Skip to content

Energy Procurement

What is a utility contract strategy, and what belongs in one?

A renewal offer arrives with an expiry date on it. A utility contract strategy settles the term, the price structure, the risk positions and who signs, before anyone has to decide under the clock.

Cohen Robinson7 min read

When retailers send your energy renewal offer, there’s always an expiry date on it. Before that date, somebody has to settle how long to contract for, which price structure to accept and who signs off.

Most organisations never write those answers down. Every renewal gets worked out from scratch, on somebody else's deadline.

A utility contract strategy is a short written document setting out how your organisation buys electricity, gas and water across every site. It records the decisions, the limits and who makes them, in advance, so the next renewal is executed rather than improvised.

Plenty of organisations have utility contracts. Fewer have a strategy, which is how renewals end up decided by whatever the market happened to be doing the week the notice arrived.

How is a strategy different from a plan or a tender?

It's a decision document. A plan lists activities against dates, and a tender is a single event. A strategy records positions you've already taken: how long you'll contract for, how much price certainty you want and what you'll pay for it. It records which structures you'll accept, and what has to be true before anyone signs.

Three to six pages is normal. A CFO who has never opened a meter data file should be able to read it, and someone other than its author should be able to run the next renewal from it. Otherwise the positions live in one person's head, get re-derived under deadline, and never get audited.

What belongs in one

Seven parts.

The seven parts of a utility contract strategy, with the register of connection points highlighted as the part everything else depends on

1. The register. Every connection point, not every site. One premises can hold more than one National Metering Identifier, so your site count and your connection point count are different numbers, and it's the second one you're billed on. Against each, record the retailer, the end date, annual consumption and the network tariff. Everything else is sized off this list, which is why it comes first, and why it's usually the thing nobody has.

2. Scope. Which utilities, which sites, and what happens at the edges. Tenanted sites, sites inside embedded networks, bottled LPG and water get left out most often, because nobody decided they were in.

3. Decision rules. The contract term you'll take and why. Whether you want a fixed energy rate, a requirement bought progressively across tranches, or costs passed through as incurred. How much of the load may stay open. Your position on renewables and energy efficiency, written as a target to buy to rather than a line item offered to you.

4. Risk positions. What you're protecting against, in order, because the risks pull against each other. Budget certainty argues for a long fixed term, and counterparty exposure argues against putting the whole portfolio with one retailer. Decide which you'd rather carry before anyone asks you to.

If a retailer fails, a large customer transfers onto published terms that must be fair and reasonable but carry no price cap, and a portfolio spread across distribution zones can land with several replacements at once. You can nominate your own replacement with AEMO in advance, and almost nobody does. What happens when a retailer goes under has the sequence.

5. Delegated authority. Who may sign, to what annual contract value, and what has to be in front of them first. Termination belongs here, because a large customer's exit cost is whatever the contract says it is, with none of the limits that protect a small one. A signing limit is worth little if the person holding it has never been shown the exit cost.

6. Data and access. A signed authority to act, scoped to information unless you mean to delegate signing. Without it nobody can pull your metering data, which is reliably where the calendar goes. Then where bills arrive, who checks them against the contract, and what happens when a charge looks wrong.

7. Review cadence. When the strategy is revisited on the calendar, and what triggers a review before then.

Written down, that's a morning's work once the register exists. Carried in somebody's head, it's a different answer every renewal.

Who signs it, and who owns it day to day?

Whoever carries the budget signs it, usually the CFO or finance director. One named person owns it, holds the register, watches the end dates and calls the start of each process.

Those are two different jobs, and the second is where it falls over. Utilities sit across finance, procurement and facilities, so a strategy with no named owner belongs to all three and to none of them. Who should own utilities is worth settling before the document gets written.

How long it should run

Longer than a contract and shorter than a corporate plan. Two to three years, reviewed quarterly against the register.

Review it early when a site is added or closed, when a retailer enters administration, when a network tariff is reassigned, or when a site crosses the large customer threshold. That last one changes the rules you operate under. The upper consumption threshold is 100 MWh a year for electricity and 1 TJ for gas, with some jurisdictions setting a different figure, and the consumer protection part of the National Energy Retail Law applies to retailers and small customers. Other than one division on responsibility for energy consumed, it does not apply to large customers. Above the threshold, the contract is the protection.

What to decide in advance

Everything that gets worse under time pressure.

The same four decisions made in advance against made when a renewal notice arrives, showing time to compare falling from months to days

A small customer on a fixed term contract gets a statutory notice that it's ending, no earlier than 40 and no later than 20 business days out. There's no large-customer equivalent in the national framework, and no regulated price to land on either. "Out-of-contract rate" is industry usage rather than a defined term, and it appears in none of the Retail Law, the Retail Rules or Victoria's Energy Retail Code of Practice. Two organisations described as being out of contract can be paying very different amounts.

Comparability collapses just as fast. How network charges reach your price is at the retailer's discretion, so two offers can be impossible to compare on the energy rate alone. A strategy that states which structure you want turns incomparable quotes into a like-for-like set, before anyone's waiting on you.

What a utility contract strategy does not do

It doesn't run the market process. Setting your positions and going to market are separate jobs, and the second one is utility strategic sourcing. It doesn't replace energy bill validation either: a strategy decides what you should be charged, and validation checks what you were.

What it does do is make the contract carry its weight, and that matters more the larger you get. The unfair contract terms protections reach standard form contracts with businesses under 100 employees or $10 million turnover, and they never reach the price itself. Most commercial supply agreements are negotiated rather than standard form anyway. Past that point there's no backstop behind the document you signed, which is what the strategy is for.

What to gather before you write one

Six inputs to gather before writing a utility contract strategy, with the signed authority to act highlighted as the usual cause of delay

Nothing on that list needs a market view, which is the point. The register, the dates, the data and the authority are assembly work, and they're what a renewal runs out of time for. Doing them while nothing is expiring is procurement readiness, and the cheapest part of the whole exercise.

Talk to us

A utility contract strategy is the document behind utility sourcing, and the register it starts from is usually the thing nobody has. For VMCH we built that picture across 20 sites first, then went to market, and the portfolio came back 22% lower.

If you want to know what your current arrangements commit you to, and what a strategy for them would say, Talk to us. One contact, the full picture, across every state, every territory, and New Zealand.

Frequently asked questions

What is the difference between a utility contract strategy and an energy procurement plan?

The strategy sets the positions: term, structure, risk tolerance, signing authority. The plan sequences the work that follows, site by site and date by date. You can write a plan without a strategy, and most organisations do, which is why the plan changes every time the market moves.

How long should a utility contract strategy be?

Three to six pages. If it runs longer it has absorbed the procurement process, and if it runs shorter it has probably skipped the register.

Who should sign it?

Whoever holds the budget it commits, usually the CFO or finance director, with one named owner underneath who holds the register and calls the start of each process.

Do we need one if we only have a handful of sites?

The register is shorter, not the decisions. A business with four connection points still has to decide its term, its structure, its renewable position and who may sign, and it has less internal resource to improvise those under a deadline, not more.

Does a strategy lock us into one retailer?

No. It records what you'll accept, not who you'll buy from. A strategy that names a retailer has stopped being a strategy.

Newsletter

The energy market, read for you once a month

The Energy Market Update: what moved last month, what it means, and what to do before your next renewal. One email a month, unsubscribe any time.

Step 1 of 2: your email

Next, your name and company. Unsubscribe any time.

We only use your details to respond to you, as set out in our privacy policy.

Where do you stand?

Get a clear read on your energy position.

We'll benchmark what you're paying against the wider market and tell you your options. No cost, no obligation.