territory has adopted a modified form of chapter 5A only, from 1 July 2019.
Why it matters
Network charges and metering obligations at a site come from the same instrument as wholesale dispatch and spot pricing, so a rule change made for market reasons can land on a site that never trades in the market.
See also
Source: National Electricity Rules, current rules
The package of retail energy regulation made up of the National Energy Retail Law, the National Energy Retail Rules and the National Energy Retail Regulations, administered and enforced by the AER. It commenced in the Australian Capital Territory and Tasmania on 1 July 2012, South Australia on 1 February 2013, New South Wales on 1 July 2013 and Queensland on 1 July 2015.
Note: It does not apply in Western Australia or the Northern Territory. Victoria applies only chapter 5A of the National Electricity Rules, from 1 July 2016, and keeps its own retail framework under the Essential Services Commission.
Why it matters
Which retail protections attach to a site depends on the jurisdiction it sits in as well as the customer's size, so a multi-state portfolio is governed by more than one framework.
See also
Source: AEMC, National Energy Customer Framework
The head statute of the National Energy Customer Framework, enacted in South Australia and applied as a law of each participating jurisdiction. It sets retailer authorisation and exemption, the customer retail contract regime and standard retail contracts, small customer protections, the retailer of last resort scheme, and the AER's retail functions.
Why it matters
The line between small and large customers that decides which protections attach to a site is drawn in this statute, as is the retailer of last resort scheme that governs what happens to supply if a site's retailer fails.
See also
Source: National Energy Retail Law, current Act
The rules made by the AEMC under the National Energy Retail Law. They cover billing, marketing conduct, connection, disconnection and reconnection, payment difficulty and hardship, life support arrangements, and the required terms of market retail contracts.
Why it matters
Some of what a market retail contract contains is required by these rules rather than offered by the retailer, so those terms read the same in every offer a site in a national framework jurisdiction receives.
See also
Source: National Energy Retail Rules, current rules
A DCCEEW publication providing default emission factors and methods for estimating greenhouse gas emissions, revised and republished each year. Each issue supersedes the previous one, and the electricity scope 2 and scope 3 factors are updated annually.
Note: DCCEEW states the factors should not be used to meet reporting requirements under the National Greenhouse and Energy Reporting Act 2007, although the methods draw on the National Greenhouse and Energy Reporting (Measurement) Determination 2008.
Why it matters
This is the publication that converts a site's kilowatt hours into tonnes. Because the factors change each year, a year-on-year emissions comparison needs the factor vintage stated or the change in the factor is read as a change in performance.
See also
Source: DCCEEW, National Greenhouse Accounts Factors: 2025
The Commonwealth scheme requiring corporations above defined thresholds to report greenhouse gas emissions and energy production and consumption. Facility thresholds are 25,000 tonnes of carbon dioxide equivalent, or 100 TJ of energy produced or consumed. Corporate group thresholds are 50,000 tonnes or 200 TJ.
Why it matters
The thresholds are measured in emissions and energy rather than revenue or headcount, so an energy-intensive business can fall into the scheme at a modest size. The corporate group thresholds aggregate across the group, so a corporation can be caught by the sum of facilities that each sit under the facility threshold.
Source: Clean Energy Regulator, assess your obligations
National Metering IdentifierThe full name for a NMI. See NMI →
NECFThe common abbreviation for the National Energy Customer Framework. See National Energy Customer Framework →
The planning step that establishes what is being bought and why, before the market is approached. Victorian government procurement guidance says a needs analysis should set out who the buyer is buying for and who needs the goods, works or services, how those benefit them now and in future, when they are needed, the geographical areas that need them, and the expected outcomes of the procurement.
Why it matters
It fixes the requirement before any offer exists, so the evaluation that follows can only test offers against what the assessment recorded.
Source: Victorian Government, identify needs
Industry usage
A spot price below zero, at which generators pay to keep producing rather than being paid for output. National Electricity Market spot prices can fall to the market price floor of minus $1,000 per megawatt hour, and the AER counts the number of negative-priced 30-minute periods in each quarter.
Why it matters
Exposure runs in both directions, so consumption in those intervals attracts a credit under a spot-linked or pass-through arrangement and does not under a fixed price for the same period.
Source: AER, Wholesale electricity market performance report 2026; AER, industry charts
Industry usage
A connection scoped and priced through negotiation rather than taken from an approved model standing offer. Under the Rules a connection applicant and a distribution network service provider may negotiate where the connection service sought is neither a basic connection service nor a standard connection service, or where it is one of those but the applicant elects to negotiate the terms on which it is provided.
Note: The defined terms in the Rules are the negotiated connection contract and the negotiation framework, and chapter 6 uses "negotiated distribution service" for a separate service classification. Under the framework both parties must negotiate in good faith, the applicant must give the network the information it reasonably requires, and the network must give an estimate of its charge for assessing the application and making the offer, an estimate of the connection charges, a statement of the basis on which they are calculated, and must comply with its connection policy.
Why it matters
The route decides what a site can put to the network. Negotiating allows a customer to raise reasonable requirements such as the location of the connection point, and it also allows the network to seek a contribution towards augmentation for forecast load growth beyond what the connection itself requires.
Source: National Electricity Rules, clauses 5A.C.1, 5A.C.3 and 5A.E.1, current rules
NEMThe common abbreviation for the National Electricity Market. See National Electricity Market →
The interval metering data file format in AEMO's Meter Data File Format Specification, used by metering data providers to deliver metering data to other participants, to embedded network managers and to AEMO. A NEM12 file is assembled from numbered records: a header (100), NMI data details (200), the interval data itself (300), interval events (400), business-to-business details (500) and an end of data record (900). Accumulated metering data uses the companion NEM13 format, and a single file carries one format or the other, never both.
Why it matters
A site whose meter records only totals produces the NEM13 format instead, so a portfolio of mixed metering types returns more than one file format and no single NEM12 file covers all of it.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, published with the metering procedures
The accumulated metering data file format in AEMO's Meter Data File Format Specification, the counterpart to NEM12. A file is assembled from a header record, basic meter data records each carrying a previous and a current register read with the quantity between them, business-to-business details and an end of data record. A single file carries one format or the other, never both.
Note: The null quality flag is not permitted in a NEM13 file.
Why it matters
The format carries two register reads and the quantity between them rather than a series of values, so the only consumption figure it yields for a site is the total across the period those reads bound.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, basic meter data file specification
NERThe common abbreviation for the National Electricity Rules. See National Electricity Rules →
NERLThe common abbreviation for the National Energy Retail Law. See National Energy Retail Law →
NERRThe common abbreviation for the National Energy Retail Rules. See National Energy Retail Rules →
A state in which the greenhouse gas emissions released over a stated period are balanced by an equivalent quantity removed from the atmosphere. Australia's target of net zero by 2050, alongside a 43 per cent reduction on 2005 levels by 2030, is set in the Climate Change Act 2022.
Why it matters
The target in the Act applies to Australia's emissions as a whole and does not by itself oblige any individual business to reduce or offset anything; obligations on particular facilities come through separate schemes.
Source: Climate Change Act 2022
The component of an energy bill that pays for transporting electricity through the transmission and distribution networks. The charges are set by each distributor through a tariff structure statement approved by the Australian Energy Regulator, and prices are updated annually on 1 July.
Why it matters
Network charges are one of the largest components of a commercial bill, they differ by distributor, and they change on a date that has nothing to do with when a retail contract starts or ends.
Source: National Electricity Rules, clause 6.18.1A, current rules
The component of an energy price covering transport of energy through the transmission and distribution networks. With wholesale costs it is one of the two largest components, and which of the two leads varies by distribution network.
Why it matters
It is determined for the network a site sits in rather than by the retailer, so two otherwise identical sites in different distribution areas carry different network costs whoever supplies them.
See also
Source: AER, annual retail markets report 2024-25
Permission to own or operate a distribution network without registering as a network service provider. An embedded network usually needs both a network exemption and a retail exemption, because the operator both runs the wires and sells the energy.
Why it matters
The two permissions are separate and carry separate conditions, so an operator can hold one without the other, and the wires side of an arrangement is exempted on different terms from the selling side.
See also
Source: AER, network exemptions guideline
The schedule of charges a distributor applies to a connection point, determined by the customer's consumption, demand and connection characteristics. Customers are assigned to a tariff class under policies published in the distributor's tariff structure statement, and reassignment is the distributor's decision against those published criteria.
Why it matters
The tariff is assigned by the distributor against its own published criteria, so it is not a term a retailer can negotiate and changing retailer does not change it. Charges under it can move while the retail contract sitting on top stays as it is.
Source: National Electricity Rules clauses 6.18.1A and 6.18.4, as quoted in distributor tariff structure statements approved by the AER
NGERThe common abbreviation for National Greenhouse and Energy Reporting. See National Greenhouse and Energy Reporting →
A National Metering Identifier is the unique identifier for an electricity connection point. Standing data about the connection point, including its address and metering arrangements, is recorded against it. One premises can hold more than one NMI, because the identifier attaches to the connection point rather than the building.
Why it matters
A tender, a contract and a bill all run on the NMI, not the address. A business with ten sites may hold more than ten NMIs, so a site count and a NMI count are different numbers, and a portfolio can only be priced accurately once every NMI is known.
Source: AEMO, MSATS technical guide and NMI procedure
The field in a metering data file giving the string of every datastream suffix applicable to a National Metering Identifier. It must represent the actual configuration of the site, and where the configuration changes during a day, every channel active for any part of that day must be provided.
Why it matters
It is the list of channels that exist at the site, so a quantity absent from it is one the metering does not record, and a difference between two files for the same NMI is often a configuration change rather than missing data.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, NMI data details and basic meter data records
The data items AEMO holds in MSATS against a National Metering Identifier, covering the participants in each role at the connection point, the metering installation and its registers, and the data streams used for settlement. The items are listed in AEMO's NMI Standing Data Schedule, published under clauses 3.13.12 and 3.13.12A of the Rules. NMI standing data is a subset of the wider CATS standing data held in MSATS.
Note: Access is restricted rather than open. Discovery of standing data is governed by the access rules in AEMO's CATS procedures, and the searches that return it are limited to defined purposes.
Why it matters
The data is held against the connection point rather than against the customer, so it persists when the occupier or the retailer changes and describes the site rather than the account.
Source: AEMO, Retail Electricity Market Procedures - Glossary and Framework, section 2.4.4; AEMO, NMI Standing Data Schedule
Telling the pipeline operator how much gas will be moved on a given gas day. The Rules define a nomination as a nomination for use of a transportation service, which may include the quantity of gas and the service points, and a day-ahead nomination as one given on a gas day about the following gas day. The nomination cut-off time is the time by which a day-ahead nomination must be made to be scheduled for that day.
Why it matters
Holding capacity and using it are separate steps, because a firm service is scheduled only to the extent it is nominated before the cut-off time. On a facility in the capacity auction, a nomination carries a standing obligation not to be false or misleading, which includes having a genuine intention to use the quantity nominated.
Source: National Gas Rules, Part 24, rule 593, and Part 25, rule 663, current rules
Industry usage
Replacing a party to a contract with a new one, so the incoming party takes on the obligations and the original party is released. It needs the agreement of all parties, which separates it from assignment, where rights move across and the original party stays liable for the obligations.
Note: Novation has a settled meaning at general law rather than a statutory one. Supply agreements usually cover the same ground through a transfer clause requiring the supplier's prior written consent to a transfer by the buyer, while recording the buyer's advance consent to transfers by the supplier.
Why it matters
A restructure that moves sites into a different entity needs the supplier's agreement to carry the contract across, and without it the original entity stays on the obligations and on any security it provided.
O
OCMThe common abbreviation for owners corporation manager. See Owners corporation manager →
Industry usage
An arrangement in which a connection point inside an embedded network is not registered in the market, so the occupant buys from the exempt seller.
Why it matters
This is where a child connection point sits until something is done to register it, and while it stays there the exempt seller's price cap is the only comparison available for that lot.
See also
The times at which a network tariff applies its lowest rate, usually overnight. Some networks now publish a separate daytime band priced lower again, reflecting high solar output in the middle of the day.
Why it matters
Where a network publishes a separate daytime band, the lowest rate at that site falls in the middle of the day rather than overnight, so the cheapest hours are not in the same place in every network. Moving load into the lowest band lowers the energy component, while any demand charge is still set by the site's peak whenever it occurs.
See also
Source: SA Power Networks tariffs
Industry usage
A contract under which a buyer commits to take, or to pay for, the output of a generation or storage project across a defined term. In electricity it is normally a power purchase agreement, settled physically or financially, and it is the instrument that converts a project's output into the contracted revenue lenders assess.
Why it matters
The commitment is to the project's output rather than to the buyer's own consumption, so the two will not match period by period and the difference has to be settled elsewhere.
Industry usage
An arrangement in which a connection point inside an embedded network is registered in the wholesale market, so the occupant can choose their own retailer.
Why it matters
Once a point is on-market, the occupant's price and contract come from the retailer they chose, so the exempt seller's price cap stops being the relevant comparison for that lot.
The National Greenhouse and Energy Reporting test deciding which entity reports a facility. A person has it where they have the authority to introduce and implement operating policies, health and safety policies or environmental policies for the facility and meet the requirements of the regulations, or where the Clean Energy Regulator declares them to have it.
Note: Only one person can hold operational control over a facility at any one time. Where two or more could qualify, the Act gives it to the one with the greatest authority to introduce and implement operating and environmental policies, and where no one holds the greatest authority a joint nomination may be made.
Why it matters
The test turns on authority over policies rather than on ownership of the asset or of the energy account, so a landlord and a tenant at the same premises can reach different answers about which of them reports the site.
Source: National Greenhouse and Energy Reporting Act 2007, sections 11, 11A and 11B, current Act
Demand in a NEM region met by local scheduled generating units, semi-scheduled generating units and non-scheduled intermittent generating units of aggregate capacity of 30 MW or more, by generation imported into the region, and by wholesale demand response. It excludes demand met by non-scheduled non-intermittent generating units, by non-scheduled intermittent generating units below 30 MW in aggregate, and by exempt generation such as rooftop solar, and it excludes the demand of local scheduled loads.
Note: AEMO also publishes underlying demand, being operational demand plus rooftop PV generation, and operational demand less significant non-scheduled generation, which matches the demand forecast in pre-dispatch and short term PASA.
Why it matters
This is the demand figure quoted in market commentary and forecasts, and because rooftop solar is netted off it, the published figure moves when behind the meter generation changes even where consumption at sites has not.
Source: AEMO, operational demand data
Industry usage
The rate a retailer applies when a customer continues taking supply after a contract has ended without a new agreement in place.
The phrase is industry usage. It appears in none of the National Energy Retail Law, the National Energy Retail Rules or Victoria's Energy Retail Code of Practice. What applies after expiry is set by the expired contract's own terms or by the retailer, and for small customers by the deemed arrangement provisions in the Retail Law.
Why it matters
Because the term is not regulated, there is no standard rate behind it and no published benchmark to compare against. Two businesses described as being on out-of-contract rates may be paying very different amounts.
Source: Absence confirmed against the National Energy Retail Law, current Act, and the National Energy Retail Rules
A hedge contract negotiated directly between two parties rather than traded on an exchange, often arranged through a broker. The AER describes swaps, caps and other customised hedge contracts as the common over-the-counter products, with their terms set out in standardised industry master agreements.
Why it matters
Volume, period and shape are negotiated rather than standardised, so a contract can be matched to a particular load, and the counterparty's credit is carried by the two parties instead of by a clearing house.
Source: AER, Wholesale electricity market performance report 2026
Gas taken or delivered above the quantity scheduled, or above a contracted maximum daily or hourly quantity. Where the service provider approves it in advance it is an authorised overrun service, charged at the authorised overrun rate stated in the access arrangement or the agreement. Where it is not approved in advance it is an unauthorised overrun.
Why it matters
The gas above the contracted quantity carries its own rate rather than the rate paid for the quantity inside the agreement, so the marginal cost of the last gigajoule differs from the average. Authorised overrun ranks below firm services for scheduling, which the Rules record by naming it as an example of a lower tier service.
Source: AER, access arrangement access principles (authorised and unauthorised overrun service, and paragraph 6 on overrun charges); National Gas Rules, Part 25, rule 647 (lower tier service)
Industry usage
A credit applied to an owners corporation's account under an embedded network arrangement, serving the same commercial purpose as an annuity.
Why it matters
It reaches the owners corporation as a reduced account balance rather than as money received, so in the owners corporation's accounts it is not the same thing as an annuity of equal value.
See also
Industry usage
The professional engaged to administer an owners corporation's affairs, including service contracts.
Why it matters
At a strata site this is usually the party holding the service contracts, so the documents governing the site's energy arrangement sit with the manager rather than with individual lot owners.
See also
P
A procurement arrangement in which several suppliers are appointed for a set period on agreed terms, including agreed pricing, and individual purchases are then made from among them. Victorian guidance describes a panel as two or more suppliers able to deliver the goods or services under a contract arrangement, and notes that panels may be open or closed. Commonwealth guidance treats each purchase from a panel as a separate procurement for which value for money must still be established.
Why it matters
Appointment to a panel is not an award of work, and the terms agreed at appointment, pricing included, hold for the panel's period, so a purchase made near the end of that period runs on the terms set at the start.
Source: Victorian Government, glossary of goods and services procurement terms; Department of Finance, panel arrangements
Industry usage
An undertaking by a buyer's parent or another group company to meet the buying entity's obligations if the buying entity does not. It is offered in place of cash or a bank guarantee where the group's financial standing supports it.
Why it matters
It puts the security on an entity the buying company does not control, so a fall in the parent's financial position can trigger a demand for replacement security against the buying company's contract.
Industry usage
The meter at the site's connection to the distribution network, which records the total electricity entering the embedded network and, where applicable, exports.
Note: The rules define the parent connection point rather than the meter.
Why it matters
The site's bill from its retailer is calculated from this meter, while occupants are billed from the child meters, so the difference between the two is the site's unmetered use and internal losses. Where the site exports, that is measured here rather than at any occupant's meter.
Industry usage
A retail power purchase agreement under which a fixed price applies to some periods or some volume and a variable price applies to the rest.
Why it matters
The unfirmed portion settles on prices as they arise, so the amount payable moves between periods while the contract itself stays the same.
Source: Business Renewables Centre Australia, Renewable Energy Power Purchase Agreements in Queensland
Participant feesThe term the National Electricity Rules use for market fees. See Market fees →
The projected assessment of system adequacy process, AEMO's programme of collecting, analysing and publishing information on supply and demand prospects so participants can make decisions about supply, demand and transmission outages. The Rules provide for two horizons. Medium term PASA covers 24 months, or 36 months for specified inputs, at daily resolution and is reviewed and published weekly. Short term PASA covers at least the seven trading days from the day of publication in 30 minute periods and is published at least daily. AEMO also runs a PASA in the pre-dispatch timeframe.
Why it matters
Forecast lack of reserve declarations are made from short term PASA and pre-dispatch PASA results, so the published forecasts are where a tight week in a buyer's region appears before any warning arrives from a retailer.
See also
Source: National Electricity Rules, clause 3.7, current rules
Industry usage
A contract structure in which network charges, market fees and regulated costs are billed to the customer as they are incurred, separately from the energy rate.
There is no regulated definition. Distributors state that how these costs reach a customer's price is at the retailer's discretion.
Why it matters
Two offers cannot be compared on the energy rate alone unless both treat network costs the same way. The packaging is a retailer choice, not a standard format.
Source: SA Power Networks, Energex and Essential Energy pricing overviews published at aer.gov.au
Industry usage
A contract under which the quantity settled in each period is whatever the project generates in that period, so the volume rises and falls with output rather than following an agreed shape. Also described as run-of-plant.
Why it matters
The quantity follows the project rather than a figure the buyer has chosen, so what the contract covers in any period turns on conditions at the generator and not on what the site consumed.
A New South Wales scheme, part of the NSW Energy Security Safeguard, that creates a market for peak reduction certificates. Scheme participants must surrender certificates to meet a peak reduction target, and accredited certificate providers create them by carrying out eligible activities in homes and businesses. Certificates represent the capacity to reduce demand at peak times rather than energy saved.
Why it matters
Certificates are earned for capacity to reduce demand at peak times, so a project that shifts when a site draws power can create them even where annual consumption is unchanged, which is a different test from the energy saved measured under the Energy Savings Scheme.
Source: IPART, about the PDRS
The times of day and year during which a network tariff applies its highest rate. The windows are set in each distributor's tariff schedule, not nationally, and a retailer may apply different times again in its own contract.
For example Ausgrid's network peak runs 3pm to 9pm in June to August and November to March, with no peak period in April, May, September or October. SA Power Networks runs a different pattern again.
Why it matters
The same consumption pattern is priced differently in different networks, and the times in a retail contract are not necessarily the times in the network tariff underneath it.
Source: Ausgrid time of use pricing; SA Power Networks tariffs
A unit of energy equal to 1,000 terajoules, or 1,000,000,000,000,000 joules. It is the unit in which Australian gas production, reserves, annual contract volumes and market forecasts are expressed.
Conversions: 1 PJ = 1,000 TJ = 1,000,000 GJ = 1,000,000,000 MJ.
Why it matters
Supply agreements and market forecasts are written in petajoules while invoices are written in gigajoules or megajoules, so a contracted annual quantity has to be converted across a factor of a million or a billion before it can be compared with metered consumption.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement) and Schedule 3 (SI prefixes), current regulations
PJThe common abbreviation for petajoule. See Petajoule →
Industry usage
Buying energy for a group of sites as one exercise rather than site by site, so that terms, pricing structure and expiry dates are set across the portfolio.
Why it matters
Sites are priced as one load rather than individually, so a site whose profile or network area differs from the portfolio's average carries the portfolio's terms rather than the terms it would have been offered alone.
The ratio of real power to apparent power at a site, that is kW divided by kVA. A site whose power factor falls below the level its distribution code requires can attract an additional charge.
Why it matters
The level that triggers a charge is set by the distribution code applying to the site rather than nationally, so the same ratio can be acceptable in one network and chargeable in another. It is a property of the equipment drawing power, so consumption can fall while the ratio stays where it was.
Source: AER, tariff structure statement glossary; SA Power Networks publishes excess kVAr charges on that basis
Industry usage
Equipment installed at a site, typically capacitors, to raise its power factor towards one, reducing the apparent power drawn for the same real load and so reducing demand and excess charges billed on kVA.
No current distributor definition could be retrieved. The mechanism follows from the regulator's definitions of power factor and demand charges.
Why it matters
The saving appears only on charges measured in apparent power, so where a site's demand is billed in kW, or its tariff has no demand component, correction changes nothing on the bill. It does not reduce consumption, because the real power the site uses is unchanged.
See also
How closely the supply at a connection point holds to its nominal level and waveform. The Rules set system standards for frequency, power frequency voltage, voltage fluctuations, harmonic voltage distortion and voltage unbalance, and define basic power quality data as measurements of voltage in volts, current in amperes and phase angle, as measured by the meter.
Why it matters
The Rules state that a participant should not rely on the system standards being fully met at a connection point in all circumstances, and that, apart from frequency and system stability, it may negotiate connection terms to lift the standard of supply. Basic power quality data from a smart meter is a separate dataset from consumption data, under its own AEMO procedures.
Source: National Electricity Rules, Schedule 5.1a and Chapter 10 (glossary), definition of basic power quality data, current rules
A Western Australian term for a customer in the South West Interconnected System that consumes, or could reasonably be expected to consume, not more than 50 MWh of electricity a year at an exit point or bidirectional point. Prescribed customers are non-contestable, so they can be supplied only by the state-owned retailer. The class is defined by order made under section 54(4) of the Electricity Corporations Act 2005, currently the Electricity Corporations (South West Interconnected System Prescribed Customers) Order 2023.
Note: The term has no counterpart in the national framework jurisdictions, where every customer can choose a retailer. It is not the same kind of definition as the Retail Law's small and large customer: it determines access to retail choice rather than which consumer protections apply.
Why it matters
The test applies at each exit point rather than to the business as a whole, so a Western Australian operator with several small sites can be non-contestable at every one of them however large its combined consumption.
Source: Electricity Corporations (South West Interconnected System Prescribed Customers) Order 2023, as made, SL 2023/39
The factor applied to a measured gas volume to convert it to the volume the gas would occupy at the base pressure and temperature used for the heating value. AEMO publishes a table of factors, and changes the basis on which they are calculated only after consulting participants.
Note: The factors are acceptable for volume conversion only up to a metering pressure of 450 kPa gauge. Above that, the change in gas compressibility with pressure and temperature has to be accounted for by a flow corrector at the metering installation instead.
Why it matters
The factor is a published figure selected for the pressure at the meter rather than a measurement taken at the site, so the pressure recorded against a meter determines it, and a change in supply pressure changes the energy billed for an unchanged volume.
Source: AEMO, Wholesale Market Metering Procedures (Victoria), sections 3.3 and 3.5
Industry usage
A clause allowing a price to be reset during a contract term on defined triggers.
Why it matters
The triggers set out in the clause determine how long the price is actually fixed for, because the rate holds only until one of them occurs.
See also
Industry usage
A clause allowing a supplier to change prices during the term. Under the Australian Consumer Law, a price variation clause in a standard form contract that leaves the customer unable to exit if they disagree is the regulator's own example of a term that may be unfair.
Why it matters
The regulator's example turns on the absence of an exit right, so whether the customer can leave on a variation is what separates the two cases. A business outside the unfair contract terms thresholds is left with general contract law.
Source: ACCC, business contracts
Integrity and honesty in the conduct of a process. Commonwealth guidance defines it as the evidence of ethical behaviour, and as complete and confirmed integrity, uprightness and honesty in a particular process. Victorian guidance gives uprightness, honesty, proper and ethical conduct and propriety in dealings, and adds that in government the word is often used in a general sense to mean good process.
Note: The Commonwealth guidance states that probity measures should be proportionate to the procurement, and that probity should not be used to justify avoiding reasonable discussion with potential suppliers during a tender.
Why it matters
The standard applies to how a process was run rather than to which offer was chosen, so a selection can be right on its merits and still be open to challenge on process.
Source: Department of Finance, ethics and probity in procurement; Victorian Government, glossary of goods and services procurement terms
Industry usage
The state of having the information and authority needed to go to market before a contract expires: current interval data, a complete list of connection points, known contract end dates and a signed authority to act.
This is settled industry usage rather than a defined term.
Why it matters
A buyer who starts assembling this after an expiry notice arrives negotiates on the retailer's timetable rather than their own.
Q
A single character on a reading in a metering data file stating whether it is actual, forward estimated, substituted, finally substituted or null. It occupies the first character of the data quality field, ahead of the method flag. Its values are listed in an appendix to the Meter Data File Format Specification, and AEMO's metrology procedure sets which values may replace which.
Note: A further value records that the flags vary across a day. It is not a quality held against an individual reading, and where it appears on a day's interval record the flags are given interval by interval in the records that follow.
Why it matters
It is what separates a measured figure from a derived one, so a month of data looks uniform until it is read, whether or not any of the figures came from the meter.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, quality flags appendix; AEMO, Metrology Procedure Part B, section 2.4
R
Industry usage
The mechanism by which a recorded maximum demand keeps setting a site's chargeable demand for a defined period after the peak occurred. On a tariff that charges on a rolling maximum, each month's charge is based on the highest demand recorded in the look-back window, so the charge falls only when the peak drops out of that window or a demand reset is granted.
Note: Australian distribution networks generally call this a rolling demand charge rather than a ratchet, and the look-back period and the rule for leaving it vary by network and by tariff. The CitiPower and Powercor rolling demand charge uses the maximum 15-minute kVA demand over a 12-month period, taking effect immediately and looking back 12 months where a full year of consumption data exists. The applicable period is the one in the relevant network's tariff schedule or pricing proposal.
Why it matters
One peak can set the demand charge for the length of the look-back period, so the cost of a single unusual interval is not confined to the month in which it occurred.
Source: CitiPower and Powercor, large business tariffs fact sheet
RCMThe common abbreviation for the Reserve Capacity Mechanism. See Reserve Capacity Mechanism →
The rate at which reactive energy is transferred, measured in volt-amperes reactive and at commercial scale in kilovolt-amperes reactive. The Rules describe it as a necessary component of alternating current electricity, separate from active power, predominantly consumed in creating magnetic fields in motors and transformers and produced by plant such as alternating current generators, capacitors and synchronous condensers.
Why it matters
It does no work at the site, but it adds to the apparent power the network has to carry, which is why it reaches the bill through a demand charge measured in kilovolt-amperes or through an excess reactive charge. Supplying it locally from capacitors is the mechanism power factor correction uses.
Source: National Electricity Rules, Chapter 10 (glossary), definitions of reactive power and reactive energy, current rules
A numeric code on a reading in a metering data file giving the reason it was substituted or estimated. The codes name causes such as a meter change, inaccessible premises, an obstructed meter and unsafe conditions, and are listed in an appendix to the Meter Data File Format Specification. A reason code is mandatory where the quality flag records substituted or finally substituted data, and one code applies across the readings a record covers.
Note: One code reserves the reason for free text, and where it is used a description must accompany it.
Why it matters
It states why the meter did not supply a figure, which separates a one-off access problem from a condition at the site that will recur at every read until work is done.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, reason codes appendix
Varying a dispatch bid after it has been submitted. Under the National Electricity Rules the price for each price band is firm and cannot be changed in any circumstances, so a rebid varies quantities instead: available capacity, daily energy constraints, dispatch inflexibilities and ramp rates. A brief, verifiable and specific reason, and the time of the event relied on, must be given to AEMO at the same time as the rebid.
Why it matters
Capacity can move between price bands close to dispatch while the prices themselves cannot, so a spot price can move within an interval because of how much capacity was offered at each band.
Source: National Electricity Rules, clause 3.8.22, current rules
RECThe common abbreviation for renewable energy certificate. See Renewable energy certificate →
A pipeline service specified as a reference service in a gas access arrangement, consistent with the AER's decision on the service provider's reference service proposal. An access arrangement must describe all the pipeline services the provider can reasonably provide on the pipeline and specify at least one of them as a reference service.
Note: One pipeline service is treated as distinct from another having regard to the service type, such as forward haul, backhaul, connection, park and loan, to its priority relative to other services of the same type, and to the receipt and delivery points. Services on the pipeline that are not reference services are negotiated.
Why it matters
A reference service carries a published tariff and published terms while anything outside the reference services is priced by negotiation, so whether a site's requirement fits a reference service decides whether there is a published rate to compare an offer against.
Source: National Gas Rules, rules 47A and 48, current rules
The tariff specified in a gas access arrangement for a reference service. The arrangement must state, for each reference service, the reference tariff and the other terms and conditions on which that service will be provided.
Note: Reference tariffs move during the access arrangement period through the variation mechanism set in the arrangement and approved by the AER. Which reference tariff applies to a site follows the network's classification of its delivery point, and a reclassification changes the applicable tariff.
Why it matters
It is the published rate sitting behind the network component of a gas bill, so that component can be checked against the approved tariff for the reference service the site actually takes.
Source: National Gas Rules, rules 48 and 97, current rules; Australian Gas Networks, Victoria and Albury access arrangement 2023-28.pdf)
The spot price at a region's regional reference node, which is the single spot price for that National Electricity Market region. The reference node itself is a location on a transmission or distribution network determined for each region by the AEMC.
Why it matters
It is one price for a whole region, so wholesale exposure is measured at the regional node rather than at a site's own connection point, and the difference between the two is accounted for separately through loss factors.
Source: National Electricity Rules, Chapter 10 glossary, current rules
The identifier of an individual data source obtained from a meter, carried both in metering data files and in MSATS standing data. A single meter may provide several, and in some cases more than one meter is summated to form a single register ID.
Note: It is not populated in every file. The specification requires it for manually read interval metering data and when historical data is provided, and does not require it for the higher metering installation types.
Why it matters
Consumption, its unit of measure and its multiplier are all held against the register rather than the meter, so a site's total is the sum across its registers and a figure quoted for one register is not the site's consumption.
Source: AEMO, Standing Data for MSATS, register-level standing data; AEMO, Meter Data File Format Specification NEM12 & NEM13, NMI data details and basic meter data records
An exemption that applies only once the seller has registered with the regulator. Commercial embedded networks beginning to sell after 31 December 2025 fall into this class rather than the deemed class.
Why it matters
Selling cannot begin until the registration is done, so a new commercial embedded network has a step to clear before it can bill occupants, and commercial networks that started selling either side of that date sit in different classes.
See also
Source: AER, retail exempt selling guideline version 7
REGOThe common abbreviation for Renewable Energy Guarantee of Origin. See Renewable Energy Guarantee of Origin →
For a distribution network service provider, a period of not less than five regulatory years for which the provider is subject to a control mechanism imposed by a distribution determination. For a transmission network service provider, a period of not less than five regulatory years in which a total revenue cap applies under a revenue determination.
Why it matters
Tariff structures are fixed for the length of the period, so within it only price levels move, and a change to the way a network charges arrives only at the start of a new period.
See also
Source: National Electricity Rules, chapter 10 (glossary), current rules
A function conferred on AEMO to maintain reliability of supply and system security by contracting reserves held outside the market. Eligible reserve includes unscheduled load that can be curtailed and restored on request, whether a single industrial load or an aggregation of smaller ones, and unscheduled generation such as standby diesel. AEMO may not enter a reserve contract for a region unless it has declared a low reserve or lack of reserve condition for that region, and not more than 12 months before the reserve is expected to be needed. Reserve already available to the market under another contract or arrangement is not eligible, and the average amount payable per MWh of reserves for a region is not to exceed the estimated average value of customer reliability for that region.
Note: AEMO's assessment criteria include whether the reserve can be activated as a block of not less than 10 MW and held continuously for at least 30 minutes, and whether the plant abstains from bidding into the market.
Why it matters
A business with curtailable load or standby generation can be paid for availability, pre-activation, usage and early termination under a reserve contract, provided that capacity is not committed elsewhere in the market. For every other buyer it is a cost, because AEMO's contracting costs are met by fees imposed on the market participants that buy energy and reach the buyer through its retailer.
Source: AEMO, Reliability and Emergency Reserve Trader (RERT)
The AEMC's specialist panel, established under section 38 of the National Electricity Law, which monitors, reviews and reports on the safety, security and reliability of the national electricity system and advises the AEMC when asked. It determines standards and some guidelines used by AEMO and market participants, reviews the reliability standard and the market price settings, and publishes an Annual Market Performance Review under clause 8.8.3 of the National Electricity Rules.
Why it matters
The settings a buyer's spot exposure runs into, including the market price cap and the cumulative price threshold, are reviewed here before the AEMC changes them, so they move at review intervals and not continuously. The panel's remit is the national market, so none of its work reaches a Western Australian or Northern Territory site.
See also
Source: AEMC, Reliability Panel
The level of supply reliability the National Electricity Market is planned to meet: expected unserved energy of no more than 0.002% of the total energy demanded in a region in a financial year, set by clause 3.9.3C(a) of the National Electricity Rules. Unserved energy is demand that cannot be supplied because generation, demand response or network capability is insufficient.
Note: The standard and the market price settings are reviewed periodically by the AEMC's Reliability Panel, so the figure is set for defined periods rather than fixed indefinitely.
Why it matters
It is a planning standard about whether a region has enough generation and network capability, so meeting it still allows some unserved energy, and it says nothing about the local faults behind most interruptions at a single site.
Source: AEMO, ESOO and reliability forecast methodology
The collective term for the tradeable certificates created under the Renewable Energy Target: large-scale generation certificates and small-scale technology certificates. Each represents one megawatt hour of renewable electricity generated or displaced, and certificates are created, transferred and surrendered through the REC Registry.
Note: Outside Australia the abbreviation refers to energy attribute certificates generally, which the Greenhouse Gas Protocol treats as contractual instruments for market-based scope 2 accounting. The two senses overlap but the Australian instruments are defined by the Renewable Energy (Electricity) Act 2000.
Why it matters
The term covers two instruments created and priced separately, and overseas it is used for energy attribute certificates generally, so a reference to renewable energy certificates in a contract or a report does not by itself say which instrument is involved.
See also
Source: Clean Energy Regulator, glossary
A Clean Energy Regulator certification scheme for renewable electricity. Each certificate equals one megawatt hour of renewable electricity generated or dispatched, states the electricity's source and when it was generated or dispatched, and can be transferred or retired as evidence of renewable electricity use. Owners and operators of renewable generation facilities and energy storage facilities, including aggregated systems, can apply to participate.
Note: The scheme's formal name is the Renewable Electricity Guarantee of Origin, one branch of the Guarantee of Origin Scheme established by the Future Made in Australia (Guarantee of Origin) Act 2024. It is separate from the Renewable Energy Target: a facility may register in both, but the same electricity cannot create both a large-scale generation certificate and a REGO certificate.
Why it matters
The Renewable Energy Target ends in 2030 and REGO continues beyond it, so the instrument behind a long-dated renewable electricity claim changes partway through the decade.
See also
Source: Clean Energy Regulator, what is the Renewable Electricity Guarantee of Origin
An Australian Government scheme that requires liable entities, generally electricity retailers and large wholesale buyers, to surrender renewable energy certificates each year or pay a shortfall charge. It has two parts: the Large-scale Renewable Energy Target, under which accredited power stations create large-scale generation certificates, and the Small-scale Renewable Energy Scheme, under which owners of eligible small systems create small-scale technology certificates. The scheme runs to 2030.
Why it matters
The liable entities are retailers and large wholesale buyers rather than the sites they supply, so the cost of the obligation reaches a business through the environmental component of a retail contract, and that component belongs to a scheme with a stated end date.
See also
Source: Clean Energy Regulator, Renewable Energy Target
An area designated for coordinated development of generation, storage and the transmission needed to connect them. AEMO identifies zones in the Integrated System Plan. In New South Wales a zone is the geographic area together with the infrastructure named in a declaration the Minister makes under section 19 of the Electricity Infrastructure Investment Act 2020, and a further declaration under section 24 sets an access scheme governing which generation and storage projects may use the new network infrastructure, with access fees paid by connecting projects funding community benefit programmes.
Why it matters
The network infrastructure built inside a zone is recovered through network charges, and in New South Wales through the Electricity Infrastructure Fund, so the cost reaches a buyer whether or not any of its sites sit inside a zone. Which zones exist, and on what terms, is set jurisdiction by jurisdiction.
See also
Source: Electricity Infrastructure Investment Act 2020 (NSW), sections 19 and 24; EnergyCo NSW, guidelines for access scheme declarations, April 2024
A certificate created under the GreenPower Renewable Gas Certification, which independently verifies the attributes of renewable gas and tracks their ownership through a registry. The functional unit is the supply of 1 GJ of renewable gas measured on higher heating values. Eligible gases are biogas, biomethane, renewable hydrogen and e-methane, whether injected into a gas network or supplied directly to a consumer.
Why it matters
The certificate is transferred and retired separately from the gas, so a buyer on an unchanged gas supply contract can hold the renewable attribute for part or all of its consumption without the physical gas delivered to the site changing.
See also
Source: GreenPower, Renewable Gas Certification Participant Guide
The basis for calculating the number of large-scale generation certificates a liable entity must surrender in a given year. The Minister for Climate Change and Energy determines it on the Clean Energy Regulator's recommendation, drawing on the annual target, estimated wholesale electricity acquisitions, a cumulative adjustment and estimated exemptions. It must be set by 31 March each year, and a default percentage applies if it is not.
Why it matters
The percentage and the prevailing certificate price together set the large-scale component of the environmental cost charged on a bill, which is why that component moves without any change in a site's consumption.
See also
Source: Clean Energy Regulator, renewable power percentage
A request made after the nomination cut-off time to vary a nomination for that gas day, including a variation to a deemed or default day-ahead nomination. On a facility in the capacity auction, a renomination that varies the last day-ahead nomination by more than 10 per cent is a material renomination, and the user must make a contemporaneous record of the circumstances, its verifiable and specific reasons, and the timing, kept for five years.
Why it matters
A renomination is a request rather than an entitlement, and the operator may decline it or schedule less than the quantity asked for. Where the record-keeping obligation applies, the AER may require the user to substantiate the reason for it.
Source: National Gas Rules, Part 24, rule 593, and Part 25, rules 651 and 666, current rules
Industry usage
A document inviting suppliers to price a defined scope, where the requirement is already specified and the main variable is commercial.
The phrase does not appear in the Commonwealth Procurement Rules, which use request for quote for the same idea. It is commercial convention.
Why it matters
Because the document fixes the requirement and leaves price as the variable, an incompletely specified scope shows up as a price difference rather than as a different proposal. Responses are only comparable to the extent every supplier was given the same scope.
See also
Industry usage
A document inviting suppliers to propose how they would meet a requirement, usually covering approach and commercial terms as well as price.
The Commonwealth Procurement Rules name a request for proposal as one form an approach to market may take, alongside a request for tender, a request for quote, a request for expression of interest and a request for information, but do not define the differences between them. The distinction that carries weight in the rules is open against limited tender, not the label on the document.
Why it matters
The label on the document sets no obligations by itself. What a supplier is asked for, and what a response commits them to, comes from the document's own terms, and under the Commonwealth rules the distinction that changes a buyer's obligations is open against limited tender.
See also
Source: Department of Finance, Commonwealth Procurement Rules, appendix B
Industry usage
A procurement document inviting suppliers to submit binding offers against a defined scope, specification and set of conditions. In energy procurement the term is used interchangeably with request for pricing, and what distinguishes the two in practice is whether the offers returned are binding.
Why it matters
A binding offer is made against the document as issued, so the scope, specification and conditions in it are what a supplier is bound to, and anything omitted from them forms no part of the offer.
RERTThe common abbreviation for the Reliability and Emergency Reserve Trader. See Reliability and Emergency Reserve Trader →
Western Australia's scheme for securing enough generation and demand-side capacity to meet forecast peak demand in the South West Interconnected System, set out in Chapter 4 of the Electricity System and Market Rules. AEMO sets a Reserve Capacity Requirement, certifies and assigns capacity to facilities as Capacity Credits, and pays for them at the Reserve Capacity Price. Each Reserve Capacity Cycle runs over four successive calendar years and relates to the capacity required between 8.00 am on 1 October of year three and 8.00 am on 1 October of year four.
Current status: The Coordinator of Energy is reviewing the mechanism in three stages. Stage one covered the definition of reliability, the capacity required, the planning criterion, the capacity products, the methods for assigning certified reserve capacity and the benchmark price. Stage two covered the consequences for the Individual Reserve Capacity Requirement, demand side programmes, outage scheduling and refunds. Stage three is to deliver detailed design as proposed rule amendments.
Why it matters
It is a cost no eastern states site carries, funded by Western Australian loads in proportion to their Individual Reserve Capacity Requirement. Because capacity is procured on a four-year cycle, the capacity a site funds in a given year was certified and priced before that year began.
See also
Source: Electricity System and Market Rules (WA), chapter 4, current rules; Government of Western Australia, Reserve Capacity Mechanism Review
The emission factor used in the market-based method for electricity consumption not covered by a qualifying contractual instrument. It represents all unclaimed energy and emissions, and is formulated by removing contractual claims data from energy production data.
Note: The factors that apply for the market-based method in Australia sit in the National Greenhouse and Energy Reporting (Measurement) Determination and are reproduced in the National Greenhouse Accounts Factors, which also carries a jurisdictional residual power percentage for the Australian Capital Territory.
Why it matters
Under the market-based method, consumption with no qualifying instrument behind it is reported at this factor instead of the grid average used in the location-based method, so the same unclaimed electricity produces two different figures.
See also
Source: Greenhouse Gas Protocol, Scope 2 Guidance
Industry usage
The amount payable to an embedded network operator for infrastructure when an agreement ends or the site changes operator, usually calculated under a formula in the services deed.
There is no statutory definition, no standard formula, and no regulated default. The deed governs.
Why it matters
This figure decides whether a site can realistically change operator, and it is the term most often disputed at the end of an embedded network arrangement.
See also
RETThe common abbreviation for Renewable Energy Target. See Renewable Energy Target →
The component of an energy price covering the retailer's costs of acquiring and serving customers, separate from its margin.
Why it matters
It is counted separately from margin, so the two together describe the retailer's own share of a price, and a figure quoted for one says nothing about the level of the other.
See also
Source: AER, annual retail markets report 2024-25
Permission to sell energy without a retailer authorisation. Exemptions fall into three classes: deemed, which apply automatically; registrable, which must be registered with the regulator; and individual, which must be applied for.
Why it matters
Which class an arrangement falls into decides whether anything has to reach the regulator before selling begins. A deemed exemption is not registered, so there is no regulator record of the seller for anyone at the site to look up.
Source: AER, retail exempt selling guideline, appendix A
The component of an energy price representing the retailer's return. The regulator describes it as "a return to retailers reflecting the risk of selling electricity".
Published benchmarks exist only for small customer instruments: the AER allows 6% of total costs in the Default Market Offer, and the ESC 5% in the Victorian Default Offer. Neither sets or caps the margin in a negotiated commercial contract.
Why it matters
The published percentages belong to regulated small customer instruments, so they are not a reference point for a negotiated commercial agreement, where margin is one of the terms being agreed rather than a figure set externally.
Source: AER, Default market offer prices 2026-27 final determination
A structure in which a buyer's retailer holds the agreement with the generation project, and the buyer pays for the project's output and certificates through its retail contract. The buyer is not a party to the agreement between retailer and project. The contract states a price for the project's output and a price or prices for electricity the retailer supplies when the project is not generating.
Why it matters
The counterparty is the retailer, so the buyer holds no obligation against the project and the project's performance reaches it through the retailer's pricing model instead.
Source: Business Renewables Centre Australia, Corporate Renewable Power Purchase Agreements in Australia
The arrangement under which customers of a failed retailer are transferred automatically to a designated replacement retailer. A transferred small customer goes onto the replacement retailer's standard retail contract at its standing offer prices. A transferred large customer goes onto terms the replacement retailer publishes, which must be fair and reasonable, with no price cap.
Why it matters
A large customer with sites in several distribution areas can be transferred to several different retailers at once, and a customer who has nominated a replacement retailer with AEMO in advance can be transferred to that one instead.
See also
Source: National Energy Retail Law, sections 145 and 146; AER, 2026 review of the Retailer of Last Resort guidelines and plan
A National Electricity Market obligation requiring liable entities to hold contracts covering their share of forecast peak demand when a reliability gap is forecast in a participating region. If AEMO's reliability forecast identifies a gap three years out, it asks the AER to issue a T-3 reliability instrument for that region. If the gap is still reported one year out, a T-1 instrument sets a contract position day by which liable entities must hold a sufficient net contract position, and a reporting day at least two months later. Large energy users can apply to opt in and become liable entities themselves, with applications closing 18 months from the date of the T-3 instrument. A Market Customer or Integrated Resource Provider whose aggregate consumption in the region is 10 GWh a year or less is not a liable entity for that region.
Current status: The final report of the National Electricity Market wholesale market settings review, released in December 2025, recommended that the obligation be phased out following implementation of an Electricity Services Entry Mechanism and a Market Making Obligation. Energy Ministers agreed to the reforms in principle in December 2025 and the Commonwealth department is considering them. The AER decided not to update its interim guidelines following the final report.
Why it matters
A business that opts in takes on a liable entity's contracting, reporting and penalty obligations in place of its retailer, including exposure to procurer of last resort costs of up to $100 million. A business that does not opt in meets the obligation only through whatever its retailer prices into a contract.
See also
Source: AER, are you a liable entity, August 2024; AER, update to interim Retailer Reliability Obligation guidelines
REZThe common abbreviation for a Renewable Energy Zone. See Renewable Energy Zone →
RGGOThe common abbreviation for a renewable gas guarantee of origin. See Renewable gas guarantee of origin →
Rollover rateAnother name for an out-of-contract rate. See Out-of-contract rate →
RoLRThe common abbreviation for retailer of last resort. See Retailer of last resort →
RROThe common abbreviation for the Retailer Reliability Obligation. See Retailer Reliability Obligation →
RRPThe common abbreviation for regional reference price. See Regional reference price →
Industry usage
The period after a contract expires or terminates during which the supplier keeps selling energy on the expired contract's terms, until another retailer becomes financially responsible for the connection points or the buyer enters a new contract. Energy and environmental charges during the period are usually calculated at a default rate rather than at the rate that just expired.
Why it matters
The clause closes any gap in supply and prices it at the same time, so a transfer that slips by a month puts that month's volume on the default rate.
S
The scheme limiting greenhouse gas emissions from Australia's largest industrial facilities. It covers facilities whose covered emissions, generally scope 1, exceed 100,000 tonnes of carbon dioxide equivalent in a year, across sectors including mining, oil and gas production, manufacturing, transport and waste. Each facility has a legislated baseline that declines over time, and a responsible emitter whose net emissions exceed the baseline must surrender Australian carbon credit units or safeguard mechanism credit units, or obtain a flexibility measure, before the 1 April compliance deadline. A facility below its baseline may earn safeguard mechanism credit units.
Note: Covered facilities also report under the National Greenhouse and Energy Reporting scheme, which is the measurement and reporting layer beneath the mechanism.
Why it matters
Coverage turns on a facility's own covered emissions, generally scope 1 and above the stated threshold, so the electricity a business buys for its sites does not by itself bring it within the mechanism.
See also
Source: Clean Energy Regulator, Safeguard Mechanism
Direct greenhouse gas emissions from sources an organisation owns or controls, such as fuel burned on site.
Why it matters
Gas burned at a site counts here while the electricity it buys does not, so one energy bill splits across two scopes. Electrifying a gas-fired process moves those emissions from scope 1 to scope 2 rather than removing them from the inventory.
Source: Greenhouse Gas Protocol; Australian factors published by DCCEEW in the National Greenhouse Accounts Factors
Indirect emissions from electricity, heat or steam an organisation buys and consumes. They can be calculated on a location-based method, using the average emissions intensity of the grid supplying the site, or on a market-based method, which reflects the contractual instruments the organisation has bought.
Why it matters
For most businesses electricity is the largest line in the emissions inventory, and the two methods can produce different numbers for the same site.
Source: Greenhouse Gas Protocol Scope 2 Guidance; DCCEEW, National Greenhouse Accounts Factors 2026
Indirect emissions in an organisation's value chain that are not scope 2, including purchased goods, transport and the extraction and distribution of fuels.
Why it matters
The upstream emissions of the fuels and electricity a site buys fall here rather than in scope 1 or 2, so an energy footprint is not complete at scope 2. The figures are built from data held by suppliers and other parties, so they move as that data changes rather than as the site does.
Source: Greenhouse Gas Protocol
Money lodged with a retailer and held against the buyer's obligations, returnable once the contract ends and all amounts owing are paid. For small customers the Retail Rules cap the amount at 37.5% of estimated bills over twelve months, require interest at the bank bill rate accruing daily, limit what the deposit may be applied to, and set when it must be repaid.
Note: Those provisions attach to small customer contracts. A large customer's deposit is governed by the agreement, which commonly provides that no interest is payable on cash held, that the retailer may draw on the deposit at any time to satisfy an outstanding obligation and then require it to be topped back up, and that the costs of providing it sit with the buyer.
Why it matters
Cash lodged as security is unavailable to the business for the whole term and, under large customer drafting, usually earns nothing while the retailer holds it.
Source: National Energy Retail Rules, rules 40 to 45, current rules
Industry usage
Market shorthand for the electrical separation of a National Electricity Market region, or part of one, from the rest of the interconnected system, usually through the loss of an interconnector. AEMO reports these as power system operating incidents and classifies the triggering event as credible or non-credible. A separated region has to balance its own supply and demand until it is reconnected.
Why it matters
A separated region's spot price is set from the generation and demand inside it alone, so the price at a site there can move sharply while prices in other regions do not. Separation also removes the imported supply the region was relying on, which puts continuity of supply at the site in question alongside its price.
Source: AEMO, Queensland to South Australia separation, 25 August 2018, incident report
The technical rules governing connection of an electrical installation to a distribution network in a given jurisdiction, published by the network businesses or by the responsible state body. They set minimum requirements for services, service equipment, switchboards and the point of connection, define the connection point for the purposes of the state's electricity legislation, and sit alongside the national wiring standard rather than replacing it. Each state and territory has its own set.
Note: Metering requirements are not uniformly inside them. In New South Wales they sit in a separate metering annexure, which the Rules define as the Metering Installation Requirements, and the body of the Rules covers only limited aspects of distributor-owned type 5 and type 6 installations.
Why it matters
They decide what physical work a new connection, an upgrade or a switchboard alteration requires, and because each jurisdiction publishes its own, the same installation design can comply in one state and not in another.
See also
Source: Service and Installation Rules of New South Wales, sections 1.1, 1.2 and 1.9.26, April 2026 edition
Industry usage
A pre-agreed reduction in what a buyer pays when a supplier does not meet a service level set out in the contract. The amount, the levels that trigger it and any ceiling on the total are fixed in the contract rather than calculated from what the failure cost the buyer.
Why it matters
It is a price adjustment rather than compensation, so the amount is unrelated to the loss, and where the contract makes it the sole remedy for a missed service level, no other claim is available for that failure.
The standard request by which a market participant asks a distribution network or metering party to carry out defined physical work at a site, and receives confirmation of whether the work will be done and then whether it has been. AEMO publishes the process and transaction requirements under clause 7.17.3 of the National Electricity Rules. The types cover supply works such as establishing, altering or abolishing a supply and changing a network tariff, metering works such as meter installation, exchange and reconfiguration, de-energisation and re-energisation, special reads, metering investigations, and a miscellaneous type for work the coded types do not cover.
Note: Requests for network augmentation sit outside the procedure.
Why it matters
No physical work happens at a site until one is raised and accepted, so a meter exchange, a special read or a tariff change runs on the timeframes set in the procedure rather than from the date it was asked for.
Source: AEMO, B2B Procedure: Service Order Process, sections 1.1, 1.4 and 2.1
Industry usage
The agreement between a site owner, developer or owners corporation and an embedded network operator, covering the services provided, responsibilities, metering and billing, infrastructure, the contract period and the exit provisions.
There is no statutory definition and no standard form. What the deed says governs, and no regulated default sits behind it.
Why it matters
The exit provisions, including any residual value payable at the end, are set entirely by this document. They are the most commonly disputed terms in an embedded network arrangement.
The process by which AEMO calculates and reconciles the amounts payable between market participants for electricity traded through the spot market, using metering data for each trading interval and the applicable loss factors.
Why it matters
Settlement runs between AEMO and market participants, so an end-use customer is not a party to it, and what it pays is set by its retail contract even where that contract's terms refer to the same spot outcomes.
See also
Source: National Electricity Rules, chapter 3, current rules
The party holding transportation capacity on a pipeline and nominating gas against it, whether a retailer, a producer or an end user. The Rules use primary shipper for a party to a primary facility agreement with the pipeline operator, and secondary shipper for a party to an operational transportation service agreement, which covers capacity acquired through the capacity auction, bilaterally or through the gas trading exchange. The Gas Bulletin Board uses BB shipper for a person who is, or has a right to be, provided with a service by means of a reportable facility or distribution system.
Why it matters
A business that contracts haulage in its own name becomes the shipper, and takes on the nomination, imbalance and overrun obligations that otherwise sit with its retailer. Registered shippers also carry reporting duties on the Bulletin Board.
Source: National Gas Rules, Part 24, rule 593 (primary and secondary shipper), and Part 18, rule 141 (BB shipper), current rules
AEMO's day-ahead gas balancing markets at the Adelaide, Brisbane and Sydney hubs, each hub sitting between transmission pipelines and a distribution system. Trading began on 1 September 2010. The day-ahead schedule sets each hub's ex ante market price by stacking and matching offers and bids in price order, within a floor of $0 a gigajoule and a cap of $400 a gigajoule, and sets scheduled injections and withdrawals for the gas day. Scheduled sellers are paid the ex ante price and scheduled buyers pay it, and an ex post imbalance price is calculated after the gas day to settle deviations.
Note: The markets operate under Part 20 of the National Gas Rules, separately from Victoria's Declared Wholesale Gas Market. Trades in them sit outside the Gas Market Code's reasonable price provisions.
Why it matters
The wholesale gas reference for a site in Sydney, Adelaide or Brisbane is set at its own hub, so three sites across those cities can face three different wholesale references on the same gas day.
Source: AER, significant price variations in the STTM guideline, version 2, 22 June 2022; National Gas Rules, Part 20, current rules
Industry usage
A charge payable where consumption over a contract year falls below the agreed minimum volume. It is usually set by a stated formula rather than a flat fee, applying the volume gap against the difference between a market reference price and the contracted energy rate, adjusted by a loss factor, and is commonly deemed to be zero where the formula returns a negative amount.
Note: The same phrase names a statutory charge under the Renewable Energy Target, payable by liable entities that do not surrender enough certificates against their liability. That charge and a contractual volume shortfall charge are separate things.
Why it matters
Because the formula prices the gap against the market, the same volume shortfall costs a different amount depending on where prices sit when it is assessed, and can come out at nil. A site closure, an efficiency project or new on-site generation lowers volume and can bring it into effect.
See also
Source: Clean Energy Regulator, liable entities
Industry usage
The reduced set of offers carried forward after an initial evaluation, from which the final selection, a negotiation or a best and final offer round is run.
Why it matters
The final selection is drawn only from this set, so an offer cut at the initial evaluation cannot be chosen later, and the cut is made on the offers as first submitted rather than on any improved in a later round.
The times between peak and off-peak, priced between the two.
Not every network uses one. Ausgrid combined its shoulder and off-peak windows in 2024, while SA Power Networks still publishes separate shoulder prices in its 2026-27 schedule.
Why it matters
A contract quoting three time bands can sit over a network tariff that has only two, and the hours in the retail band need not match the network's. Where a network has merged its shoulder and off-peak windows, consumption that was priced in the middle band moves to the lowest one.
See also
Source: Ausgrid; SA Power Networks tariff price list 2026-27
Industry usage
A drawing that represents an electrical installation with one line per circuit, showing the supply point, switchgear, transformers, metering and major loads rather than every conductor. Network businesses require one with connection and connection alteration applications, and it is the reference document for where metering sits relative to loads and any on-site generation.
Why it matters
Where the metering sits on the diagram determines what the meter at the supply point measures, including whether a given load or any on-site generation falls behind it or is measured separately.
See also
Industry usage
A record listing each supply point in a portfolio, with its identifier, address, network area, tariff, metering type and annual consumption. For electricity the identifier is the NMI; gas uses its own delivery point identifier.
Why it matters
The unit is the supply point rather than the property, so one address with two connections appears as two entries, and electricity and gas at the same site are recorded under different identifiers.
SLDThe common abbreviation for single line diagram. See Single line diagram →
A structure in which a buyer negotiates the agreement with the generation project directly and a retailer then takes that agreement inside a retail supply contract. Offers using it are also described as hybrid.
Why it matters
The commercial terms are settled with the project while delivery and billing sit with the retailer, so the two sets of terms are agreed with different parties and both have to be read together to see what applies.
Source: Business Renewables Centre Australia, Corporate Renewable Power Purchase Agreements in Australia
A contract for a supply of goods or services, or a sale or grant of an interest in land, where at least one party makes it in the course of carrying on a business and satisfies the Australian Consumer Law's employee number or turnover condition. With consumer contracts, it marks out the class of contracts the unfair contract terms regime applies to. The thresholds are set out under Unfair contract terms.
Why it matters
The condition is tested on a party as at the time the contract is made, so a business that grows past it during a term keeps the protection for that contract, and the same business entering a later contract does not carry the protection across to it.
See also
Source: Australian Consumer Law, section 23, in Schedule 2 of the Competition and Consumer Act 2010
A residential customer, or a business customer consuming below the upper consumption threshold. The consumer protection provisions of the National Energy Retail Law apply to small customers.
Why it matters
Classification follows consumption at the premises, not revenue or headcount, so a small business with heavy energy use can sit outside the consumer protections while a larger business with a light site keeps them. The same organisation can be a small customer at one site and not at another.
Source: AER, Retail Exempt Selling Guideline version 7
A certificate created for small-scale renewable installations, including rooftop solar, under the Renewable Energy Target. Certificates are calculated using a deeming period and a zone rating, and are usually assigned to the installer in exchange for a discount at the point of sale. From 1 October 2026 eligibility extends to systems up to 1 MW.
Why it matters
Because the value is taken as a point-of-sale discount, the benefit reaches the buyer through the installed price rather than as a payment, which makes competitive quoting the only way to see it.
Source: Clean Energy Regulator
The basis for calculating the number of small-scale technology certificates a liable entity must surrender in a given year. It is set to match the estimated number of certificates created, adjusted for past over-creation or under-creation, and is determined by the Minister for Climate Change and Energy on the Clean Energy Regulator's recommendation by 31 March each year, with a default percentage if that date is missed.
Why it matters
Because the percentage is set to match the certificates created and corrects for earlier over or under creation, the small-scale component charged on a bill moves with how much small-scale generation was installed across the country rather than with anything at the site.
See also
Source: Clean Energy Regulator, small-scale technology percentage
An electricity meter that records consumption in intervals and can be read remotely. In the National Electricity Rules this is a type 4 metering installation. Under a rule made in November 2024, all remaining type 5 and type 6 meters are to be replaced with smart meters by 1 December 2030.
Why it matters
A smart meter is what makes interval data available without a manual read, which is the precondition for demand analysis, bill validation and accurate tendering.
Source: AEMC, Accelerating smart meter deployment, final rule determination, 28 November 2024.pdf)
Industry usage
A contract in which a single rate applies across the whole term, averaging what would otherwise be stepped rates.
Why it matters
A smoothed rate sits above the first year of the equivalent stepped offer and below its last, so which structure costs less over the term turns on how consumption is spread across the years rather than on the headline figure.
See also
The main interconnected electricity network in the south-west of Western Australia, running from Kalbarri in the north to Albany in the south and Kalgoorlie in the east. It is not connected to the National Electricity Market. Wholesale electricity in the system is traded through the Wholesale Electricity Market, which AEMO operates under the Western Australian rules, and network access is regulated by the Economic Regulation Authority.
Note: Western Australia also has the North West Interconnected System and a number of separate regional systems, which sit outside both the SWIS and the national market.
Why it matters
Because the system is not connected to the national market, wholesale prices and events in the eastern states do not reach a site inside it, so National Electricity Market price benchmarks describe nothing about what that site pays.
See also
Source: Government of Western Australia, South West Interconnected System
Industry usage
The share of an organisation's total spend that is covered by a structured procurement arrangement rather than bought ad hoc, usually stated as a percentage.
Note: There is no standard rule for what counts as managed or what is excluded from total spend, so a figure from one organisation is not comparable with another's.
Why it matters
It measures coverage rather than price, so the figure can rise when spend moves under an arrangement without any change in what is paid for the energy itself.
The wholesale price for electricity determined by AEMO for each dispatch interval in each region of the National Electricity Market.
Why it matters
Exposure to the spot price depends on when a site consumes, because the price is set for every dispatch interval and differs by region. Fixing a retail rate moves that exposure to the retailer rather than removing it from the market, and the transfer is part of what the rate covers.
Source: AEMO
Industry usage
Setting contract end dates across a portfolio so that they fall at different times rather than together, so that no single market price at a single moment sets the cost of the whole portfolio.
Why it matters
The portfolio holds several contracts at different rates at once, so its blended cost moves gradually as each one is renewed, and each renewal covers only part of the total volume.
A contract one party prepares and offers with little or no opportunity for the other to negotiate. Under the Australian Consumer Law a contract alleged to be one is presumed to be a standard form contract unless another party proves otherwise, and a court deciding the question must take into account matters including which party holds most of the bargaining power, whether the contract was prepared before any discussion of the transaction, how many contracts in the same or substantially similar terms that party has made, and whether the other party had an effective opportunity to negotiate.
Why it matters
A negotiated commercial supply agreement and an unnegotiated offer from the same supplier sit on opposite sides of the unfair contract terms regime on this condition alone. An opportunity to negotiate changes that are minor or insubstantial, or to pick a term from a range of options the other party set, does not by itself take a contract out of the category.
Source: Australian Consumer Law, section 27, in Schedule 2 of the Competition and Consumer Act 2010
The contract a designated retailer must offer small customers at its standing offer prices, on terms set by the Retail Rules rather than by negotiation.
Why it matters
Its terms are not negotiable, so price is the only point of difference between one designated retailer's standard retail contract and another's. The duty to offer one runs to small customers, so whether a large customer can reach a standing offer at all depends on the jurisdiction it sits in.
Source: National Energy Retail Law, section 22
Industry usage
A network arrangement under which a site with its own generation pays for network capacity held in reserve, so that supply is available when that generation is not running.
Note: There is no market-wide definition or charge. On the TasNetworks network, where a customer with critical electricity supply needs requires standby capability, the network charges applying to that connection are negotiated between the network and the customer, taking into account the assets and network capacity to be kept in reserve. Where a network offers such an arrangement, the applicable terms are the ones in its AER-published tariff guide or connection terms.
Why it matters
The charge is for capacity the network keeps available rather than for energy delivered, so it continues while the site's own generation is covering its load, and on networks that negotiate it the amount is not readable from a published tariff before the connection is discussed.
See also
Source: TasNetworks, network tariff application guide 2024-2029
A retail contract a designated retailer is obliged to make available to small customers, on published terms and at published prices. The obligation applies to small customers only; there is no equivalent obligation to large customers, except in Queensland where a separate assigned retailer regime applies.
Why it matters
A standing offer is a backstop, not a good deal. For a large customer it is usually not available at all, which is why letting a contract lapse exposes the business to whatever the retailer's terms allow rather than to a regulated fallback.
Source: National Energy Retail Law, sections 22 and 64D, as applied in Queensland: current Act
STCThe common abbreviation for a small-scale technology certificate. See Small-scale technology certificate →
Industry usage
A contract in which the rate changes at set points during the term, usually rising year on year.
Why it matters
The rate in year one is not the average rate across the term, so where the steps rise, a contract quoted on its first year sits below what is paid over the full period.
See also
The fixed price per megawatt hour a contract settles against. Where the spot price exceeds it, the seller pays the buyer the difference; where the spot price sits below it, the buyer pays the seller.
Why it matters
It is set when the contract is struck and does not move with the market afterwards, so over a term of ten years or more the same figure can sit above or below prevailing prices at different points.
Source: AER, State of the energy market 2021, chapter 2; Business Renewables Centre Australia, Renewable Energy Power Purchase Agreements in Queensland
STTMThe common abbreviation for the Short Term Trading Market. See Short Term Trading Market →
Industry usage
Metering data supplied in place of data that is missing or has failed validation, worked out under AEMO's metrology procedure, which sets the substitution types and the order in which they apply.
Note: Substituted data is replaced by actual data once it becomes available, which is a common trigger for an invoice to be cancelled and reissued.
Why it matters
The figures come from a method set in the procedure rather than from the site, so demand or consumption analysis covering a period with substituted data partly reflects the substitution rather than what the site did.
A numbered method AEMO permits for filling a gap in metering data, or for estimating data forward. Each type carries a short descriptor naming its method, among them a like day, an average of like days, a linear interpolation, a previous read and a calculated or SCADA-derived value. The types are grouped by whether the installation has remote acquisition, is manually read, accumulates, or has its data calculated. They are listed in AEMO's metrology procedure, made under clauses 7.16.3 to 7.16.5 of the National Electricity Rules, and the type applied to a reading is recorded in its method flag.
Note: Some types serve both substitution and estimation. Types are added and withdrawn over time, so a type appearing in historical data is not necessarily available for a new substitution.
Why it matters
The type determines how closely a substituted figure can follow what the site actually did, because a value interpolated between two actual reads and a value copied from a comparable day are different claims about the same period.
Source: AEMO, Metrology Procedure Part B, sections 2.2, 2.3 and 2.6
A single arrangement with a retailer covering all of a buyer's electricity in one or more National Electricity Market regions, both the contracted renewable quantity and the balancing power, with a financial power purchase agreement behind it providing the price hedge. Either the retailer or the buyer may be counterparty to that financial agreement.
Why it matters
The whole load sits under one contract, so the renewable quantity and the remainder share a term and an expiry rather than being negotiated and renewed separately.
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements, section 4.2
Supply pointAnother name for a connection point, used in Western Australia and in some distributor documentation. See Connection point →
The act of returning renewable energy certificates or carbon credits to the Clean Energy Regulator, which removes them from the certificate market. Surrender may be mandatory, to comply with a liability or obligation, or voluntary for any reason.
Why it matters
A renewable or carbon claim rests on certificates having been surrendered rather than held, because surrender is what stops the same megawatt hour or tonne being claimed again by someone else.
See also
Source: Clean Energy Regulator, glossary
Industry usage
The flexibility a gas supply agreement gives a buyer to take more or less than the daily contract quantity on a given day, usually expressed as a percentage above and below it.
Why it matters
It sets how far a day's take can move from the baseline before the agreement's limits are exceeded, which is what determines whether a load with strong seasonal or batch variation fits the contracted shape.
SWISThe common abbreviation for the South West Interconnected System. See South West Interconnected System →
The ability of the power system to maintain and control the voltage waveform at a given location, both in steady state operation and following a disturbance. The AEMC describes it more narrowly as a measure of the electrical current that would flow into a fault at a given point in the power system.
Note: The Rules set the requirement in two parts: a minimum three-phase fault level at each system strength node, and a requirement for stable voltage waveforms at connection points so that the inverter-based resources AEMO forecasts can operate without creating, amplifying or reflecting instability. AEMO determines both under clause 5.20C of the Rules and its System Strength Requirements Methodology, made under clause 5.20.6.
Why it matters
It is a property of a location rather than of the grid as a whole, so the same equipment can meet the requirement at one connection point and not at another.
See also
Source: AEMO, System security planning and System Strength Requirements Methodology; AEMC, Energy terminology
T
Industry usage
A term in a gas supply or transportation agreement obliging the buyer or shipper to pay for a minimum quantity in a period whether or not it is taken. Contracts often pair it with make-up rights, allowing gas paid for but not taken to be lifted later.
No regulator definition could be located. This is settled industry usage, and the obligation itself is set entirely by the contract.
Why it matters
A fall in production does not reduce the bill, because the minimum quantity is payable whether or not the gas is taken. Make-up rights change when that gas can be lifted, not whether it has already been paid for.
A class of retail customers for one or more direct control services who are subject to a particular tariff or particular tariffs. A network constitutes its classes, and sets the procedures and policies for assigning customers to tariffs within them, through its tariff structure statement.
Note: Classes are commonly drawn on the nature of the connection, such as low voltage, high voltage or sub-transmission, and on demand or annual consumption above a stated level. Both the classes and the assignment rules belong to the relevant network, so the same site can sit in differently named classes on different networks.
Why it matters
The class determines which tariffs a site is eligible for, so a change in voltage level, recorded demand or annual consumption can move a site onto a different set of charges.
See also
Source: National Electricity Rules, chapter 10 (glossary) and clauses 6.18.3 and 6.18.4, current rules
The gas network tariff family for demand delivery points, charged on maximum hourly quantity rather than on the volume of gas delivered. The Australian Gas Networks Victoria and Albury access arrangement names it as the tariff applying to Demand DPs, and that network's published schedule charges it as annual rates per GJ of MHQ in bands.
Note: The maximum hourly quantity for a demand delivery point on that network is the quantity agreed between the network user and the network from time to time, or, in default of agreement, the quantity the network determines acting reasonably. Tariff D sits in each gas network's own access arrangement, so the bands, the rates and the threshold for reaching it are those of the network serving the site.
Why it matters
The charge follows the hourly quantity the site is entitled to draw, not the gas it uses over the year, so an agreed MHQ set above what the site needs raises the network charge for every month it stands.
Source: Australian Gas Networks, Victoria and Albury access arrangement 2023-28.pdf); Australian Gas Networks, Victoria tariffs 2024-25
Moving a connection point from one network tariff class to another. The distributor decides, against published eligibility criteria, and in some networks only the customer's retailer can lodge the request. Customers have a right to object and to seek review.
Why it matters
A site on an inappropriate tariff can pay more than it needs to for years, and correcting it is a process with evidence requirements rather than a phone call.
Source: Distributor tariff structure statements; SA Power Networks states that requests can only be lodged by the retailer
The statement a distribution network service provider must have approved by the AER, setting out for a regulatory control period its tariff classes and the allocation of customers to them, the procedures and policies for assigning customers to tariffs, the structure of each tariff and its charging parameters, and the approach to setting tariffs. It must be accompanied by an indicative pricing schedule giving, for each tariff, the indicative price level for each regulatory year of the period.
Why it matters
It fixes which tariff classes exist and the rules for assigning customers to tariffs, so whether a site can move to a different network tariff is governed by the approved statement rather than settled site by site.
Source: National Electricity Rules, clause 6.18.1A, current rules; AER, standardised TSS compliance document template
The gas network tariff family for volume delivery points, charged on the quantity of gas delivered. On the Australian Gas Networks Victoria and Albury networks the volume haulage service carries two tariffs, one for residential delivery points and one for non-residential delivery points, and the published schedule groups them under the Tariff V heading with a daily charge and per GJ rates that step down as consumption rises.
Note: A delivery point is a volume delivery point for a period if it is not a demand delivery point, so the volume family is defined by exclusion and has no test of its own. On that network the distributor determines whether gas delivered through a point was used primarily for residential purposes, and its determination binds the network user unless proven incorrect.
Why it matters
Smaller sites in a multi-site gas portfolio sit here while larger ones sit on Tariff D, so one portfolio can be billed on two different bases at once, and a site that grows past the demand threshold moves from one to the other.
Source: Australian Gas Networks, Victoria and Albury access arrangement 2023-28.pdf); Australian Gas Networks, Victoria tariffs 2024-25
A process in which a buyer invites suppliers to submit offers against a defined requirement. Australian government procurement distinguishes an open tender, where the approach to market is published and anyone may respond, from a limited tender, where one or more suppliers are approached directly.
Why it matters
In energy, a tender run across multiple retailers on one set of assumptions is the only way to compare offers that would otherwise use different load assumptions, different treatment of network costs and different contract terms.
Source: Department of Finance, Commonwealth Procurement Rules, appendix B
A unit of energy equal to 1,000 gigajoules, or 1,000,000,000,000 joules. It is used for wholesale gas volumes and in the annual consumption threshold that separates small from large gas customers under the national retail framework.
Conversions: 1 TJ = 1,000 GJ = 1,000,000 MJ = 277,777.8 kWh = 277.7778 MWh.
Why it matters
The gas threshold separating small from large customers is expressed in terajoules while invoices are commonly in megajoules, and a million megajoules make a terajoule, so an annual volume has to be converted before it can be tested against the threshold.
Source: National Measurement Regulations 1999, Schedule 1 (Australian legal units of measurement), current regulations
Industry usage
A short document recording the commercial terms the parties have agreed before the full contract is drafted, covering matters such as price, term, volume and the main conditions. Whether it binds the parties is decided on its wording and on how they have acted on it.
Why it matters
The full contract is drafted from it, so a point left out or left open at this stage is settled in drafting rather than in the negotiation where the commercial positions were traded.
TJThe common abbreviation for terajoule. See Terajoule →
The period for which a spot price is determined and wholesale energy is settled in the National Electricity Market. It has been five minutes since 1 October 2021. Before that it was 30 minutes, and the spot price was the time-weighted average of the six dispatch prices within it.
Note: Rules that still work on a half-hour basis use a separate defined 30 minute period, made up of six consecutive trading intervals.
Why it matters
Consumption is valued at the price of the interval in which it occurs, so two sites using the same total energy across a day can settle at different amounts purely because of when they used it.
Source: National Electricity Rules, chapter 10 glossary, current rules
A person who engages in the activity of owning, controlling or operating a transmission system. Transmission network service providers are registered with AEMO and their revenues are regulated by the AER.
Why it matters
Most sites have no dealings with a transmission network service provider directly; its regulated revenue reaches them inside the distributor's network charges, as the transmission component.
Source: National Electricity Rules, chapter 10 definitions, current rules
Under the Australian Consumer Law, a term that is expressed in reasonably plain language, legible, presented clearly and readily available to any party affected by it. A court deciding whether a term is unfair must take into account the extent to which the term is transparent, and the contract as a whole.
Why it matters
Transparency is one input into the unfairness test rather than a test in its own right, so a term written plainly can still be unfair, and an opaque term is not unfair on that ground alone.
Source: Australian Consumer Law, sections 24(2) and 24(3), in Schedule 2 of the Competition and Consumer Act 2010
Transmission use of system charges, the component of network charges covering the cost of shared transmission services that carry electricity from generators to customers.
The term covers prescribed transmission services only. A negotiated transmission service is still a use-of-system charge but is not TUOS.
Why it matters
The charge recovers the cost of shared transmission across customers rather than pricing one site's use of it, so it reaches a bill whether or not the site has any direct transmission connection. A bill line described as transmission is not necessarily TUOS, because a negotiated transmission service is charged separately.
See also
Source: AER, tariff structure statement decision; AEMC, network use of system charges fact sheet
Type 4 meterThe classification in the National Electricity Rules for an interval meter with remote communication. See Smart meter →
U
The difference between the energy metered as entering a local area and the energy metered as consumed within that local area over a trading interval. AEMO allocates it across the connection points in the local area in proportion to each point's share of adjusted metered energy, and publishes periodic reports on it under the Rules.
Note: Recognised sources include energy theft, inaccurate or failed meters, errors in the estimation of unmetered loads, and errors in metering data.
Why it matters
Under global settlement, unaccounted-for energy is settled by the market participants financially responsible for connection points in the local area rather than absorbed by the distributor, so it sits in the cost base behind the prices those participants offer.
Source: National Electricity Rules, clause 3.15.5B, current rules; AEMO, unaccounted for energy information and reports and the UFE reporting guidelines consultation final report
Industry usage
Large-scale generation certificates bought separately from the electricity they were created against. An agreement that includes both the certificates and the electricity is described as bundled.
Why it matters
The certificates carry no link to where or when a site consumed electricity, so the volume surrendered is what the claim rests on and it can come from generation that never physically supplied the site.
See also
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements, section 4.1
Unbundled pricingAnother name for pass-through pricing. See Pass-through pricing →
A regime under the Australian Consumer Law prohibiting unfair terms in standard form contracts, including those with businesses of fewer than 100 employees or under $10 million annual turnover. It does not apply to terms setting the upfront price or defining the main subject matter.
Why it matters
Most commercial energy agreements are negotiated rather than standard form, and a business above both thresholds falls outside the regime entirely, leaving general contract law.
Source: ACCC, business contracts
The field in a metering data file stating the unit in which a channel is recorded. The permitted values cover active energy, reactive and apparent energy, instantaneous power, volts, amps and power factor, each at watt, kilo and mega scale, and are listed in an appendix to the Meter Data File Format Specification. The same item is held against each register in MSATS standing data.
Why it matters
It carries the scale as well as the quantity, so a channel recorded in megawatt hours and read as kilowatt hours is out by a thousand, and a reactive or apparent channel read as consumption is the wrong quantity altogether.
Source: AEMO, Meter Data File Format Specification NEM12 & NEM13, format and unit of measure appendix; AEMO, Standing Data for MSATS, register-level standing data
Industry usage
The price charged for each unit of energy consumed, expressed in cents per kilowatt hour for electricity and cents per megajoule or dollars per gigajoule for gas. It applies to measured consumption, so the amount payable under it rises and falls with usage.
Note: A unit rate is distinct from a fixed charge, which is payable per day or per billing period whatever the consumption, and from a demand or capacity charge, which is set by the highest rate of draw in a period rather than the volume consumed. A single tariff can carry all three at once, and a quoted unit rate says nothing about the level of the other two.
Why it matters
A change in consumption reaches the invoice through this line and no other, so the saving from using less is bounded by the share of the bill the unit rate accounts for.
Under the Australian Consumer Law, the consideration provided or to be provided for the supply, sale or grant under a contract that is disclosed at or before the time the contract is entered into. It does not include any other consideration that is contingent on an event occurring or not occurring. A term setting it cannot be declared unfair.
Why it matters
Contingent amounts fall outside it, so a charge that depends on an event, such as one triggered by a volume shortfall or an early exit, is not shielded from challenge in the way the disclosed price is.
See also
Source: Australian Consumer Law, sections 26(1)(b) and 26(2), in Schedule 2 of the Competition and Consumer Act 2010
The Northern Territory's independent economic regulator, established under the Utilities Commission Act 2000 and constituted by the Utilities Commissioner and associate commissioners. Section 6 gives it functions including regulating prices for monopoly services, performing licensing functions under the industry Acts, and developing, monitoring and enforcing service standards. It licenses the electricity supply industry under the Electricity Reform Act 2000, and the water supply and sewerage industries.
Note: The National Energy Customer Framework does not apply in the Northern Territory, which has adopted a modified form of chapter 5A of the National Electricity Rules from 1 July 2019. Retail choice in the Territory is limited to larger customers.
Why it matters
Prices for monopoly services at a Northern Territory site, and the licences of the businesses supplying them, are set within the Territory by this body, so neither an AER network determination nor a national retail rule describes the position there.
Source: Utilities Commission, about; Utilities Commission Act 2000 (NT), section 6
V
Industry usage
A charge on an energy invoice for services provided alongside the supply of energy rather than for the energy itself. The term has no regulated definition, and what it covers varies by retailer and by contract.
Note: Because the label is not standardised, the services a charge of this name refers to are identifiable only from the contract or from the invoice itself.
Why it matters
The charge sits outside the regulated and standard charge categories, so a comparison built on energy, network and metering lines does not account for it, and no regulator approves the amount.
VASThe common abbreviation for value-added services charge. See Value-added services charge →
VDOThe common abbreviation for the Victorian Default Offer. See Victorian Default Offer →
VEECThe common abbreviation for Victorian energy efficiency certificate, the tradeable certificate created under the Victorian Energy Upgrades programme. See Victorian Energy Upgrades →
A price cap set by Victoria's Essential Services Commission for electricity sold on standing offers to domestic customers and to small business customers consuming no more than 40 MWh a year. Victoria sits outside the national retail framework and regulates separately.
Why it matters
The Victorian threshold is 40 MWh, far lower than the 100 MWh that applies in the national framework. A Victorian site can be a large customer at a consumption level that would still be a small customer in New South Wales.
Source: ESC, Victorian Default Offer
A Victorian programme that reduces greenhouse gas emissions by giving households and businesses access to discounted energy efficient products and services. Large energy retailers must acquire and surrender Victorian energy efficiency certificates to meet an annual target set in Victorian legislation, and accredited persons who install eligible products in residential or non-residential premises create the certificates, with the number determined by the greenhouse gas savings from the installation or decommissioning. The Essential Services Commission regulates participants and products and administers the programme, and the Department of Energy, Environment and Climate Action develops the Act and regulations.
Note: The discount a customer sees is not fixed by the programme. It varies with the activity and the prevailing certificate price.
Why it matters
Certificates are created by the accredited person who installs the product, so the value reaches a business as a discount at the point of installation in Victorian premises rather than as something claimed back afterwards.
Source: Essential Services Commission, about the Victorian Energy Upgrades program
An aggregation of resources such as decentralised generation, storage and controllable loads, coordinated to deliver services for power system operations and electricity markets.
Why it matters
Participation hands dispatch of the site's battery or controllable load to the aggregator, so the asset can charge or discharge to serve the market at times that do not match the site's own demand pattern.
See also
Source: AEMO, Virtual Power Plant (VPP) Demonstrations
Industry usage
A label for a power purchase agreement settled in cash against the spot price with no electricity delivered under it.
Note: The NSW Guide to Corporate Power Purchase Agreements treats "financial" and "virtual" as alternative names for one contract model, so a party using one label is not describing a different structure from a party using the other.
Why it matters
The same structure reaches buyers under both labels, so offers named differently may differ only in their commercial terms rather than in how they work.
Source: NSW Government, NSW Guide to Corporate Power Purchase Agreements, section 4.2
Industry usage
The range of consumption, above and below the contracted volume, within which a buyer can vary usage without triggering an adjustment.
Why it matters
Consumption outside the band triggers an adjustment, so a change on site such as a closure, an expansion or new on-site generation can carry a contractual consequence even where it lowers the volume taken.
See also
An average spot price in which each interval's price carries a weight set by the volume in that interval rather than counting equally. The AER reports annual and quarterly volume weighted average prices for each National Electricity Market region, weighted against native demand.
Note: What the weighting uses differs between publishers. The AER's native demand measure excludes demand met by rooftop solar systems, so one published figure is comparable only with another calculated on the same basis.
Why it matters
The intervals carrying the most energy carry the most weight, so the figure sits above a simple average of prices wherever consumption was higher in the dearer intervals.
Source: AER, Wholesale electricity market performance report 2026
VPPThe common abbreviation for virtual power plant. See Virtual power plant →
VPPAThe common abbreviation for a virtual power purchase agreement. See Virtual PPA →
VWAPThe common abbreviation for volume weighted average price. See Volume weighted average price →
W
WDRMThe common abbreviation for the wholesale demand response mechanism. See Wholesale demand response mechanism →
Industry usage
An evaluation method that gives each criterion a defined share of the total score, scores each offer against the criteria, and combines the results into a single figure for comparison. Commonwealth guidance says the evaluation methodology adopted should be appropriate to the nature of the procurement, rather than an inflexible rating and weighting approach in which numerical scores are entered into a predetermined formula in place of the evaluation committee's judgement.
Why it matters
The weights determine how much of a price difference a difference in service or capability can offset, and they are fixed when the criteria are published, before any offer has been seen.
Source: Department of Finance, ethics and probity in procurement
A NABERS rating assessing the energy used by a building's office tenancies together with the base building services supplied to office lettable and common spaces.
Why it matters
It reaches both the landlord's services and the tenancies, so producing one requires consumption data for every office tenancy in the building as well as for the central services.
See also
Source: NABERS, The Rules: Energy and Water for Offices, Table 1.1.3
Metering in which the whole of the load current passes through the meter itself, with no instrument transformers between the load and the measuring element. AEMO's metrology procedure treats it as a category distinct from instrument transformer connected metering, with its own verification arrangements for small customer installations.
Note: The current rating of the meter sets the ceiling, so a site whose maximum demand grows beyond that rating has to move to current transformer metering, which is switchboard work rather than a meter swap.
Why it matters
The register records the quantity consumed with no further factor applied, so the reading on the meter can be compared directly against the bill.
See also
Source: AEMO, Metrology Procedure Part A, sections 3.1 and 12.5
The component of an energy price covering the purchase of electricity from the wholesale market and the management of price risk.
Why it matters
It covers the management of price risk as well as the energy itself, so the figure reflects what was paid to contract ahead of a period as much as what energy cost within it.
Source: AER, annual retail markets report 2024-25
The arrangement under which a registered Demand Response Service Provider offers a consumer's reduction in consumption into the wholesale electricity market, is dispatched for it and is settled on it. The reduction is measured against a baseline, being an estimate of what the connection point would have drawn had the unit not been dispatched.
Note: The Rules provide for wholesale demand response without using this name for the mechanism, which comes from the AEMC rule change of that title. A connection point qualifies as a wholesale demand response unit only if, among other requirements, it is not a small customer load, it has a type 1, 2, 3 or 4 metering installation, and the retail customer at the point has consented to the provider using it. AEMO must be satisfied with the baseline methodology and settings before approving the classification.
Why it matters
The eligibility tests attach to the connection point, so whether a site can take part turns on its metering installation type and its customer classification rather than on the size of the reduction it could offer.
See also
Source: National Electricity Rules, clauses 2.1A.4, 2.3.6 and 3.10.5, current rules; AEMC, wholesale demand response mechanism rule change
A structure in which a buyer contracts the generation project directly, separately from its retail electricity agreement. The buyer pays a fixed price per megawatt hour to the project, often with an annual escalation factor, and in exchange receives the revenue from the electricity the project sells into the wholesale market and usually the large-scale generation certificates.
Why it matters
What the buyer receives depends on what the project's output earns in the wholesale market, which varies with the region and the periods the project generates in, and the retail contract still has to cover the site's actual supply.
Source: Business Renewables Centre Australia, Corporate Renewable Power Purchase Agreements in Australia
A measure of gas interchangeability, combining heating value and relative density, used to judge whether one gas will burn correctly in equipment set up for another. Pipeline gas specifications reproducing AS 4564 state a Wobbe index window of 46.0 to 52.0 megajoules per cubic metre, measured for dry gas at standard conditions.
Why it matters
Two gases with the same heating value can sit at different points in the window, so combustion behaviour in tightly tuned burners can change while the gigajoules billed stay the same. The window belongs to the gas specification applying at the injection point, so it is settled by the pipeline or network a site draws from rather than by the supply contract.
Source: Jemena, Queensland Gas Pipeline gas specification, reproducing the AS 4564 limits; National Gas Rules, Part 19, rule 200
Z
A heating value applied by network zone rather than as a single figure across a whole market. AEMO decided in December 2023 to move Victorian retail market consumers to zonal heating values, in the 1 May 2024 release of the Victorian Retail Market Procedures, replacing the single daily state-wide value that had applied to sites not read daily. The change also moved from zones assigned by postcode to zones defined by the custody transfer meters supplying each area.
Why it matters
The heating value applied to a site follows the area it is supplied from, so two sites taking the same volume in different zones are billed different energy quantities.
Source: AEMO, Notice of AEMO decision: Package 3A, zonal heating values and the accompanying retail impact and implementation report
The rating attached to a location's zone under the Small-scale Renewable Energy Scheme, applied with system capacity and the deeming period to calculate how many small-scale technology certificates a system is eligible for. Zones reflect expected system performance and differ between small generation units, air source heat pumps and solar water heaters. The Clean Energy Regulator publishes the postcode to zone tables.
Why it matters
Two identical systems installed in different postcodes earn different numbers of certificates, so the upfront discount available on the same equipment varies by location.
Source: Clean Energy Regulator, calculate small-scale technology certificate entitlements
Industry usage
A substation that takes supply at sub-transmission voltage and steps it down to distribution voltage, feeding the distribution lines that serve an area. Distribution substations further along those lines step the voltage down again to low voltage.
Note: The Rules do not define the term and the voltages differ by network. Input is commonly at 132, 66 or 33 kV and output at 22 or 11 kV, but the levels in use are those of the relevant network.
Why it matters
Charging parameters can be set by reference to the zone substation a site connects through. On the United Energy network, for example, the months in which the incentive demand charge applies depend on whether the site's zone substation peaks in summer or winter.
Source: United Energy, large customer fact sheet
More power to you
Rather we just explained it?